53,667-CA Precedential Affirmed Processed

David C. McDaniel, Jr. v. R.J.'s Transportation, L.L.C., Comstock Oil & Gas- Louisiana, L.L.C., Baker Hughes Oilfield Operations, Inc.

Louisiana Court of Appeal, Second Circuit · Filed January 13, 2021

Authorities cited

Identified automatically; this list may not be exhaustive.

Opinion text

Judgment rendered January 13, 2021.
Application for rehearing may be filed
within the delay allowed by Art. 2166,
La. C.C.P.

No. 53,667-CA

COURT OF APPEAL
SECOND CIRCUIT
STATE OF LOUISIANA

*****

DAVID C. MCDANIEL, JR. Plaintiff-Appellant

versus

R.J.’S TRANSPORTATION, Defendants-Appellees
L.L.C., COMSTOCK OIL & GAS-
LOUISIANA, L.L.C., BAKER
HUGHES OILFIELD
OPERATIONS, INC.

*****

Appealed from the
Forty-Second Judicial District Court for the
Parish of Desoto, Louisiana
Trial Court No. 77,122

Honorable Amy Burford-McCartney, Judge

*****

H. LYN LAWRENCE, JR. Counsel for Appellant
ANDREW C. JACOBS

VOORHIES & LABBE Counsel for Appellee,
By: Cyd Sheree Page R.J.’s Transportation, L.L.C.

LISKOW & LEWIS Counsel for Appellee,
By: Paul M. Adkins Comstock Oil & Gas-
Louisiana, L.L.C.

GALLOWAY, JOHNSON, TOMPKINS, Counsel for Appellee,
BURR & SMITH Baker Hughes Oil Field
By: Timothy William Hassinger Operations, Inc.

MELCHIODE MARKS KINGS, L.L.C. Counsel for Appellee,
By: Jennifer L. Simmons Zurich American Insurance
Edward S. Voelker IV Company

KEAN MILLER, LLP Counsel for Appellee,
By: Scott Louis Zimmer Chaps Oilfield Services, L.L.C.

MAX C. TUEPKER, PC Pro hac vice Counsel for
By: Max Charles Tuepker Appellee,
Chaps Oilfield Services, L.L.C.

*****

Before MOORE, THOMPSON, and BODDIE (Pro Tempore), JJ.

THOMPSON, J.

This appeal arises from the trial court’s judgment granting a motion

for summary judgment in favor of Comstock Oil & Gas-Louisiana, LLC. At

issue in this personal injury action is the determination of independent

contractor status of Chaps Oilfield Services, LLC, and whether operational

control of activities at a well site were retained or exercised by Comstock

Oil & Gas-Louisiana, LLC. For the reasons more fully detailed below, we

affirm the judgment of the trial court.

FACTUAL AND PROCEDURAL HISTORY

This case involves a personal injury action arising from a hydrochloric

acid spill at the Harrison 30-19 HC No. 1-Alt well, a DeSoto Parish natural

gas well location owned and operated by Comstock Oil & Gas-Louisiana,

LLC (“Comstock”). Comstock hired Chaps Oilfield Services, LLC

(“Chaps”), as the on-site “company man” to be responsible for the

supervision of the completion operations. Comstock and Chaps executed a

Master Service Agreement (hereinafter, the “Chaps MSA”). The Chaps

MSA provides that Chaps is an independent contractor free and clear of any

dominion or control by Comstock in the manner in which its work is to be

performed. The Chaps MSA requires Chaps to furnish its own tools,

supplies, or materials, and allows Chaps to determine the manner in which

its work is performed.

Comstock also hired Baker Hughes Oilfield Operations, Inc. (“Baker

Hughes”) to perform the ongoing fracking operations to complete the well.

Baker Hughes was hired to be responsible for all aspects of the fracking

2

operation and used its own employees to conduct those operations.

Comstock also executed a Master Service Agreement with Baker Hughes,

the terms of which are not currently before the court.

On June 27 or 28, 2015, R.J.’s Transportation, LLC (“R.J.’s”)

delivered a requested tanker load of liquid hydrochloric acid to the well site.

Baker Hughes ordered the acid from Univar USA, Inc., which in turn hired

R.J.’s to deliver the acid to the well site. Plaintiff, David C. McDaniel, Jr.

(“McDaniel”), was employed as a vacuum truck driver for Target Oilfield

Services, LLC (“Target”).

McDaniel alleges that the R.J.’s driver and a Baker Hughes employee

were offloading the acid from the tanker into a stationary tank when a

substantial amount of the liquid acid spilled, for reasons still uncertain, onto

the ground. McDaniel, who was on standby at another location on the site,

claims that a Baker Hughes employee directed him to the spill area in his

truck. McDaniel testified that the Baker Hughes employee placed the

vacuum hose some distance away, where McDaniel could not initially see or

smell the acid, and instructed McDaniel to engage the vacuum mechanism.

After learning that the hose was resting in acid, McDaniel shut off the

vacuum mechanism.

McDaniel claims that the truck’s tank valve was damaged such that

the acid already vacuumed would leak out unless the truck’s engine was

running and the vacuum mechanism was engaged. He states that one of the

Chaps company men told him that he needed to keep the vacuum

mechanism engaged to prevent the acid already in his vacuum truck’s tank

from leaking back out on the ground. This required him to be in and around

3

his truck and in close proximity to the acid spill on site. McDaniel alleges

that he inhaled the fumes from the acid from about 8:30 p.m. until nearly the

end of his shift at 6:00 a.m. the following morning, during which he

maintained the vacuum action as instructed by and at the insistence of the

Chaps company man on location.

McDaniel claims that the inhalation of the fumes caused him serious

injury and that the defendants are at fault for the injuries, due to their actions

of negligently causing the acid spill, failing to warn him of the acid spill,

directing him to the area of the spill without warning, instructing him to

initiate the vacuum process of his truck without informing him of the nature

of the spill, its composition, and directing/causing him to stay near his

vehicle within the spill area causing continued exposure to the harmful

fumes.

On February 2, 2016, McDaniel filed suit against R.J.’s, Comstock,

and Baker Hughes. McDaniel later amended his petition to include Chaps.

On October 10, 2019, Comstock filed a motion for summary judgment, in

which the company argued that it was not liable for the actions of Baker

Hughes or Chaps because they were independent contractors and directed

the court to the existing Master Service Agreements. The trial court granted

Comstock’s motion for summary judgment, dismissing the company with

prejudice from the proceeding. This appeal by McDaniel followed.

PLAINTIFF’S ASSIGNMENT OF ERROR

McDaniel argues that the district court erred in granting summary

judgment in favor of Comstock by finding that no genuine issue of material

fact exists as to whether Chaps was an independent contractor in relation to

4

Comstock; and thus, Comstock was not liable for any acts or omissions of

Chaps.

SUMMARY JUDGMENT

Summary judgment procedure is designed to secure the just, speedy

and inexpensive determination of every action except those disallowed by

law. La. C.C.P. art. 966(A)(2); Klein v. Cisco-Eagle, Inc., 37,398 (La. App.

2 Cir. 09/24/03), 855 So. 2d 844. After an opportunity for adequate

discovery, a motion for summary judgment shall be granted if the motion,

memorandum, and supporting documents show that there is no genuine issue

as to material fact and that the mover is entitled to judgment as a matter of

law. La. C.C.P. art. 966 (A)(3). The burden of proof rests with the mover;

however, the burden is on the adverse party to produce factual support

sufficient to establish the existence of a genuine issue of material fact or that

the mover is not entitled to judgment as a matter of law. La. C.C.P. art. 966

(D)(2). Mere speculation is not sufficient. Klein, supra.

Review of a grant or denial of a motion for summary judgment is de

novo. Lawrence v. Sanders, 49,966 (La. App. 2 Cir. 06/24/15), 169 So. 3d

790, writ denied, 15-1450 (La. 10/23/15), 179 So. 3d 601.

DISCUSSION

This case involves the relationship between Comstock, the owner and

operator of a well site, and Chaps, its “company man,” whose job entailed

supervising the work on the site. It was Chaps’ employee at the well site

when the events unfolded that resulted in the alleged injuries to McDaniel.

McDaniel alleges that Chaps was not an independent contractor, and thus,

5

Comstock should be liable for the Chaps’ employees’ actions on the day of

his accident, which resulted in his injuries.

This court is aware of the risk of the potential for a troubling

cramdown of overly broad indemnifications from liability which can result

from master service agreements that are not the product of equal bargaining

positions. However, Louisiana law is clear that a principal is generally not

liable for the offenses of an independent contractor. Ainsworth v. Shell

Offshore, Inc., 829 F.2d 548, 549 (5th Cir. 1987), cert. denied, 485 U.S.

1034, 108 S. Ct. 1593 (1988). Louisiana courts have identified a number of

relevant factors in determining whether the relationship of principal and

independent contractor exists, including the existence of a contract for

performance of a specific job, payment of a fixed price for the work,

employment by the contractor of assistants who are under his control, the

furnishing of necessary tools and materials by the contractor, and his right to

control the conduct of his work while in progress. Davenport v. Amax

Nickel, Inc., 569 So. 2d 23 (La. App. 4 Cir. 1990), writ denied 90-2426 (La.

01/04/91), 572 So. 2d 68. It is not the supervision or control which is

actually exercised by the employer that is significant, but whether, from the

nature of the relationship, the right to do so exists. White v. Shell Expl. &

Prod. Co., 06-677 (La. App. 5 Cir. 01/30/07), 951 So. 2d 1208, 1211, writ

denied 07-0407 (La. 04/20/07), 954 So. 2d 164.

In this instance, the record is clear that the Chaps MSA governed the

relationship between the two parties, and it is undisputed that the contract

explicitly states that Chaps was an independent contractor. The contract also

explicitly states that Chaps would furnish necessary tools, supplies, or

6

materials to perform the work. Finally, although the Chaps MSA does not

describe the specific site or general duties for Chaps or state a fixed price for

the work to be performed, the MSA includes the following language:

[The] Agreement shall control and govern all work performed
or to be performed by [Chaps] for [Comstock] under verbal or
written work orders, purchase orders, delivery tickets, invoices
or other verbal or written agreements between the Parties,
relating to work to be done by [Chaps] for [Comstock]

Courts applying Louisiana law have recognized that an ongoing contractual

relationship between parties can still create a principal/independent

contractor relationship. See Namer v. Hall, 06-10698, (E.D. La. 3/25/08),

2008 WL 819397; White, supra. The Chaps MSA plainly provides that

additional work orders, both verbal and written, will be provided between

the parties under the contractual umbrella of the MSA. Considering the

above, we find that Comstock has presented undisputed evidence that Chaps

was an independent contractor for which Comstock was not liable.

Having determined there exists an independent contractor

relationship, we must now explore the two exceptions to the general rule that

principals are not liable for independent contractors. The first occurs when

the liability arises from ultrahazardous activities performed by the contractor

on behalf of the principal. The second exception occurs when the principal

retains “operational control” over the contractor’s work or expressly or

impliedly approves the unsafe work practices that lead to an injury. Klein,

supra. McDaniel alleges that there is a genuine issue of material fact as to

whether Comstock retained operational control over Chaps at the well site.

In order to determine whether a principal has retained operational

control, a court must first analyze whether, and to what extent, the principal

7

contractually reserved the right to control the work. Klein, supra;

Ainsworth, supra. Actual control is also relevant to the operational control

exception, but the supervision and control that is actually exercised by the

principal is less significant than the contractual reservation of the right to

control by the principal. Ainsworth, supra.

The provisions of the Chaps MSA establish Comstock specifically

relinquished all contractual control over the work to be performed by Chaps.

The Chaps MSA provides:

§8. Independent Contractor. In the performance of the
services hereunder, [Chaps] agrees that it shall act as and be an
Independent Contractor free and clear of any dominion or
control by [Comstock] in the manner in which said services are
to be performed, and as such [Chaps]:
a. acts as the employer of any employee of the [Chaps] by
paying wages, directing activities, performing other similar
functions characteristic of an employer-employee
relationship;
b. is free to determine the manner in which the work or service
is performed, including the hours of labor or method of
payment to any employee;
c. is required to furnish or have his employees, if any, furnish
necessary tools, supplies, or materials to perform the work
or service;
d. possess the skills required for the specific work or service;
e. agrees to file all required tax reports and pay all income
taxes due on payments to [Chaps] hereunder;
f. agrees that neither [Chaps] nor [Chaps’] employees, agents
or subcontractors will be covered by [Comstock’s] Workers
Compensation.

“When the contract assigns the independent contractor responsibility for its

own activities, the principal does not retain operational control.” Klein, 855

So. 2d at 850 (quoting Fruge ex rel. Fruge v. Parker Drilling Co., 337 F.3d

558 (5th Cir. 2003), cert. denied, 540 U.S. 1161, 124 S. Ct. 117 (2004)).

The unambiguous language of the Chaps MSA refers to Chaps as an

“independent contractor” and establishes the principal/independent

8

contractor relationship. There is no evidence in this record that Comstock

contractually reserved the right to control the work.

We must next determine whether Comstock retained any actual

operational control over Chaps. A principal is entitled to maintain

supervisory control over a project done by an independent contractor to

ensure that it complies with the contract. Nippa v. Chevron, USA, 99-2953

(La. App. 4 Cir. 11/15/00), 774 So. 2d 310, 314, writ denied, 2000-3420 (La.

02/09/01), 785 So. 2d 823. However, the status of an independent contractor

can be in doubt when the principal exercises operational control over a

project. Id.

The origin of the term “operational control” in Louisiana

jurisprudence can be traced back to the Restatement (Second) of Torts

(1965), in which the comment to §414 provides:

In order for the rule stated in this section to apply, the
employer must have retained at least some degree of
control over the manner in which the work is done. It is
not enough that he has merely a general right to order the
work stopped or resumed, to inspect its progress or
receive reports, to make suggestions or recommendations
which need not necessarily be followed, or to prescribe
alterations or deviations. Such a general right is usually
reserved to employers, but it does not mean that the
contractor is controlled as to his methods of work, or as
to operative detail. There must be such a retention of a
right of supervision that the contractor is not entirely free
to do the work in his own way.

Grammer v. Patterson Services, Inc., 860 F.2d 639 (5th Cir. 1988), cert.

denied 491 U.S. 906, 109 S. Ct. 3190 (1989)(quoting Restatement (Second)

of Torts (1965)). Operational control exists only if the principal has direct

supervision over the step-by-step process of accomplishing the work such

that the contractor is not entirely free to do the work in his own way. Klein,

9

supra. A federal court applying Louisiana law defined “step-by-step

process” as a case where a principal substitutes the independent contractor’s

entire method and manner of operation for one of its own. Romero v. Mobil

Expl., 727 F. Supp. 293 (W.D. La. 1989), aff’d 939 F.2d 307 (5th Cir. 1991).

Operational control is the retention of right of supervision in such a way that

the contractor is not entirely free to do the work in his own way. Skinner v.

Schlumberger Technology Corp., 13-03146, (W.D. La. July 13, 2015), 2015

WL 4253986. Specifically, “for purposes of determining operational

control, the relevant inquiry becomes whether [the defendant] had control

over the operation of the particular activity during which the plaintiff was

injured.” Robertson v. Arco Oil & Gas Co., 948 F.2d 132, 133 (5th Cir.

1991).

McDaniel directs the Court to the affidavit of Dan Harrison,

Comstock’s Chief Operating Officer, who testified that:

Comstock would consult with Chaps personnel regarding the
operations at the well site and Comstock would identify and provide
specifications for each operation. Comstock consulted with Chaps
employees regularly and would discuss issues and problems as they
arose.

McDaniel also directs the court to the deposition of Preston Poole, a Chaps

employee, who testified that he could order the operation to shut down if

directed to do so by Comstock, but he did not otherwise supervise Baker

Hughes’ operations. Finally, McDaniel cites the testimony of Comstock

environmental specialist Keith Lorenz, who stated that he was called after

the acid spill by a Chaps employee. Lorenz testified that he was one of the

employees who is required to be notified when a spill has occurred so that he

can alert the proper authorities in accordance with Comstock’s spill plan,

10

which remained in the possession of Comstock employees. Lorenz testified

that in the present matter, he notified the proper authorities and then visited

the site several days after the acid spill occurred. McDaniel argues this

testimony creates a genuine issue of fact as to whether Comstock had

operational control over Chaps. We disagree under these specific facts.

In Fruge, supra, the court affirmed a summary judgment in favor of

the principal when the representative was present on the project site 24 hours

a day, but there was no evidence of direct supervision or control. The court

in Klein found that there was no operational control when the principal

visited the site several times a week and made suggestions regarding the

completion of the project. The Klein court held that mere suggestions or

instructions to an independent contractor does not equate to control over the

methods or details of a contractor’s work. Klein, supra at 851. The United

States Fifth Circuit, applying Louisiana law, found that there was no

operational control when the principal reserved the right to monitor the

contractor’s performance, stationed a “company man” on the platform to

observe the contractor’s activities, and the contractor was obligated to report

unsafe work practices or conditions to the principal. Coulter v. Texaco, Inc.,

117 F.3d 909, 912 (5th Cir. 1997).

Considering the above jurisprudence, we cannot find that the

testimony cited by McDaniel rises to such a level as to create a genuine issue

of fact as to whether Comstock retained operational control over Chaps. The

record reflects that Comstock did not have any employees at the well site on

the day of McDaniel’s accident. While Comstock had regular consultations

with Chaps, there is no evidence that Comstock substituted its method or

11

manner of operation for that of Chaps. There is also no evidence that

Comstock had any control over the particular activity that caused

McDaniel’s injury, i.e. the vacuuming of hydrochloric acid. Comstock’s

environmental specialist notified authorities about the acid spill but did not

direct the clean-up and only visited the site several days after the spill

occurred. The relationships between Comstock and Chaps in the present

matter is one of supervisory control, rather than operational control.

Supervisory control does not negate the principal/independent contractor

relationship. As such, the granting of the motion for summary judgment

under these specific circumstances was proper.

CONCLUSION

For the foregoing reasons, the judgment of the trial court is affirmed.

AFFIRMED.

12