CA-0004-0173 Nonprecedential Affirmed Processed

Don M. Barron Contractor, Inc. v. City of Natchitoches, Louisiana

Louisiana Court of Appeal, Third Circuit · Filed July 7, 2004

Opinion text

STATE OF LOUISIANA
COURT OF APPEAL, THIRD CIRCUIT

04-173

DON M. BARRON CONTRACTOR, INC.

VERSUS

CITY OF NATCHITOCHES, LOUISIANA

**********

APPEAL FROM THE
TENTH JUDICIAL DISTRICT COURT
PARISH OF NATCHITOCHES, NO. 76468, DIVISION B
HONORABLE FRED C. SEXTON, JR., DISTRICT JUDGE

**********
ULYSSES GENE THIBODEAUX
CHIEF JUDGE
**********

Court composed of Ulysses Gene Thibodeaux, C.J., Billie Colombaro Woodard, and
Marc T. Amy, Judges.

AMY, J., CONCURS AND ASSIGNS REASONS.

AFFIRMED.

Daniel T. Murchison, Sr.
Murchison and Murchison, L.L.C.
P. O. Box 226
Natchitoches, LA 71458-0226
Telephone: (318) 352-2303
COUNSEL FOR:
Defendant/Appellee - City of Natchitoches, Louisiana

Mark Watkins Odom
Booth Lockard Politz LeSage Hayter & Odom, L.L.C.
P. O. Drawer 1092
Shreveport, LA 71163
Telephone: (318) 222-2333
COUNSEL FOR:
Plaintiff/Appellant - Don M. Barron Contractor, Inc.

Mark Alexander Begnaud
McCoy Roberts & Begnaud
P. O. Box 1369
Natchitoches, LA 71458-1369
Telephone: (318) 352-6495
COUNSEL FOR:
Intervenor/Appellee - CBC Services, Inc.

THIBODEAUX, Chief Judge.

In this public bid law case, plaintiff-appellant, Don M. Barron

Contractor, Inc. (Barron), the second lowest bidder on a city construction project,

appeals the judgment of the trial court in favor of the City of Natchitoches, Louisiana

(the City). The judgment dismissed Barron’s petition for injunctive relief recalling

the temporary restraining order it obtained on December 12, 2003. Barron sought

injunctive relief against the City to prevent it from contracting with CBC Services,

Inc. (CBC), the apparent low bidder for the construction of an alternate water supply

for the City. For the following reasons, we affirm the judgment of the trial court.

I.

ISSUE

The issue in this case is whether the trial court properly applied La.R.S.

38:2212 (A)(1)(a), also called the “Public Bid Law,” where the lowest bidder did not

properly fill in the blanks of the bid form supplied by the City to potential

construction bidders.

II.

FACTS

The facts of this case are not disputed. Sibley Lake provides water for

the City. To supply an alternate water source for the city in times of drought, the City

decided to connect Sibley Lake with Bayou Pierre. Thereafter, the City advertised for

bids on the construction project that would link the two water bodies. Public bids

were opened in November 2003. CBC and Barron were two of the seven companies

that bid on the project. The City determined that CBC provided the lowest bid at

$1,449,180.00, and Barron provided the second lowest bid at $1,502,633.50, a

1

difference of $53,453.50. After a meeting of the City’s evaluation committee, the City

chose to award the contract to CBC.

Barron objected to the City’s action awarding the contract to CBC.

However, its objection was to no avail as the City Council voted unanimously to

award the project contract to CBC because it was the lowest responsible bidder.

Thereafter, Barron filed a petition for injunctive relief seeking a temporary restraining

order and preliminary injunction against the City to enjoin it from executing the

contract with CBC for the construction of the alternate water supply project. CBC

intervened supporting the City’s position in this matter. Barron alleged that it, not

CBC, was actually the lowest responsible bidder because CBC failed to complete the

City’s bid form correctly.

The portion of the bid form regarding the price of the top soil required

to complete the project is at issue. Portions of the City’s bid form required that the

bidders provide prices based on the per unit cost of a listed item. In one column, the

amount per unit of material is to be written in both words and numerals. The form

provided that “[i]n case of discrepancy, the amount in words will govern.” The bid

form stated that the project would require 250 cubic yards of top soil. Thus, in the

unit price column, the bidders were required to write the price of one cubic yard of

soil. In the last column, the bidder is required to provide the total cost by multiplying

the cost per cubic yard of topsoil by 250 cubic yards. In the present case, CBC

correctly noted the topsoil at $20.00 per cubic yard in the blank provided for placing

the cost in numeric terms. However, in the blank provided for writing out the

monetary term in words, CBC wrote out the total cost of providing topsoil for the

project instead of writing the unit price of “twenty dollars and no/100.” Thus, from

the words written in that blank, it appears that CBC quoted a $5,000.00 unit price for

the topsoil, which, when calculated, results in a total cost, for just the project’s topsoil

2

needs, of $1,250,000.00, which would make CBC’s bid clearly higher than Barron’s

bid when the cost of the remainder of the project’s needs are taken into account. CBC

did correctly write the total cost of $5,000.00 based on the $20.00 per unit of topsoil

in the total column.

In response to Barron’s petition, the trial court entered a temporary

restraining order. On December 18, 2003, after a hearing, the trial court recalled the

temporary restraining order and dismissed Barron’s petition for injunctive relief. It

is from this action by the trial court that Barron appeals.

III.

LAW AND DISCUSSION

Barron argues that the trial court committed legal error in finding that the

public bid law does not prohibit the acceptance of bids that are not completed in

conformity with the bid form provided by the public agency requesting bids. Barron

asserts that the trial court erred in finding that CBC submitted the lowest bid where

the unit price of the topsoil quoted by CBC would make CBC the highest bidder on

the City’s water project.

Public contracts are governed by Title 38 of the Louisiana Revised

Statutes, Public Contracts, Works & Improvements. Specifically, La.R.S. 38:2212

A(1) regulates the awarding of public works contracts and provides:

(a) All public work exceeding the contract limit as
defined in this Section, including labor, materials, to be
done by a public entity shall be advertised and let by
contract to the lowest responsible bidder who had bid
according to the contract, plans, and specifications as
advertised, and no such public work shall be done except as
provided in this part.

(b) The provisions and requirements of this Section,
those stated in the advertisement for bids, and those
required on the bid form shall not be considered as
informalities and shall not be waived by any public entity.

3

Further, La.R.S. 38:2212, which requires that public contracts be advertised and

competitive bids be obtained prior to a public entity contracting for public works, “is

a prohibitory law founded on public policy. It was enacted in the interest of tax

paying citizens of this state, and its purpose is to protect these citizens against

contracts of public officials awarded through favoritism and possibly involving

exorbitant and extortionate prices.” Mickey O’Connor Gen. Contractor, Inc. v. City

of Westwego, 01-825, p. 4 (La.App. 4 Cir. 11/27/01), 804 So.2d 128, 130, writ denied,

01-3391 (La. 3/15/02), 811 So.2d 908 (citations omitted). In Haughton Elevator Div.

v. State, 367 So.2d 1161 (La.1979), the supreme court instructed that when awarding

a public works contract, the public agency is vested with the power and discretion to

determine the responsibility of the bidder and to reject all bids if none is satisfactory.

The public agency cannot arbitrarily select a bid that is higher and reject bids that are

lower. Mickey O’Connor Gen. Contractor, Inc., 804 So.2d 128. All that is required

of the awarding public agency, after careful consideration of the bid document, is that

it act in a manner that is not arbitrary. Williams v. Board of Sup'rs, 388 So.2d 438

(La.App. 2 Cir. 1980).

In the present case, the City interpreted the CBC bid on the 250 cubic

square yards of topsoil at $20.00 per unit for a total of $5,000.00. It chose to rely on

the amount in the bid form written in numerals, which corresponded to CBC’s total

cost for providing all of the topsoil, instead of the amount written in words. The

primary issue presented for our review is whether this interpretation by the City is

arbitrary or is an abuse of discretion.

There is no question that the CBC bid, with respect to the unit price of

the topsoil, contained a discrepancy between the amount written in words and the

amount written in numerals. There is also no question that CBC’s bid for the total

cost of the 250 cubic yards of topsoil corresponded with the unit price amount written

4

in numerals. The record indicates, and Barron points out, that note 2 of the bid form

on page 8 stated that the amounts quoted are to be shown in both words and figures

and that, in case of discrepancy, the amount shown in words would prevail. Barron

argues that a discrepancy exists with respect to CBC’s bid on the unit price of topsoil;

therefore, the $5,000.00 unit price written out in words should prevail over the $20.00

unit price written in figures.

To support its position, Barron cites La.R.S. 38:2220 (A) which provides

that public contracts entered into contrary to the Public Bid Law are null and void, and

the requirements of the bid form cannot be waived by the public entity. La.R.S.

38:2212 (A)(1)(b). Accordingly, because CBC did not complete the bid form as

required and given that the City has no authority to waive the requirement, the City

should not have entered into a contract with CBC for construction of the alternate

water supply system.

Further, Barron argues that this court’s decision in V.C. Nora, Jr. Bldg.

& Remodeling, Inc. v. State, through Dep’t of Transp. & Dev., 93-1469 (La.App. 3

Cir. 3/30/94), 635 So.2d 466 directly addresses the issue in the present case and is

binding. We disagree. In Nora, the Louisiana Department of Transportation (DOTD)

received a bid from Nora. Nora completed the form by writing out the total amount

for the various items as opposed to the unit price. Like the bid form in the present

case, some items were to be priced in total and some were to be priced per unit.

However, unlike the present case, the bid form in Nora with respect to items to be

priced by unit, did not have a blank or a column within which a bidder could write out

the price in numbers. Further, the Nora bid form had no column in which the unit

price could be multiplied by the number of units needed to get a total cost for the

amount of that item needed. Thus, there was no way for the DOTD to determine,

from the document, whether the amount written in the blank was the unit price or total

5

price. Apparently, the City in the present case addressed the problem of Nora in its

bid form where it provided separate blanks for numerically writing the price and for

writing the price in words as well as a separate column for the total. As we stated in

Nora:

While under the present facts it is apparent Nora
intended its bid to be $239,358 and not $41 million, this
conclusion requires an interpretation outside the four
corners of the bid. We cannot deny that by ordering DOTD
to accept a bid subject to different interpretations, we may
be injecting ambiguity into the public bidding process. . . .
[S]uch ambiguity would erode the objective basis upon
which contracts are awarded and thereby open a “Pandora’s
box” to the favoritism and corruption that the public bid
laws were established to prevent.

V.V. Nora, Jr. Bldg. & Remodeling, Inc., 466 So.2d at 472. Finally, in Nora, DOTD

was questioning compliance with its bid forms. Here, the City submits that CBC

conformed substantially to the City’s bid requirements. To the extent that we must

give deference to a governmental agency’s decision vis-a-vis a public bid contract, our

decision is not inconsistent with Nora. See Haughton Elevator Div. v. State of La.,

367 So.2d 1161 (La.1979).

In this case, the City did not have to go outside the four corners of the

CBC’s bid form to determine CBC’s intent with respect to the cost of topsoil. All

relevant information was provided on the bid form. Under the circumstances

presented here, we find that the City’s interpretation of the question of the unit price

of the topsoil in CBC’s bid form is reasonable and is neither arbitrary nor capricious.

Based on the information provided on the bid form and a simple mathematical

calculation, it was reasonable for the City to conclude that CBC’s unit price for the

topsoil to be used in the project was $20.00 per unit as opposed to $5,000.00 per unit.

The City did not abuse its discretion in determining that CBC met the bid

requirements and was the lowest bidder.

6

The trial court found that CBC’s bid amount was apparent on the face of

the document despite the discrepancy between the unit price written in words and the

unit price written in numbers. Under the particular circumstances of this case, we

agree with the trial court’s conclusion that the CBC bid was merely a clerical error

easily corrected without the necessity of going outside of the four corners of the bid

document.

IV.

CONCLUSION

Because Barron has failed to show that the City abused its discretion in

its interpretation of CBC’s completed bid form or that it substantially deviated from

the public bid law, the trial court acted correctly in denying Barron’s request for

injunctive relief. Based on the foregoing, the judgment appealed from is affirmed. All

costs of this appeal are assessed to plaintiff-appellant, Don M. Barron Contractor, Inc.

AFFIRMED.

7

NUMBER 04-173

COURT OF APPEAL, THIRD CIRCUIT

STATE OF LOUISIANA

DON M. BARRON CONTRACTOR, INC.

VERSUS

CITY OF NATCHITOCHES, LOUISIANA

AMY, J., concurring.

In my opinion, the proper focus in the matter on appeal is whether the

construction contract at issue was awarded to CBC as a result of arbitrary conduct on

the part of the City of Natchitoches. It is apparent from the face of the bid sheet that

the portion of CBC’s bid pertaining to topsoil totalled $5,000 and that this figure was

derived by multiplying $20.00 by 250 cubic feet. It is likewise apparent that the City

of Natchitoches readily understood what was intended in this portion of CBC’s bid,

and, as such, it did not act arbitrarily in awarding the contract to CBC.

The appellant cites V.C. Nora, Jr. Building and Remodeling, Inc. v. State,

through Department of Transportation & Development, 93-1469 (La.App. 3 Cir.

3/30/94), 635 So.2d 466, for the proposition that the written words found on a bid

sheet govern in situations in which written and numeric bids conflict. In reliance upon

Nora, the appellant argues that the written portion of CBC’s topsoil bid, “Five

thousand dollars and zero cents,” is, in fact, CBC’s unit price for topsoil instead of the

numeric “$20.00” that appears therein. In my opinion, however, the present appeal

does not implicate Nora. In Nora, a panel of this court commented that a proper

interpretation of the ambiguous bid in dispute would necessitate reference to

information outside the bid sheet’s four corners; as such, the panel determined that the

written figures on the bid sheet were to be used in calculation instead of the numeric

figures listed. However, in the present appeal, the bid at issue is not ambiguous.

Moreover, the interpretation urged by the appellant would yield an obviously incorrect

result.

Finally, it is worth remembering that an underlying purpose of the public bid

law is to promote fair and responsible decision making by public entities. It is my

opinion that in the instant matter, the City of Natchitoches’ actions with respect to

CBC’s bid were not in contravention of these principles.

Accordingly, I respectfully concur in the result reached by the majority.