56,765-CA Precedential Affirmed Processed

Bossier Parish by and through the Bossier Parish Police Jury v. Boggs & Poole Contracting Group, Inc.

Louisiana Court of Appeal, Second Circuit · Filed February 25, 2026

Authorities cited

Identified automatically; this list may not be exhaustive.

Opinion text

Judgment rendered February 25, 2026.
Application for rehearing may be filed
within the delay allowed by Art. 2166,
La. C.C.P.

No. 56,765-CA

COURT OF APPEAL
SECOND CIRCUIT
STATE OF LOUISIANA

*****

BOSSIER PARISH BY AND THROUGH Plaintiff-Appellee
THE BOSSIER PARISH POLICE JURY

versus

BOGGS & POOLE CONTRACTING Defendant-Appellant
GROUP, INC.

*****

Appealed from the
Twenty-Sixth Judicial District Court for the
Parish of Bossier, Louisiana
Trial Court No. 172,938

Honorable Charles A. Smith, Judge

*****

SINCLAIR LAW FIRM, LLC Counsel for Appellant
By: Scott C. Sinclair

WIENER, WEISS & MADISON, APC Counsel for Appellee,
By: Geoffrey D. Westmoreland Bossier Parish by and
Reid Allen Jones through the Bossier
Parish Police Jury

PATRICK R. JACKSON Counsel for Appellee,
Bossier Parish

LONG LAW FIRM, LLP Counsel for Appellees,
By: Albert Dale Clary Prevot Design Services
Alec Brendan Keane and Civil Design Group

DONOHUE, PATRICK & SCOTT, PLLC Counsel for Appellee,
By: Leigh F. Groves Estes, McClure &
Associates, Inc. D/B/A
EMA Engineers &
Consultants

*****

Before ROBINSON, MARCOTTE, and ELLENDER, JJ.

ROBINSON, J.

Boggs & Poole Contracting Group, Inc. (“B&P”), which was awarded

a contract to build a new central branch public library in Bossier Parish,

appeals a judgment denying its petition for a writ of mandamus under La.

R.S. 38:2191 to order the Bossier Parish Police Jury (“Bossier”) to make the

final payment under the construction contract.

Concluding that mandamus was not available because the final

payment was not due under the construction contract when the project

architect had not approved the final payment, we affirm the judgment.

FACTS

B&P agreed to construct the library for $9,267,001. Substantial

completion was to be reached within 365 days from the start of the work.

B&P agreed to pay $2,500 in liquidated damages for each calendar day that

the project was inexcusably delayed in meeting substantial completion.

B&P provided a performance bond executed by Travelers Casualty and

Surety Company. The contract was awarded to B&P on October 6, 2021.

The official start date of the project was October 25, 2021. After

B&P requested extensions, Bossier agreed to move the deadline for

substantial completion to July 5, 2023.

The project architect, Prevot Design Services, issued a certificate of

substantial completion on December 4, 2023. On January 10, 2024, Bossier

voted to accept the certificate of substantial completion, which was recorded

in the Bossier Parish mortgage records on January 11, 2024. The clerk of

court issued a clear lien certificate on February 27, 2024. The library

opened to the public on March 11, 2024.

Change orders had increased the construction cost to $9,342,355.87.

Bossier has paid $8,715,977 to B&P, leaving an unpaid balance of

$626,378.87.

The construction contract provides in Section 5.2.1 that final payment

shall be made to B&P when (1) B&P has fully performed the contract except

for B&P’s responsibility to correct work and to satisfy other requirements, if

any, which extend beyond final payment, and (2) a final certificate of

payment has been issued by the architect.

Section 9.5.1 of the contract states:

The Architect may withhold a Certificate for Payment in whole
or in part, to the extent reasonably necessary to protect the
Owner, if in the Architect’s opinion the representations to the
Owner required by Section 9.4.2 cannot be made. . . . The
Architect may also withhold a Certificate for Payment or,
because of subsequently discovered evidence, may nullify the
whole or a part of a Certificate for Payment previously issued,
to such extend as may be necessary in the Architect’s opinion to
protect the Owner from loss for which the Contractor is
responsible, including loss resulting from acts and omissions
described in Section 3.3.2. . . .

The contract also provides in Section 9.10.1 that when the architect

finds the work acceptable under the contract documents and the contract

fully performed, the architect will promptly issue a final certificate for

payment stating to the best of the architect’s knowledge, information, and

belief, and on the basis of the architect’s onsite visits and inspections, the

work was completed in accordance with the contract and the entire balance

found to be due to the contractor and noted in the final certificate was due

and payable.

Section 9.10.2 of the contract states that neither final payment nor any

remaining retained percentage shall become due until B&P submits to the

2

architect: (1) an affidavit that payrolls, bills for materials and equipment, and

other indebtedness connected with the work for which Bossier or Bossier’s

property might be responsible or encumbered (less amounts withheld by

Bossier) had been paid or otherwise satisfied; (2) a certificate evidencing

that insurance required by the contract documents to remain in force after

final payment was currently in effect; (3) a written statement that B&P knew

of no reason that the insurance would not be renewable to cover the period

required by the contract documents; (4) consent of the surety, if any, to final

payment; (5) documentation of any special warranties, such as

manufacturers’ warranties or specific subcontractor warranties; and (6) if

required by Bossier, other data establishing payment or satisfaction of

obligations, such as receipts and releases and waivers of liens, claims,

security interests, or encumbrances arising out of the contract to the extent

and in such form as may be designated by Bossier.

On February 27, 2024, B&P submitted a payment application to

Prevot. On April 4, 2024, B&P requested that Bossier pay the total contract

price minus the value of certain punch list items.

Prevot did not approve the final payment application. On April 17,

2024, Prevot wrote to B&P that given the value of the liquidated damages

and unresolved issues concerning outstanding architectural, MEP, and civil

items, it could not recommend payment at the time because it was unable to

provide the representations to Bossier as required by Section 9.4.2 and as

outlined in Section 9.5.

On April 29, 2024, Bossier Parish filed suit against B&P. Bossier

alleged that B&P owed $377,500 in liquidated damages for 151 days of

3

unexcused delays. Bossier also alleged that B&P failed to install a dry pipe

sprinkler system as set forth in the construction contract. It estimated the

cost to convert the system to a dry system would be $245,000. Bossier

further alleged that B&P failed to complete several items of work. Finally,

Bossier alleged that there were construction defects from B&P’s failure to

construct the library in accordance with the plan and specifications. Bossier

alleged that the cost to correct the defects and finish the work would likely

exceed $48,000.

In its lawsuit, Bossier sought a declaratory judgment that it was not

liable for payment of the remaining balance because of damages owed by

B&P. It also sought damages for the cost to complete the project and to

resolve all construction defects that will exceed the remaining balance

because of B&P’s alleged breach of the construction contract.

On December 12, 2024, B&P filed an answer, a reconventional

demand, and a third party demand. Prevot Design Services, EMA

Engineering & Consulting, Inc., and Civil Design Group, LLC, were named

as third party defendants. B&P asserted a claim against Bossier for the

balance due under the construction contract, which B&P alleged was

$626,378.87 and was due 45 days following receipt of the clear lien

certificate. B&P contended it was owed attorney fees and interest as

allowed under La. R.S. 38:2191. B&P also asserted a claim against Bossier

for delay damages of $259,999.26.

B&P asserted a claim against Bossier, Prevot, and Civil Design for a

declaratory judgment that the cracking of the concrete paving in the parking

lot was caused by a defective design. B&P also sought a declaratory

4

judgment against Bossier, Prevot, and EMA that the specifications called for

the installation of a wet sprinkler system, that Bossier accepted it, and that

Bossier was estopped from asserting a claim for a dry sprinkler system.

B&P contended that if Bossier was awarded any judgment against it related

to the sprinkler system, then B&P was entitled to judgment in a like amount

against Prevot and EMA in solido.

On July 21, 2025, B&P’s attorney wrote to Bossier making a final

demand for payment of the remaining balance of $626,378.87. Sent along

with the demand letter was Harry Boggs’s affidavit of project completion,

which stated that B&P had complied with the six requirements set forth in

Section 9.10.2 of the contract.

On July 29, 2025, B&P filed a petition for a writ of mandamus

seeking final payment of $626,378.87 under the construction contract.

On August 5, 2025, Bossier filed an amended and supplemental

petition. It added Travelers Casualty and Surety Company as a defendant.

Bossier also sought a declaratory judgment that it was not liable to B&P for

any further payment for its work on the project. Bossier alleged that B&P

had breached the construction contract by failing to complete the project

within the required time period, failed to complete all items within the

required scope of work, installed a noncompliant fire suppression system,

and performed defective work. Bossier alleged that as B&P’s surety under

the performance bond, Travelers was liable to Bossier for all damages

resulting from B&P’s breaches and defaults, and was required to remedy

those breaches and defaults.

5

On August 14, 2025, Bossier filed an exception of unauthorized use of

summary proceedings and an exception of no cause of action as to the

petition for a writ of mandamus. Bossier argued that mandamus under La.

R.S. 38:2191 is only available when final payment is due under the contract,

and it was not due because Prevot had not approved the final payment

application, which is a discretionary function. Bossier further argued that

this case is inappropriate to be resolved on mandamus because of its

complexity as it involves highly technical contracts, plans, and

specifications.

A hearing on the petition for a writ of mandamus and on Bossier’s

exceptions was held on August 28, 2025. After the court overruled the

exceptions and indicated that it would deny the petition, it accepted evidence

and heard testimony from Henry Boggs, the Vice-President of B&P. Boggs

testified that all items had been completed, and that there were just questions

remaining about whether they had been completed correctly. He also

testified that all the requirements of Section 9.10.2 had been met. He further

testified that around $288,000 was owed to subcontractors, who are subject

to a pay-when-paid clause.

The trial court concluded that mandamus was not proper at that time

because the contract required approval by the project architect, which had

not been given.

On September 8, 2025, the trial court rendered judgment overruling

Bossier’s exceptions to the petition for a writ of mandamus and denying the

petition. B&P has appealed.

6

DISCUSSION

The starting point for the interpretation of any statute is the language

of the statute itself. McBride v. Old Republic Insurance Company, 24-01519

(La. 6/27/25), 413 So. 3d 452. When a law is clear and unambiguous and its

application does not lead to absurd consequences, the law shall be applied as

written and no further interpretation may be made in search of the intent of

the legislature. La. C.C. art. 9.

It is presumed that every word, sentence, or provision in a law is

intended to serve some useful purpose, that some effect is given to each such

provision, and that no unnecessary words or provisions were employed.

Colvin v. Louisiana Patient’s Compensation Fund Oversight Bd., 06-1104

(La. 1/17/07), 947 So. 2d 15. Courts are thus bound to give effect, if

possible, to all parts of a statute and to construe no sentence, clause, or word

as meaningless and surplusage if a construction giving force to and

preserving every word can legitimately be found. Id.

A writ of mandamus is an extraordinary remedy that is directed at a

public officer to compel the performance of a ministerial duty required by

law. Jazz Casino Company, L.L.C. v. Bridges, 16-1663 (La. 5/3/17), 223 So.

3d 488.

Ministerial duties are duties in which no element of discretion is left

to the public officer. Hoag v. State, 04-0857 (La. 12/1/04), 889 So. 2d 1019.

If a public officer is vested with any element of discretion, mandamus will

not lie. Id.

Where statutory interpretation is at issue in a mandamus proceeding,

a de novo standard of review is used on appeal. Town of Sterlington v.

7

Greater Ouachita Water Company, 52,482 (La. App. 2 Cir. 4/10/19), 268

So. 3d 1257, writ denied, 19-00913 (La. 9/24/19), 279 So. 3d 386, and writ

denied, 19-00717 (La. 9/24/19), 279 So. 3d 931.

La. R.S. 38:2191, which concerns payments under public contracts

states:

A. All public entities shall promptly pay all obligations
including approved change orders, arising under public
contracts when the obligations become due and payable under
the contract. All progressive stage payments and final
payments shall be paid when they respectively become due and
payable under the contract.

B. (1) Any public entity failing to make any progressive stage
payment within forty-five days following receipt of a certified
request for payment by the public entity without reasonable
cause shall be liable for reasonable attorney fees and interest
charged at one-half percent accumulated daily, not to exceed
fifteen percent. Any public entity failing to make any final
payments after formal final acceptance and within forty-five
days following receipt of a clear lien certificate by the public
entity shall be liable for reasonable attorney fees and interest
charged at one-half percent accumulated daily, not to exceed
fifteen percent.
(2) Any interest received by the contractor pursuant to
Paragraph (1) of this Subsection, shall be disbursed on a
prorated basis among the contractor and subcontractors, each
receiving a prorated portion based on the principal amount due
within ten business days of receipt of the interest.

C. The provisions of this Section shall not be subject to waiver
by contract.

D. Any public entity failing to make any progressive stage
payments arbitrarily or without reasonable cause, or any final
payment when due as provided in this Section, shall be subject
to mandamus to compel the payment of the sums due under the
contract up to the amount of the appropriation made for the
award and execution of the contract, including any authorized
change orders.

E. A declaration that a public works contract is null and void as
being contrary to the provisions of R.S. 38:2211 et seq. shall
not affect amounts due and payable under the contract,
including overhead and profit, for the work performed by or on
behalf of the contractor.

8

Subsection (D) was added by Act 184 of 2011.

B&P states that the sole question on appeal is whether the trial court

properly relied on the contract terms to determine when final payment was

due for the purposes of La. R.S. 38:2191(D). B&P contends that the express

terms of La. R.S. 38:2191 show that the trial court was incorrect and that the

court’s interpretation was contrary to the rules of statutory construction.

B&P argues that Subsection (D) refers to Subsection (B) to determine

when final payment is due because that is the only subsection which

provides when final payment is due. Thus, B&P contends that a final

payment becomes due under La. R.S. 38:2191(D) when two things occur:

first, when formal final acceptance is established through the issuance and

recordation of a substantial completion certificate, and second, 45 days

following receipt of a clear lien certificate. B&P maintains that it is entitled

to mandamus because both of those had occurred. B&P adds that the fact

that Prevot did not issue a certificate for payment cannot defeat Bossier’s

liability under Subsection (B)(1).

B&P maintains that if the legislature only intended for mandamus to

be available when the public entity failed to make final payment when due

“under the contract,” then it would have stated so.

Bossier counters that payment was not due for purposes of mandamus

because it was not due under the contract since Prevot had not given

approval for final payment. Bossier argues that Prevot’s approval was a

prerequisite for final payment, and that adopting B&P’s position would

“wreak havoc” on public contracting by forcing public entities to make final

payments before contractual conditions are met.

9

Bossier maintains that Subsection (A) answers when final payment is

due under Subsection (D). Bossier notes that the words “when” and “due”

are completely absent from Subsections (B) and (C).

In support of its argument, B&P relies on Woodrow Wilson

Construction LLC v. Orleans Parish School Board, 17-0936 (La. App. 4 Cir.

4/18/18), 245 So. 3d 1, writ denied, 18-0971 (La. 10/8/18), 253 So. 3d 793.

Wilson was awarded a contract to build a school. After receiving a

certificate of substantial completion, Wilson submitted an application for

final retainage payment, lien waivers, and a clean lien certificate. When the

school board failed to make the final payment, Wilson filed a petition to

enforce the contract and a petition for a writ of mandamus. The school

board asserted that it was allowed to withhold payment because it was

entitled to liquidated damages. The trial court denied the petition for a writ

of mandamus, concluding that La. R.S. 38:2191 was not applicable because

there was a question of whether final payment was due under the contract.

The appellate court in Wilson first addressed the board’s exception of

no cause of action, which was raised for the first time on appeal and

premised on the ground that the petition for a writ of mandamus did not

name a public official as a defendant. The Wilson court noted that La. R.S.

38:2191(D) stated that a public entity shall be subject to mandamus. The

court denied the exception, concluding that La. R.S. 38:2191(D) superseded

the more general civil code articles dealing with mandamus.

Turning to the mandamus claim, the Wilson court stated that the real

issue in dispute was when final payment was considered due under the terms

of the contract. The court noted that the contract provided that payment for

10

normal retainage was due when six things occurred, and those six

enumerated contractual requirements had been fully satisfied. Moreover, the

requirements under La. R.S. 38:2191(B) of formal final acceptance of the

work and the owner receiving a clear lien and privilege certificate were

replicated in the enumerated requirements and were met when Wilson

satisfied the contract’s requirements.

Relying on a different contract provision, the school board countered

that because the amount owed by Wilson in liquidated damages exceeded

the amount owed in retainage, final payment was not due under the contract

and La. R.S. 38:2191 did not apply. However, the court noted that while

that provision allowed the school board to withhold liquidated damages in

any way, including by withholding final payment, any alleged right to

withhold payment arose only when payment became due. Thus, the school

board could not rely on that contract provision without acknowledging that

the final retainage payment was due. The Wilson court recognized that the

school board’s ministerial duty to tender payment arose upon satisfaction of

the enumerated contract requirements, which in turn satisfied La. R.S.

38:2191(B). As a result, the school board had no discretionary authority to

withhold payment under the different contract provision when the

requirements of La. R.S. 38:2191 had been met and a ministerial duty was

owed. The court added that the school board’s reliance on the provision was

ill-founded because of La. R.S. 38:2191(C)’s express prohibition against

contractually waiving the ministerial duty.

The Wilson court concluded that because Wilson had satisfied the

requirements of La. R.S. 38:2191, final payment became due and payable,

11

and the board had a ministerial duty to issue final payment and had no

discretion to withhold payment based on a separate claim against Wilson.

We recognize that in Wilson, the fourth circuit began its analysis by

addressing whether six requirements in the contract for payment had been

satisfied. Furthermore, there is no indication that the contract in Wilson

required specific architect approval for payment.1

B&P also relies on Law Industries, LLC v. Board of Supervisors of

Louisiana State University, 18-1756 (La. App. 1 Cir. 3/2/20), 300 So. 3d 21,

writ denied, 20-00745 (La. 10/6/20), 302 So. 3d 515. There, the contractor

filed a petition for a writ of mandamus to collect an outstanding contract

balance of $29,000. The trial court denied the petition, noting that it

believed the defendant had a contractual right to an offset for liquidated

damages, and that there was element of discretion by LSU as to the amount

due once the liquidated damages were applied. The first circuit reversed,

concluding that the plaintiff could seek payment through a mandamus

proceeding, and the trial court would determine in the summary proceeding

what sum was owed under the contract, including the amount of liquidated

damages.

Similar to Wilson, there is no indication in Law that architect approval

was required for final payment. We also note that in Law, the court

recognized the link between Subsections (A) and (D). The court stated:

Pursuant to La. R.S. 38:2191(A), all contracting public entities
“shall” pay all obligations, progressive stage payments, and
final payments when they become due and payable under the
contract. The use of the word “shall” in this provision
unequivocally expresses a public entity’s mandatory duty to

1
We acknowledge that among the enumerated requirements was that the architect
and owner approve and accept the certificate of substantial completion.

12

fulfill its contractual obligations as they become due. Should a
public entity fail to fulfill its mandatory duty under La. R.S.
38:2191(A), subsection D, again employing the mandatory
“shall,” subjects the public entity to a mandamus proceeding to
compel payment of the sums due under the contract. Wallace C.
Drennan, Inc. v. St. Charles Parish, 2016-177 (La. App. 5 Cir.
9/22/16), 202 So.3d 535, 544.

Id., 18-1756 at p. 7, 300 So. 3d at 26.

In support of its position, Bossier cites Stevens Construction &

Design, L.L.C. v. St. Tammany Fire Protection District No. 1, 19-0955 (La.

App. 1 Cir. 7/8/20), 308 So. 3d 724, writ denied, 20-00990 (La. 11/4/20),

303 So. 3d 652. Stevens served as the general contractor for the

construction of a new fire station and headquarters building. After Stevens

was terminated, it submitted three pay applications, none of which were

certified by the project architect. Stevens filed a petition for a writ of

mandamus seeking to compel payment of five pay applications, including

the three submitted after termination. Following a hearing, the trial court

dismissed the petition for a writ of mandamus.

The first circuit in Stevens read Subsection (D) as allowing mandamus

relief against public entities when the public entity failed to tender a final

payment when due under the contract. The court added:

Thus, in order to be entitled to mandamus relief against the Fire
District, Stevens Construction must establish that the Fire
District “arbitrarily or without reasonable cause” failed to make
progressive stage payments or failed to make final payment
“when due” under the contract. . . . The public entity is not
subject to mandamus compelling payment when the terms of
the contract give the public entity discretion as to whether
payment is due and payable. Mandamus relief under La. R.S.
38:2191 is available only when there is no discretion left to the
public entity as to whether payment is due and payable under
the terms of the contract.

Id., 19-0955 at p. 11, 308 So. 3d at 732. Citations omitted.

13

Affirming the trial court, the first circuit noted that the provisions of

the construction contract did not mandate payment under the circumstances

and allowed for discretion in payment when the provisions of the

construction contract were not met. Evidence presented at the hearing

included letters from the project architect explaining the reasons for

withholding payment. The fire district had not failed to tender final payment

when due under the contract.

Bossier further cites LA Contracting Enterprise, LLC v. South

Lafourche Levee District, 24-0272 (La. App. 1 Cir. 12/20/24), 404 So. 3d

898, where the levee district contracted with LA Contracting to construct a

ramp. After the levee district terminated the contract, LA Contracting

submitted a final application for payment. The engineering firm tasked with

reviewing the payment applications instructed LA Contracting to amend and

resubmit it. The engineering firm later advised that it would approve a

payment amount that was less than that sought by LA Contracting. LA

Contracting filed a suit for mandamus pursuant to La. R.S. 38:2191. The

trial court determined that mandamus was not available. The judgment was

affirmed.

The first circuit noted that while it had previously held that the general

rules of mandamus have limited application when mandamus is sought

under La. R.S. 38:2191, a public entity is not subject to mandamus

compelling payment when the contract gives the public entity discretion as

to whether payment is due and payable.

Although the payment application was characterized as a “progressive

stage payment” rather than a “final payment,” we note that the LA

14

Contracting court cited the above-quoted language from Stevens as well as

language that Subsection (D) makes mandamus relief available when a

public entity had failed to tender final payment when due under the contract.

We agree with the rationale in Stevens Construction and LA

Contracting and interpret La. R.S. 38:2191(D) to mean that final payment

can be compelled only when final payment is due under the contract. Here,

final payment is not due under the contract because the project architect,

within its discretion, has not approved the final payment application.

Finally, the contract terms making Prevot’s approval of final payment

a prerequisite to final payment does not run afoul of Subsection (C)’s

prohibition because the contract contained no express waiver of the

protections afforded by the statute.

CONCLUSION

For the foregoing reasons, the judgment denying the petition for a writ

of mandamus is affirmed at B&P’s costs.

AFFIRMED.

15