55,328-CA Precedential Affirmed. Robinson, J., dissents with written reasons. Processed

City of Ruston v. Womack & Sons Construction Group, Inc.

Louisiana Court of Appeal, Second Circuit · Filed November 15, 2023

Authorities cited

Identified automatically; this list may not be exhaustive.

Opinion text

Judgment rendered November 15, 2023.
Application for rehearing may be filed
within the delay allowed by Art. 2166,
La. C.C.P.

No. 55,328-CA

COURT OF APPEAL
SECOND CIRCUIT
STATE OF LOUISIANA

*****

CITY OF RUSTON Plaintiff-Appellant

versus

WOMACK & SONS Defendants-Appellees
CONSTRUCTION GROUP, INC.

*****

Appealed from the
Third Judicial District Court for the
Parish of Lincoln, Louisiana
Trial Court No. 61,968

Honorable Thomas Wynn Rogers, Judge

*****

LAW OFFICES OF RUSSELL Counsel for Appellant
ALAN WOODARD, JR., LLC
By: Russell Alan Woodard, Jr.

KEAN MILLER, LLP Counsel for Appellees
By: Michael D. Lowe
G. Trippe Hawthorne
Thomas D. Bourgeois, Jr.

*****

Before THOMPSON, ROBINSON, and MARCOTTE, JJ.

ROBINSON, J., dissents with written reasons.

THOMPSON, J.

In the middle of a large-scale construction project to create a sports

complex, the city of Ruston was faced with a difficult business decision

regarding the synthetic field turf playing surfaces on some of the baseball

fields. It could either stay the course on the original design, which would

delay the completion date and cause it to lose out on hosting a lucrative

inaugural event, or it could modify the design plan to complete the project

timely, which option included a request from the contractor for additional

construction funds for the new design. The city elected the modified

construction design and faster completion date, signed a change order for the

revision, and paid the requested added cost for the revision. The project was

completed on time, and the city hosted the event, resulting in an economic

boon for the city and area businesses. Subsequently, the city sought to

recover the additional costs it paid to the contractor, which, in turn, argued

that a clause in the construction contract acted as a final settlement for all

claims regarding the change order and that it is not required to refund the

funds paid for the revision to the project. The trial court granted a summary

judgment in favor of the contractor, and the city appealed. For the reasons

set forth below, we affirm the trial court.

FACTS AND PROCEDURAL HISTORY

In an effort to expand recreational facilities, generate economic

impact for the region and tax revenue for itself, the City of Ruston (the

“City”) contracted to host the 2019 Dixie World Series. To host this and

potential future large-scale events, the City designed and put out for bid the

Ruston Sports Complex, which comprised of four different complexes

and facilities, and included 16 baseball fields. On August 31, 2017, the City

awarded the approximately $35,000,000 public construction contract to

build the complex on U.S. Highway 167 South in Ruston (the “Project”) to

Womack & Sons Construction Group, Inc. (“Womack”). The architect for

the Project was Yeager, Watson & Associates, LLC (“YWA”). This dispute

arises from that part of the Project concerning the construction of the

synthetic field turf playing surfaces on some of the fields. The Project had a

425-day deadline, to enable the City to satisfy its contractual obligations to

host the Dixie League World Series in July, 2019. The World Series was

anticipated to generate over $6,000,000 in economic impact.

On September 26, 2017, the parties executed a written contract

outlining their rights and obligations on the Project. The contract is a

standard form contract prepared by the American Institute of Architects,

known as the AIA Document A101-2007, Standard Form of Agreement

between Owner and Contractor (the “Contract”). Several other documents

were incorporated into the Contract. Article 1 of the Contract describes the

other documents, including (1) Conditions of the Contract (General,

Supplementary, and other Conditions), (2) Drawing Specifications, (3)

Addenda issued prior to execution of this Agreement, and (4) Modifications

issued after execution of this Agreement, “all of which form the Contract,

and are as fully a part of the Contract as if attached to this Agreement or

repeated herein.” The General Conditions are on a standard-form document

prepared by the American Institute of Architects-AIA Document A201-

2007, General Conditions of the Contract for Construction (the “General

2

Conditions”). The Supplementary Conditions were prepared by YWA and

were included within the Project Manual.

The General Conditions allowed for changes to be made to the

Contract during construction, a commonly anticipated occurrence in large

construction projects. Article 7 of the General Conditions provided:

Changes in the Work may be accomplished after execution of
the Contract, by Change Order, Construction Change Directive
or order for a minor change in the Work, subject to the
limitations stated in this Article 7 and elsewhere in the Contract
Documents.

Article 7.1.2 of the General Conditions states that “a Change Order

shall be based upon agreement among the Owner, Contractor and Architect.”

Article 7.2.1 defines a Change Order as:

A Change Order is a written instrument prepared by the
Architect and signed by the Owner, Contractor and Architect
stating their agreement upon all of the following:

.1 The Change in the Work;
.2 The amount of adjustment, if any, in the Contract Sum;
and
.3 The extent of the adjustment, if any, in the Contract
Time.

As noted above, the Supplementary Conditions modify the General

Conditions. Article 7.2 of the Supplementary Conditions adds Subparagraph

7.2.2 to Article 7.2 of the General Conditions, and states:

Agreement on any change order shall constitute a final
settlement of all matters relating to the change in the Work
which is the subject of the Change Order, including, but not
limited to all direct and indirect costs associated with such
change and any and all adjustments to the Contract Sum and the
Contract Time. In the event a Change Order increases the
Contract Sum, Contractor shall include the Work covered by
such Change Order in Applications for Payment.

There were five change orders executed in connection with the

Project. The change order at issue in the present matter is Change Order No.

3

2, which was executed in February of 2019. Change Order No. 2 directed

Womack to make 16 changes to the project. It added 139 days to the

contract time to accommodate the changes and inclement weather. The

original contract sum was increased by $1,779,682.33 to address the

modifications outlined in Change Order No. 2. YWA prepared and executed

Change Order No. 2 on February 6, 2019. Womack executed it on February

7, 2019, and the City executed it on February 18, 2019. It was recorded in

Lincoln Parish on February 22, 2019.

Change Order No. 2 was required for the Project in order to correct a

problem with the subsurface installed under the turf fields in five of the

baseball fields at the sports complex. Womack had hired a subcontractor,

GeoSurfaces (“Geo”), to install the subsurface base and the turf fields in

accordance with the original contract. The Project design originally called

for compacted dirt, topped with a geomembrane liner, a drainage pad, and

rock. The turf was to be placed on top of the subsurface.

In the late fall of 2018, Geo and Womack discussed the fact that there

was a leak in the geomembrane liner of five of the fields from rain. The

record reflects an email between Womack and Geo, wherein Womack states

that “I do not want any inspectors noticing and causing a problem”

regarding the wet subsurface liners and discussing possible solutions for the

problem. The parties dispute whether the cause of the wet subsurface liners

was the rainy weather or Womack’s poor workmanship.

In January of 2019, Womack shared with YWA the fact that the

subsurface layer of these fields was wet and the turf could not be laid over

the wet subsurface. Any resolution over the passage of time that Womack

4

may have hoped for never materialized, and the problem remained. YWA

informed the City of the situation and explained that the only remedy under

the current specifications was to peel back the liner and let the underlying

foundation dry out. The City felt that although this proposed resolution

would resolve the problem as originally engineered in the Project, the added

delay was an undesirable option because it would take too long and

potentially disrupt its contract to host the approaching Dixie Youth World

Series. In the alternative, Womack and Geo suggested a base system, using

concrete, which could be installed on top of the subsurface already in place.

This would allow the turf to be installed without the need to take any

additional action or delay.

YWA issued a memorandum to Womack and the City on February 1,

2019, confirming the use of the GeoBase structural system and suggested

that the change should be at no additional cost to the City. It opined that the

changes being made to the Project plans were due to Womack’s lack of

attention and timely responsiveness throughout the project. Womack

objected to the suggestion that the new base should be added at no cost to

the City. It asserted the fields could be completed as originally designed and

planned in the Project but noted that additional time would be required to

address the conditions, understandably apparently more concerned with its

obligation and contract with the City, and not as concerned by any contract

the City may have entered with Dixie Little League.

A site visit was held on February 5, 2019, and afterwards, the mayor

of the City approved the inclusion of the GeoBase system. The approval

was relayed by Womack to YWA, along with the pricing for the change.

5

Womack states that they discounted its portion of the cost associated with

the new GeoBase system by 50%.

As noted above, Change Order No. 2 was executed by the parties in

February of 2019, and the City paid the amount owed and outlined in the

document. The City argues that Change Order No. 2 does not discuss a

settlement or release. It contends that it paid the money to Womack so that

Womack could pay Geo, “with the understanding that Ruston and Womack

would ‘get square’ later.” An affidavit provided by the City states that “[a]t

all times, Ruston’s intentions were clearly expressed: Ruston would pay

Womack the amount stated under Change Order #2 [which Womack would

immediately pay its turf subcontractor Geo] to get the Project completed in

time for Ruston to host the World Series.” The parties agree that, using the

new subsurface system, the work was timely completed to allow the City to

successfully host the World Series, generating millions of dollars in

economic impact and significant tax revenue for the City.

On October 8, 2021, the City filed suit against Womack, alleging

breach of contract and seeking a refund on the $1,779,682.33 included in

Change Order No. 2. On January 12, 2022, Womack filed a motion for

summary judgment, seeking dismissal of the claims against it pursuant to the

language in Section 7.2.2 of the Contract. Womack also filed a motion for

protective order to not have to produce the voluminous discovery requested

by the City. Both motions were heard by the trial court on June 20, 2022.

The City argued that the motion for summary judgment was premature

because it had not had the opportunity to conduct discovery, and Womack

6

argued that the plain language of the contract required dismissal of the

City’s claims. The trial court took the matter under advisement.

On June 27, 2022, the City filed a motion for leave to file a first

supplemental/amended petition (the “motion to amend”). Womack argued

this motion to amend was really a supplemental opposition to its motion for

summary judgment. The trial court set a hearing on the matter for August

25, 2022. On July 8, 2022, the trial court issued a ruling continuing further

consideration of the motion for summary judgment in order to give the City

the opportunity to conduct discovery related to the issues raised in the

motion. After a request for an extension was filed by both parties, the trial

court set the hearing date for both the motion for summary judgment and the

motion to amend on November 17, 2022. In the interim, discovery was

conducted by the City.

After arguments at the motion for summary judgment hearing, the

trial court denied the City’s motion to amend and took the motion for

summary judgment under advisement. On January 9, 2023, the trial court

granted Womack’s motion for summary judgment, finding that the contract

as a whole was clear, explicit, and will not lead to absurd consequences. It

found no evidence of fraud and rejected the City’s attempt to introduce parol

evidence regarding the meaning of the contract and the intent of the parties.

It ultimately concluded that the City made a business decision to continue on

with the amended Project plans and chose pay for the new subsurface

product. This appeal by the City followed.

7

DISCUSSION

The City asserts five (5) assignments of error from the ruling of the

trial court. The City’s first three assignments of error all relate to the trial

court’s ruling on the motion for summary judgment and the parties’ intent.

As such, we will address them together.

First Assignment of Error: The trial court erred by ignoring material
factual disputes to impermissibly evaluate the parties’ credibility and
intent.

Second Assignment of Error: The trial court erred by misinterpreting a
single sentence of the contract, which renders 19 other sections
meaningless: a patent violation of the “Cardinal Rule” that contracts be
interpreted to harmonize provisions to give them meaning and effect.

Third Assignment of Error: The trial court erred by holding Ruston
responsible for a $1.8 million problem caused by Womack.

Appellate courts review motions for summary judgment de novo,

using the same criteria that govern the district court’s consideration of

whether summary judgment is appropriate. Peironnet v. Matador Res. Co.,

12-2292 (La. 6/28/13), 144 So. 3d 791; Springbok Royalty Partners, LLC v.

Cook, 54,788 (La. App. 2 Cir. 11/16/22), 351 So. 3d 850, writ denied, 22-

01832 (La. 4/14/23), 355 So. 3d 614. A motion for summary judgment is a

procedural device used when there is no genuine issue of material fact for all

or part of the relief prayed for by a litigant. Schultz v. Guoth, 10-0343 (La.

1/19/11), 57 So. 3d 1002. The procedure is favored and shall be construed

to secure the just, speedy, and inexpensive determination of actions. La.

C.C.P. art. 966(A)(2).

A motion for summary judgment shall be granted if the motion,

memorandum, and supporting documents show that there is no genuine issue

as to material fact and that the mover is entitled to judgment as a matter of

8

law. La. C.C.P. art. 966(A)(3). A fact is material if it potentially ensures or

precludes recovery, affects a litigant’s ultimate success, or determines the

outcome of the legal dispute. A genuine issue of material fact is one as to

which reasonable persons could disagree; if reasonable persons could reach

only one conclusion, there is no need for trial on that issue and summary

judgment is appropriate. Maggio v. Parker, 17-1112 (La. 6/27/18), 250 So.

3d 874; Jackson v. City of New Orleans, 12-2742 (La. 1/28/14), 144 So. 3d

876, cert. denied, 574 U.S. 869, 135 S. Ct. 197, 190 L. Ed. 2d 130 (2014);

Springbok, supra. In determining whether an issue is genuine, a court

should not consider the merits, make credibility determinations, evaluate

testimony, or weigh evidence. Springbok, supra.

The burden of proof rests with the mover. Nevertheless, if the mover

will not bear the burden of proof at trial on the issue that is before the court

on the motion for summary judgment, the mover’s burden on the motion

does not require him to negate all essential elements of the adverse party’s

claim, action, or defense, but rather to point out to the court the absence of

factual support for one or more elements essential to the adverse party’s

claim, action, or defense. The burden is on the adverse party to produce

factual support sufficient to establish the existence of a genuine issue of

material fact or that the mover is not entitled to judgment as a matter of law.

La. C.C.P. art. 966(D)(1). Supporting and opposing affidavits shall be made

on personal knowledge, shall set forth such facts as would be admissible in

evidence, and shall show affirmatively that the affiant is competent to testify

to the matters stated therein. La. C.C.P. art. 967(A). When a motion for

summary judgment is made and supported as provided above, an adverse

9

party may not rest on the mere allegations or denials of his pleading, but his

response, by affidavits or as otherwise provided above, must set forth

specific facts showing that there is a genuine issue for trial. If he does not so

respond, summary judgment, if appropriate, shall be rendered against him.

La. C.C.P. art. 967(B).

When a contract can be construed from the four corners of the

instrument, interpretation of the contract presents a question of law that can

be decided on summary judgment. Sequoia Venture No. 2, Ltd. v. Cassidy,

42,426 (La. App. 2 Cir. 10/10/07), 968 So. 2d 806, writ denied, 07-2210 (La.

1/11/08), 972 So. 2d 1166.

The City argues in its first assignment of error that there are many

factual disputes in the present matter, specifically concerning the parties’

intent. In support of its argument, the City cites Chase Womack’s

deposition and affidavit and the letter sent by YWA to Womack in

anticipation of Change Order No. 2. In its second assignment of error, the

City contends that the trial court’s ruling renders the Contract meaningless

under the Cardinal Rule, i.e. that a contract must be interpreted in light of the

other provisions so that each is given the meaning suggested by the contract

as a whole. Finally, in its third assignment of error, the City argues that

requiring it to pay almost 1.8 million dollars for work caused by Womack’s

error is an absurd result.

Under Louisiana law, contracts are interpreted according to the

common intent of the parties. La. C.C. art. 2045. When the words of a

contract are clear, explicit, and lead to no absurd consequences, no further

interpretation need be made in search of the parties’ intent. La. C.C. art.

10

2046. The City argues that there are disputes between the parties regarding

the cause of the damage to the original fields, which party would pay for the

new fields, and the parties’ agreements thereto. However, interpretation of a

contract within the instrument’s four corners is a matter of law, and the use

of extrinsic evidence is proper only if a contract is ambiguous after an

examination of the four corners of the agreement. Frierson v. Stephens, Inc.,

55,115 (La. App. 2 Cir. 8/9/23), --- So. 3d ---, 2023 WL 5065900. A

contract is ambiguous when it lacks a provision bearing on the issue, its

written terms are susceptible to more than one interpretation, there is

uncertainty as to its provisions, or the parties’ intent cannot be ascertained

from the language used. Campbell v. Melton, 01-2578 (La. 5/14/02), 817

So. 2d 69; Sequoia Venture, supra. A provision is not considered

ambiguous merely because one party creates a dispute about it. Campbell,

supra.

A review of the record reveals that the terms of the Contract are clear,

explicit, and lead to no absurd consequences. Section 7.2.2 unambiguously

states that an agreement to a change order shall constitute a final settlement

of all matters relating to the change order, including all costs associated with

the change and all adjustments to the contract sum. Change Order No. 2

clearly states that the additional work to be performed under Change Order

No. 2 will cost the City $1,779,682.33. Change Order No. 2 includes the

undisputed signatures of representatives of YWA, Womack, and the City.

Unexpressed intentions or desires, not included in the written

agreement of the parties, do not create an ambiguity. The City has not

explicitly argued that the terms of the contract are ambiguous, but rather,

11

directs this Court to numerous provisions that it contends will be

“neutralized” by the enforcement of Section 7.2.2 and Change Order No. 2.

We find no ambiguity in the terms of the Contract. The portions of the

Contract cited by the City are provisions that would have allowed the City to

take action against Womack for the alleged poor workmanship on the

disputed fields. However, the record is clear that the City chose not to avail

itself of these provisions and, instead, negotiated a new option with Womack

for the disputed fields, which involved an additional cost for different

materials and a different design than originally planned.

The record reflects that the City had several options when faced with

what it now asserts as the alleged poor workmanship from Womack,

including but not limited to: (1) seeking to enforce the provisions it has cited

from the Contract, which would have mandated Womack correct the work at

its own expense; (2) suing Womack for breach of contract; and (3) refusing

to sign Change Order No. 2 without a reservation of rights. These are

sophisticated parties with ready access to legal counsel, and the City had the

benefit of YWA recommending it should not obligate itself to pay for the

costs associated with the change of the scope of the project. Rather than

availing itself of the advice of the supervising architect and any of the

options listed above, the City chose to sign Change Order No. 2, which was

clearly subject to Section 7.2.2, and also elected to pay the additional cost

described within the Change Order.

As noted by the trial court, this was a business decision related to the

City’s need to have completed baseball fields in time for the Dixie League

World Series. It is understandable that the City is unhappy it paid almost 1.8

12

million dollars for additional work that it feels would not have been

necessary but for Womack’s poor workmanship. However, Louisiana law

states that when a clause in a contract is clear and unambiguous, the letter of

that clause should not be disregarded under the pretext of pursuing its spirit,

as it is not the duty of the courts to bend the meaning of words of a contract

into harmony with a supposed reasonable intention of the parties. Prejean v.

Guillory, 10-0740 (La. 7/2/10), 38 So. 3d 274. Further, the fact that one side

made a “bad deal” is not an “absurd consequence” that would justify

rescinding the entire contract. Gibbs Const. Co. v. Thomas, 500 So. 2d 764

(La. 1987); KCREW Invest., LLC v. Clark, 55,092 (La. App. 2 Cir. 5/10/23),

362 So. 3d 1288. Additionally, Womack has steadfastly declared the change

in the scope of work and additional costs associated therewith were not its

responsibility under the original Contract without added compensation.

The record reflects that the parties disagreed about the cause of the

problems with the disputed fields and which party should pay for those

problems. However, the parties knew of these issues before signing Change

Order No. 2, and the language of the Contract is clear and unambiguous.

Any unresolved issues either party asserts remained were resolved when the

language of Change Order No. 2 was finalized and the parties signed it and

proceeded with the work outlined. The trial court and this court cannot bend

the meaning of words of a contract. Accordingly, the City’s first three

assignments of error are without merit.

Fourth Assignment of Error: The trial court erred by refusing to
consider the context surrounding the second change order; it is clouded
with errors, fraud, financial duress, and an absence of
consideration/causation.

13

In its fourth assignment of error, the City argues that all of the listed

vices of consent exist in the present matter. Louisiana law provides that a

contract is formed by the consent of the parties. La. C.C. art. 1927.

However, consent may be vitiated by error, fraud, or duress. La. C.C. art.

1948. We will discuss each below.

Error

The City contends that there was no meeting of the minds between

itself and Womack regarding Change Order No. 2, which is actionable error

pursuant to La. C.C. arts. 1949 and 1950. Louisiana law provides that error

vitiates consent only when it concerns a cause without which the obligation

would not have incurred and that cause was known or should have been

known to the other party. La. C.C. art. 1949; Peironnet, supra. Unilateral

error will not vitiate consent to a contract if the error was inexcusable. Id.

The Louisiana Supreme Court stated in Peironnet, supra:

It seems quite clear that, unless induced to do so by outright
fraud, a party who signs an instrument without reading it
thereby fails to exercise elementary prudence that, if observed,
would have prevented him from making his alleged error. As
such contract-making conduct cannot be excused, so the
resulting error cannot be excused either.

We find no evidence of error in the present matter. As discussed

above, the Contract is clear and unambiguous and the City has not named a

specific error that would vitiate consent. The result of being held to the

negotiated terms of Change Order No. 2 and the Contract may not have been

what the City ultimately wanted once the Dixie League World Series was

completed, but that does not satisfy the requirements of the vice of consent

of “error” as contemplated by Louisiana jurisprudence.

14

Fraud

As to fraud, the City argues that Womack made material

misrepresentations and failures to disclose that amount to fraud regarding

the state of the subsurface of the disputed fields between November 1, 2018

and January 9, 2019. The City contends that Womack’s intention was to

hide and misrepresent facts so that it did not have to correct the work done to

the fields according to the original plans and that but for these

misrepresentations, Change Order No. 2 would not have existed.

Fraud is a misrepresentation or a suppression of the truth made with

the intention either to obtain an unjust advantage for one party or to cause a

loss or inconvenience to the other. La. C.C. art. 1953. Fraud may also result

from silence or inaction. When fraud is based on silence or suppression of

the truth, the plaintiff must prove a duty to speak or disclose the information.

Priority Hosp. Group, Inc. v. Manning, 53,564 (La. App. 2 Cir. 9/23/20),

303 So. 3d 1106, writ denied, 20-01238 (La. 1/20/21), 308 So. 3d 1160.

However, fraud does not vitiate consent when the party against whom the

fraud was directed could have ascertained the truth without difficulty,

inconvenience, or special skill. Id. The circumstances constituting fraud

must be alleged with particularity. La. C.C.P. art. 856. There are three basic

elements to an action for fraud against a party to a contract: (1) a

misrepresentation, suppression, or omission of true information; (2) with the

intent to obtain an unjust advantage or to cause damage or inconvenience to

another; and (3) the error induced by a fraudulent act must relate to a

circumstance substantially influencing the victim’s consent to (a cause of)

15

the contract. Murray v. Bostwick, 52,802 (La. App. 2 Cir. 8/14/19), 276 So.

3d 1120.

We find the high standard set forth above has not been satisfied in the

present matter. The record reflects one email between Womack and Geo,

wherein a representative of Womack stated that he did not want inspectors at

the site while they worked on the problem. It is undisputed that the City was

aware of the problem with the wet liners on the fields before it signed

Change Order No. 2, and in fact, the record is clear that Womack, the City,

and YWA had meetings and discussed potential options prior to signing

Change Order No. 2. The City contends that Womack was deceptive in not

disclosing the fact that there was a problem with the liners when it was

discovered in November, rather than waiting for January. As outlined

previously, the City had numerous remedies available to it at that point. Due

to the pending obligations to host the Dixie League World Series, the City

elected to proceed with a different product and its faster date of completion.

Even if the omission by Womack rose to the level of fraud, the City could

have ascertained the truth without difficulty, inconvenience, or special skill.

Duress

Finally, the City argues that by the time Womack disclosed the

problems with the field, it had no other practical alternative to Change Order

No. 2, which amounts to financial duress. The pressure to complete the

fields pursuant to the original deadline was caused by the City’s reasonable

desire to have the fields completed in time for the World Series. That

separate contract and related implications has no bearing on the clear

language of the four corners of the Contract for the Project.

16

Consent to a contract is vitiated when it has been obtained by duress

of such a nature as to cause a reasonable fear of unjust and considerable

injury to a party’s person, property, or reputation. Age, health, disposition,

and other personal circumstances of a party must be taken into account in

determining reasonableness of the fear. La. C.C. art. 1959. The threat of

doing a lawful act or exercising a right does not constitute duress. Vogler v.

Ayres, 54,734 (La. App. 2 Cir. 8/17/22), 345 So. 3d 1184.

In support of its argument, the City cites Wolf v. Fair Grounds Corp.,

545 So. 2d 976 (La. 1989), wherein jockeys who wished to race at a track

were required to sign an agreement waiving their right to sue the track for

negligence resulting in personal injury and limit their claims to worker’s

compensation. The Louisiana Supreme Court held that because of the

superior bargaining strength of the track and the economic vulnerability of

the jockeys, it was reasonable to conclude that the jockeys would have felt

forced into signing the contract. The court found this particular situation

met the level of duress required to vitiate consent to the contract. Id.

Here, unlike in Wolf, supra, the City, YWA, and Womack were

sophisticated parties who negotiated Change Order No. 2 prior to signing the

document. The City certainly had the same, if not greater, bargaining

strength than Womack. While the City may have felt some economic stress

to have the fields completed on time for the World Series, that alone is not

sufficient to constitute duress as contemplated by Article 1959. Here, any

stress the representatives of the City may have experienced to satisfy its

obligations to have the fields ready does not equal the vice of consent of

duress.

17

There is clear evidence of consent by all parties to the Contract and

Change Order No. 2 in the record. The record does not reflect any evidence

sufficient to satisfy the standard for vices of consent under Louisiana law,

and as such, this assignment of error is without merit.

Fifth Assignment of Error: The trial court manifestly erred by denying
Ruston’s request to amend and supplement its petition even because (1)
it was Ruston’s first and only request, (2) Womack filed no opposition,
(3) suit had been pending for only 8 months, and (4) it was based on
newly discovered facts.

Finally, the City argues that the trial court erred in denying its motion

to amend and supplement its petition because it was the City’s first request

to amend, suit had only been pending for eight months, it was based on

newly discovered facts, and Womack allegedly did not oppose the motion.

The law takes a liberal approach to allowing amended pleadings to

promote the interests of justice. Walton v. Burns, 47,388 (La. App. 2 Cir.

1/16/13), 151 So. 3d 616. Amendment is generally allowed, provided the

mover is acting in good faith, the amendment is not sought as a delaying

tactic, the opponent will not be unduly prejudiced, and trial of the issues will

not be unduly delayed. Giron v. Housing Auth. of City of Opelousas, 393

So. 2d 1267 (La.1981); Bilyeu v. Nat’l Union Fire Ins. Co. of Pittsburgh,

PA, 50,049 (La. App. 2 Cir. 9/30/15), 184 So. 3d 69, writ denied, 15-2277

(La. 2/19/16), 187 So. 3d 462. However, a trial court has broad discretion in

ruling on motions to amend pleadings, and a decision to accept or reject an

amendment should not be disturbed on appeal absent abuse of that

discretion. Aymond v. Citizens Progressive Bank, 52,623 (La. App. 2 Cir.

6/26/19), 277 So. 3d 477, writ denied, 19-1200 (La. 10/15/19), 280 So. 3d

602.

18

While the motion for summary judgment was pending at the trial

court, the City sought to amend its petition to include the following claims:

(1) no cause or meeting of the minds pursuant to La. C.C. art. 1967; (2)

substantial inequity adjustment per Section 7.3.4; (3) economic duress; and

(4) cardinal change. After the motion to amend was filed, the trial court

granted the City’s motion for discovery, allowed time for additional

discovery, and each party filed additional briefs related to the pending

motion for summary judgment. Those briefs included arguments related to

the above claims. The record reveals the trial court considered those claims

in its ruling on the motion for summary judgment. Under the facts of this

case, we cannot say the trial court abused its discretion in denying the

motion to amend. This assignment of error lacks merit.

CONCLUSION

For the foregoing reasons, the ruling of the trial court is affirmed.

Costs of this appeal are assessed to the City of Ruston.

AFFIRMED.

19

ROBINSON, J., dissenting.

I respectfully dissent from the majority opinion. A motion for

summary judgment is a procedural device used when there is no genuine

issue of material fact for all or part of the relief prayed for by a litigant.

Reynolds v. Bordelon, 14-2371 (La. 6/30/15), 172 So. 3d 607. Appellate

courts review motions for summary judgment de novo, using the same

criteria that govern the district court’s determination of whether summary

judgment is appropriate. Id. I find that there are genuine issues of material

fact.

As stated in the majority’s opinion, the City entered into a contract

with Womack on September 26, 2017, to construct the Ruston Sports

Complex with a provision stating that the project was to be completed within

425 days. Prior to this contract, the City entered into a contract with Dixie

Baseball to host the Dixie Youth World Series in July, 2019. Womack was

aware of this deadline when they entered into this contract to construct the

complex, knowing time was of the essence.

In the Fall of 2018, Womack discussed with its subcontractor, Geo, a

problem with the liner on the fields allowing water to infiltrate the turf,

causing problems. This was not brought to the attention of the City or the

City’s architect until January, 2019, only six months prior to the beginning

of the World Series. This delay was, in fact, a major contributor to the entry

of change order #2. Had this information been shared with the City or its

architect upon discovery, then the City possibly would have been able to

exercise one of the several options stated by the majority in the opinion. The

1

delay in informing the City or the architect of this problem amounted to

duress on the part of Womack. Furthermore, the email between Womack and

Geo stating that, “I do not want any inspectors noticing and causing a

problem,” further evidences the fact that this knowledge was withheld. The

City’s architect, upon realizing there was a problem, stated that any costs

associated with remedying the problem should not be paid by the City. The

architect recognized, and even stated, that the delay and poor workmanship

was the reason for the change order #2.

Knowing the timeframe under which the City was operating, and

failing to disclose the defects in a timely manner, amounted to duress on the

part of Womack. By the time the City was informed of these defects, there

was no other option than to enter into change order #2 because of the

contract with Dixie Baseball. The majority states that this contract has no

bearing on the contract between Womack and the City and that any

economic distress felt by the City does not constitute duress. I disagree.

Womack entered into this contract knowing that time was of the essence.

Any delays caused by Womack should have been considered in applying the

standard for summary judgment.

In my opinion, genuine issues of material fact exist and preclude

summary judgment. I believe that the trial court should be reversed and the

matter remanded for further proceedings.

2