LAMAR CONTRACTORS, LLC NO. 22-CA-212

VERSUS FIFTH CIRCUIT

SRF GROUP CONSULTING, LLC COURT OF APPEAL

STATE OF LOUISIANA

ON APPEAL FROM THE TWENTY-THIRD JUDICIAL DISTRICT COURT
PARISH OF ST. JAMES, STATE OF LOUISIANA
NO. 36,600, DIVISION "E"
HONORABLE ALVIN TURNER, JR., JUDGE PRESIDING

February 01, 2023

JOHN J. MOLAISON, JR.
JUDGE

Panel composed of Judges Robert A. Chaisson,
Stephen J. Windhorst, and John J. Molaison, Jr.

REVERSED; REMANDED
JJM
RAC
SJW

COUNSEL FOR PLAINTIFF/APPELLEE,
LAMAR CONTRACTORS, LLC
Steven B. Loeb
Jacob E. Roussel

COUNSEL FOR DEFENDANT/APPELLANT,
ST. JAMES PARISH
Victor J. Franckiewicz, Jr.

MOLAISON, J.

The appellant, St. James Parish, seeks review of the trial court’s granting of

a partial summary judgment which struck several of its reconventional demands

brought against the appellee, Lamar Contractors, L.L.C. For the reasons that

follow, the trial court’s ruling that granted Lamar’s motion for summary judgment

on the issue of the Parish’s reconventional demands is reversed.

FACTS AND PROCEDURAL HISTORY

The basis of the underlying lawsuit pertains to the construction of a public

recreation building (“the building”)1 owned by, and located within, St. James

Parish (“the Parish”). On July 30, 2013, the Parish entered into a written contract2

with Lamar Contractors, L.L.C. (“Lamar”) to serve as the general contractor for

the project and to construct the building, which was designed by SRF Group

Consulting, L.L.C. (“SRF”). Following a dispute over the design and

specifications for the roof decking, Lamar stopped work on the project. On July

15, 2015, pursuant to the general contract between the parties, Lamar filed a

required “Notice of Termination.” Lamar then filed the underlying lawsuit, which

later named the Parish in an amended petition.3 The Parish filed a reconventional

demand against Lamar on January 19, 2016, alleging that Lamar had performed

defective work and had breached the general contract in unilaterally deciding to

stop work on the building.

Lamar’s motion for a partial summary judgment on the Parish’s

reconventional demands was held on December 6, 2021. In its judgment dated

December 22, 2021, the trial court granted Lamar’s motion for partial summary

1
The record shows that the official name of the project was “St. James Parish District 5 Multi-
Purpose Recreation Building Welcome Park.”
2
The contract used a pre-drafted form with the designation of “Document A101-2007.”
3
Lamar’s original petition and its amended petition have not been made part of the designated
record on appeal.

22-CA-212 1

judgment as to the Parish’s claims for “defective work” as “asserted in Paragraph

36, Subparts (a) through (aa) of the Reconventional Demand,” and “reasserted in

Paragraph 36, Subparts (a) through (z) and (bb) of the Amended Reconventional

Demand.” The judgment also dismissed the Parish’s claim against Lamar for

“stopping work and walking off the job.” This appeal followed.

ASSIGNMENTS OF ERROR

On appeal, the Parish assigns two errors:

1. The trial court committed legal error in misconstruing the
construction contract and applying the Article 15 claims procedure to the
Parish’s reconventional demand without considering that article in context,
and without applying the provisions of the contract as a whole.

2. The trial court committed legal error by granting summary
judgment when material facts remain in dispute.

LAW AND ANALYSIS

Standard of review

Appellate courts review summary judgments de novo, using the same criteria

that govern the trial court’s consideration of whether summary judgment is

appropriate. Vill. Shopping Ctr. P'ship v. Kimble Dev., L.L.C., 18-740 (La. App. 5

Cir. 4/24/19), 271 So.3d 376, 381; Lincoln v. Acadian Plumbing & Drain, LLC,

17-684 (La. App. 5 Cir. 5/16/18), 247 So.3d 205, 209, writ denied, 18-1074 (La.

10/15/18), 253 So.3d 1302. A motion for summary judgment is a procedural device

used to avoid a full-scale trial when there is no genuine issue of material fact, and

is favored and designed to secure the just, speedy, and inexpensive determination

of every action. Id. A motion for summary judgment shall be granted if the motion,

memorandum, and supporting documents show that there is no genuine issue as to

material fact and that the mover is entitled to judgment as a matter of law. La.

C.C.P. art. 966. If only one conclusion could be reached by reasonable persons,

summary judgment is appropriate, as there is no need for a trial on that issue. Id.

22-CA-212 2

First assignment of error

In its motion for partial summary judgment, Lamar argued that the

Parish failed to preserve its reconventional claims in the manner mandated

by the contract under Article 15.4 The relevant provisions that Lamar relied

upon state:

§ 15.1.1 DEFINITION
. . .
A Claim is a written demand or assertion by one of the parties
seeking, as a matter of right, payment of money, or other relief with
respect to the terms of the Contract. The term "Claim" also includes
other disputes and matters in question between the Owner and
Contractor arising out of or relating to the Contract. The responsibility
to substantiate Claims shall rest with the party making the Claim.
Claims must be initiated by written notice. Verbal communications
shall not constitute claims.

§ 15.1.2 NOTICE OF CLAIMS
. . .
Claims by either the Owner or Contractor must be initiated by
written notice to the other party and to the Initial Decision Maker with
a copy sent to the Architect, if the Architect is not serving as the
Initial Decision Maker. Claims by either party must be initiated within
21 days after occurrence of the event giving rise to such Claim or
within 21 days after the claimant first recognizes the condition giving
rise to the Claim, whichever is later.

In its first assignment of error, the Parish contends that the trial court erred in

finding that a failure to follow the procedures in Article 15 of the contract served

as a bar to its reconventional demands.

The interpretation of a contract’s provisions is typically a matter of law that

may properly be decided on a motion for summary judgment. Hall v. Malone, 12-

0264 (La. App. 4 Cir. 11/7/12), 104 So.3d 593, 596. In analyzing contracts, certain

fundamental legal principles apply. According to the rules of construction, the

4
The only specific examples provided in the contract which pertain to notice are: 15.1.4- Claims
for additional cost, and; 15.1.5- Claims for additional time.

22-CA-212 3

responsibility of the judiciary in interpreting contracts is to determine the parties’

common intent. See, La. C.C. art. 2045. Courts begin their analysis of the parties’

common intent by examining the words of the contract itself. See, La. C.C. art.

2046. In ascertaining the common intent, words and phrases in a contract are to be

construed using their plain, ordinary and generally prevailing meaning, unless the

words have acquired a technical meaning, in which case the words must be

ascribed their technical meaning. See, La. C.C. art. 2047.

A contract is to be construed as a whole, and each provision in the contract

must be interpreted in light of the other provisions. One provision of the contract

should not be construed separately at the expense of disregarding other provisions.

See, La. C.C. art. 2050. Neither should a contract be interpreted in an unreasonable

or a strained manner so as to enlarge or to restrict its provisions beyond what is

reasonably contemplated by its terms or so as to achieve an absurd conclusion.

Edwards v. Daugherty, 03-2103 (La. 10/1/04), 883 So.2d 932, 941. Courts lack the

authority to alter the terms of contracts under the guise of contractual interpretation

when its provisions are couched in unambiguous terms. Cadwallader v. Allstate

Insurance Co., 02-1637 (La. 6/27/03), 848 So.2d 577, 580. The rules of contractual

interpretation simply do not authorize a perversion of the words or the exercise of

inventive powers to create an ambiguity where none exists or the making of a new

contract when the terms express with sufficient clarity the parties’ intent. Edwards,

883 So.2d at 941.

Lamar’s obligations created in the July 30, 2013 contract

It is clear from the contract that Lamar’s overall obligation was to supply

any work, labor and materials required to produce a “functionally complete

project.”5 To further this goal, the contract outlines a process for identifying

5
Contract, Article 1, section 1.2.

22-CA-212 4

unsatisfactory work, through the use of a “punch list.”6 The contract states that the

“Architect” is responsible for preparing a punch list to deliver to the owner, which

in this case is the Parish.7 Identification of items on the punch list are not identified

as “claims” in the contract. The final payment to Lamar, as the contractor, is

conditioned upon its obligation to correct work under 12.2.2.8 A one year period

for correction of work is provided to Lamar. 9 The contact provides that the Parish

could terminate the contract if Lamar fails to timely complete the punch list.10

Finally, section 3.20 contract states, in part, that “[t]he Contractor shall be liable to

the Owner for all costs and/or damages that the Owner incurs as result of the

Contractor’s failure to perform the Work…”

The contract is clear on its face that the Parish has the right to redress in the

event that Lamar’s work is deemed unsatisfactory, through the process described

above. The contract also states that a failure by the Parish to use that process does

not result in a waiver of those claims. As provided in section 13.4.2, “[N]o action

or failure to act by the Owner, Architect or Contractor shall constitute a waiver of a

right or duty afforded them under the Contract, nor shall such action or failure to

act constitute approval of or acquiescence in a breach there under, except as may

be specifically agreed in writing.” This would specifically apply to Lamar’s claim

that the Parish waived its right to recover for a defect in Lamar’s workmanship.

We would reach this same conclusion even if we were to find 15.1.2 applicable, as

argued by Lamar. That section also does not specifically state that the Parish

waives legal recourse otherwise provided under the contract11 by failing to give

notice.

6
Contract, Article 3, section 3.4. The term “punch list” is not defined in the contract. In common
usage, we understand the term to mean “[l]ists of jobs that have not been completed by a contractor before
he is due to be paid,” as defined in the Black Law Dictionary 2nd Ed.
7
Contract, Article 5, section 5.1.8.
8
Contract, Article 5, section 5.2.1.
9
Contract, Article 12, section 12.2.2.
10
Contract, Article 14, section 14.2.1.
11
Contract, Section 3.20 correlates to La. C.C. art. 2769, which states:

22-CA-212 5

The Parish’s obligation after Lamar’s termination of the contract

The notice and remediation procedures detailed in the contract are logical in

the context of a continuing construction project. The next question is what, if any,

obligation the Parish had to report defects to Lamar once the contract was

terminated.

When Lamar terminated or ended the project, it also ended any obligations

the Parish had except those which were provided for in the contract, which was to

pay Lamar “for Work properly executed, including reasonable overhead and profit

on that portion of the Work properly executed, installed, performed or completed.”

The alleged defects are relevant, however, to show the Parish’s entitlement to a

potential offset for the remaining payment left to Lamar after its termination of the

contract. The Parish’s only recourse at that time was to assert these claims in

district court, as per the Binding Dispute Resolution clause of 6.2.12

The Parish’s reconventional demands are also permissible under La. C.C.P.

art. 424, which states:

A person who has a right to enforce an obligation also has a
right to use his cause of action as a defense.
Except as otherwise provided herein, a prescribed obligation
arising under Louisiana law may be used as a defense if it is incidental
to, or connected with, the obligation sought to be enforced by the
plaintiff.

Under this article, Louisiana courts have allowed reconventional demands to stand,

even when they otherwise would have been prescribed, as long as they are

incidental to, and directly connected with the obligation sought to be enforced.

If an undertaker fails to do the work he has contracted to do, or if he does not execute it
in the manner and at the time he has agreed to do it, he shall be liable in damages for the losses
that may ensue from his non-compliance with his contract.
12
Contract, Article 6, section 6.2 provides that an optional mediation between the parties is a
precursor to litigation. In its brief, the Parish asserts that prior to the filing of its reconventional demand, all
parties to Lamar’s lawsuit went through mediation and even sought the appointment of a special master to
assist in re-starting construction.

22-CA-212 6

Dixie Bldg. Materials Co., Inc. v. Bob L. Whittington & Associates, Inc., 588 So.2d

78 (La.1991); Hennessey Const. Corp. v. Halpern, 06-1099 (La. App. 4 Cir.

1/31/07), 952 So.2d 739, 741. In the instant case, because Lamar’s main demand

pertains to the construction of a building, we find the Parish’s reconventional

demands regarding defects in the work to be connected.

In conclusion, upon de novo review, and construing the contract as a whole,

we find that the trial court erred as a matter of law in finding that Article 15 could

be used to preclude the Parish’s reconventional demand. We reverse the trial

court’s granting of Lamar’s motion for summary judgment. As noted above, even

if the Parish’s claims for damages were prescribed, La. C.C.P. art. 424 allows them

to use these claims as a reconventional demand.

Because we have granted relief on the Parish’s first assignment of error, we

pretermit discussion on its second assignment as moot.

CONCLUSION

For the foregoing reasons, the trial court’s ruling that granted Lamar’s

motion for summary judgment on the issue of the Parish’s reconventional demands

is reversed. This matter is remanded for further proceedings consistent with this

opinion.

REVERSED; REMANDED

22-CA-212 7

SUSAN M. CHEHARDY CURTIS B. PURSELL

CHIEF JUDGE CLERK OF COURT

SUSAN S. BUCHHOLZ
FREDERICKA H. WICKER
INTERIM CHIEF DEPUTY CLERK
JUDE G. GRAVOIS
MARC E. JOHNSON
ROBERT A. CHAISSON LINDA M. WISEMAN
STEPHEN J. WINDHORST
FIRST DEPUTY CLERK
HANS J. LILJEBERG
JOHN J. MOLAISON, JR. FIFTH CIRCUIT
MELISSA C. LEDET
JUDGES 101 DERBIGNY STREET (70053)
DIRECTOR OF CENTRAL STAFF
POST OFFICE BOX 489
GRETNA, LOUISIANA 70054 (504) 376-1400

(504) 376-1498 FAX
www.fifthcircuit.org

NOTICE OF JUDGMENT AND CERTIFICATE OF DELIVERY
I CERTIFY THAT A COPY OF THE OPINION IN THE BELOW-NUMBERED MATTER HAS BEEN DELIVERED
IN ACCORDANCE WITH UNIFORM RULES - COURT OF APPEAL, RULE 2-16.4 AND 2-16.5 THIS DAY
FEBRUARY 1, 2023 TO THE TRIAL JUDGE, CLERK OF COURT, COUNSEL OF RECORD AND ALL PARTIES
NOT REPRESENTED BY COUNSEL, AS LISTED BELOW:

22-CA-212
E-NOTIFIED
23RD JUDICIAL DISTRICT COURT (CLERK)
HONORABLE ALVIN TURNER, JR. (DISTRICT JUDGE)
STEVEN B. LOEB (APPELLEE) VICTOR J. FRANCKIEWICZ, JR. ELLIOT W. SCHARFENBERG (APPELLEE)
(APPELLANT)

MAILED
DARREN A. PATIN (APPELLEE) KEITH J. BERGERON (APPELLEE) JACOB E. ROUSSEL (APPELLEE)
ATTORNEY AT LAW TERRENCE L. BRENNAN (APPELLEE) ATTORNEY AT LAW
3445 NORTH CAUSEWAY BOULEVARD ATTORNEYS AT LAW POST OFFICE BOX 3197
SUITE 800 755 MAGAZINE STREET BATON ROUGE, LA 70821
METAIRIE, LA 70002 NEW ORLEANS, LA 70130