Robert and Bonnie Beattie v. James Gerard Chavin and Olde Orleans Construction, Inc
Robert and Bonnie Beattie v. James Gerard Chavin and Olde Orleans Construction, Inc, No. 2026 CW 0846 (La. Ct. App. 1st Cir. Oct. 21, 2026).
Authorities cited
Identified automatically; this list may not be exhaustive.
- 395 So. 3d 296 not in our corpus
- J. Caldarera & Co. v. LA. STADIUM 725 So. 2d 549
Opinion text
STATE OF LOUISIANA
COURT OF APPEAL, FIRST CIRCUIT
ROBERT AND BONNIE BEATTIE NO. 2026 CW 0846
VERSUS
JAMES GERARD CHAUVIN AND
OLDE ORLEANS CONSTRUCTION,
INC. OCTOBER 21, 2026
In Re: James Gerard Chauvin and Olde Orleans Construction,
Inc., applying for supervisory writs, 22nd Judicial
District Court, Parish of St. Tammany, No. 2025-13605.
BEFORE : McCLENDON, C.J., THERIOT, HESTER, MILLER AND GREENE,
JJ.
WRIT GRANTED. The May 20, 2026 judgment denying the
exception of prematurity filed by defendants, James Chauvin and
Olde Orleans, is reversec. The burden of proof is on the
defendant to establish that a valid and enforceable arbitration
agreement exists. See Crosby as Tr. of Aaron Guidry Tr. v.
Crosby Enterprises, LLC, 2023-1338 (La. App. lst Cir. 8/9/24),
395 So.3d 296, 300. If the defendant satisfies its burden of
proof establishing its right to arbitration, the burden then
shifts to plaintiffs to demonstrate they did not consent to
arbitration. Id. Article V of the construction contract between
defendants and plaintiffs was sufficient to mandate the parties
submit their issues to arbitration. The contract provided, “The
request for arbitration shall be sought by both parties within
30 days of written notice of a dispute by either of the
parties.” The reference to arbitration in Article VI further
showed the parties’ intent to arbitrate. See Caldarera & Co. v.
Louisiana Stadium & Exposition Dist., 98-294 (La. App. 5th Cir.
12/16/98), 725 So.2d 549, Therefore, the exception of
prematurity is granted, and plaintiffs’ claims against
defendants are dismissed without prejudice.
PMc
MRT
CHH
HG
Miller, J., dissents and would deny the writ. I would defer
to the trial court’s determination that the language of the
contract was “unclear..ambiguous...[and] internally inconsistent.”