CA-0005-1255 Nonprecedential Remanded Processed

Smit Land & Marine, Inc. v. Whc, Inc.

Louisiana Court of Appeal, Third Circuit · Filed May 3, 2006

Authorities cited

Identified automatically; this list may not be exhaustive.

Opinion text

STATE OF LOUISIANA
COURT OF APPEAL, THIRD CIRCUIT

05-1254 consolidated with 05-1255

SMIT LAND & MARINE, INC.

VERSUS

WHC, INC.

**********

APPEAL FROM THE
SIXTEENTH JUDICIAL DISTRICT COURT
PARISH OF ST. MARTIN, NO. 99-61611 & NO. 99-61612
HONORABLE KEITH RAYNE JULES COMEAUX, DISTRICT JUDGE

**********

ULYSSES GENE THIBODEAUX
CHIEF JUDGE

**********

Court composed of Ulysses Gene Thibodeaux, Chief Judge, Jimmie C. Peters, and J.
David Painter, Judges.

APPEAL DISMISSED; ORDER
VACATED AND CASE REMANDED.

Bernard E. Boudreaux, Jr.
Murphy J. Foster, III
Breazeale, Sachse & Wilson, L.L.P.
One American Place - Suite 2300
P. O. Box 3197
Baton Rouge, LA 70821-3197
Telephone: (225) 387-4000
COUNSEL FOR:
Defendant/Appellant - WHC, Inc.

Lloyd Noble Shields
650 Poydras Street - Suite 2400
New Orleans, LA 70130
Telephone: (504) 581-4445
COUNSEL FOR:
Defendant/Appellant - WHC, Inc.

David Arthur Hurlburt
Hurlburt, Privat & Monrose
Post Office Drawer 4407
Lafayette, LA 70501
Telephone: (337) 237-0261
COUNSEL FOR:
Plaintiff/Appellee - Smit Land & Marine, Inc.

Robert Beattie McNeal
1100 Poydras Street - Suite 3600
New Orleans, LA 70163
Telephone: (504) 599-8014
COUNSEL FOR:
Defendant/Appellee - Exxon Mobile Pipeline Company

L. Katherine A. Theunissen
Mahtook & Lafleur
P. O. Box 3089
Lafayette, LA 70502
Telephone: (337) 266-2189
COUNSEL FOR:
Defendant/Appellee - National Union Fire Insurance Co.

Patricia Elise Weeks
Weeks & Gonzalez
400 Magazine Street - Suite 200
New Orleans, LA 70130
Telephone: (504) 799-2888
COUNSEL FOR:
Defendant/Appellee - Exxon Mobile Pipeline Company

THIBODEAUX, Chief Judge.

Plaintiff-appellee, Smit Land & Marine, Inc. (“Smit”), filed a motion for

partial summary judgment regarding its claim for nonpayment of fees allegedly owed

to it under its contract with defendant-appellant, WHC, Inc. (“WHC”). The trial court

granted the motion and certified the judgment as final pursuant to La.Code Civ.P. art.

1915(B). WHC has appealed the judgment as well as the trial court’s certification of

the judgment as final. For the following reasons, the appeal is dismissed, the order

certifying the partial summary judgment as final is vacated, and the case is remanded

for trial.

I.

ISSUES

1. Did the trial court err in certifying its judgment as
final and appealable pursuant to La.Code Civ.P. art.
1915(B)?

2. Did the trial court erroneously find that there is no
genuine issue of material fact as to Smit’s
entitlement to the unpaid fees?

II.

FACTUAL BACKGROUND

In this ongoing litigation, multiple parties are suing and/or being sued

for damages resulting from alleged acts of negligence, breach of contract, and

intentional tort, arising out of a pipeline construction job. This saga began on August

28, 1998, when Exxon Pipeline Company, now known as ExxonMobil Pipeline

Company (“Exxon”), hired general contractor, WHC, to construct approximately

forty-six miles of pipeline in an area extending from the vicinity of Anchorage,

Louisiana to the vicinity of St. James, Louisiana. This project was referred to as the

South Louisiana Pipeline Project (“the project”). On October 15, 1998, WHC hired

a subcontractor, Smit, to perform directional drilling work for four pipeline crossings

for the project. One of those crossings, known as the North Mississippi River

Crossing, is the subject of this dispute.

The North Mississippi River Crossing was to be placed under the

Mississippi River near Baton Rouge, Louisiana. The subcontract required Smit to

bore one hole of a sufficient capacity to house a single bundle of pipelines, consisting

of one twenty-four-inch pipeline and two twelve-inch pipelines. The work was to be

completed within twenty-five days. The final agreed upon price for the work to be

performed by Smit on the North Mississippi River Crossing was $898,388.15.

It is undisputed that this work was not completed in the manner

described by the subcontract. Rather, Smit completed the North Mississippi River

Crossing by drilling two holes instead of one—one hole was used for the placement

of the two twelve-inch pipelines and the other was used for the placement of the one

twenty-four-inch pipeline. In addition, this crossing was completed thirty to forty

days beyond the original twenty-five-day deadline. Smit explained that these contract

variations resulted because it was unprepared for soil conditions it encountered. Smit

claimed that this was a result of its reliance on erroneous soil condition information

set forth in the geotechnical report provided by Exxon.

The contractor, WHC, also had work obligations under the subcontract.

WHC was to provide Smit with equipment and personnel during its “pullback” and

“preream” operations of the drilling. According to WHC, these operations required

more work than originally expected because of the problems encountered by Smit on

the job. Therefore, WHC was necessarily required to provide additional supporting

work to Smit beyond what was originally set forth in the subcontract. WHC

submitted a claim to Smit in the amount of $621,410.77 for these additional support

services and withheld this amount from final payment to Smit.
2

Smit, in turn, sued WHC. It also filed a separate action in the same

district court1 against Exxon and Eustis Engineering Co., Inc. (“Eustis Engineering”),

the engineering firm that prepared the allegedly faulty geotechnical report for Exxon.2

In both suits, Smit sought payment of the unpaid subcontract fee of $621,410.77, as

well as $2,013,063.24 in additional costs it claims to have incurred during completion

of the North Mississippi River Crossing. Smit sought additional damages for

wrongful conversion of funds, unjust enrichment, breach of contract, and unfair trade

practices under the Louisiana Unfair Trade Practices Act.

Smit also sought, from WHC only, penalties for its nonpayment of funds

pursuant to La.R.S. 9:2784. Smit claimed that months had passed since WHC had

received its final payment from Exxon for all work under their principal contract;

however, it asserted that WHC had failed to pay it within fourteen days of receiving

those funds, in violation of La.R.S. 9:2784. Therefore, Smit asked the court to

impose the statute’s maximum penalty of fifteen percent ($93,211.61) of the

$621,410.77 being withheld, along with attorney fees.

WHC answered the petition and filed a reconventional demand, naming

as defendants, Smit; Exxon; Eustis Engineering; and Smit’s bonding company,

National Union Fire Insurance Co. (“National Union”).3 In its answer, WHC alleged

that Smit materially breached the contract, was negligent, and had been paid all sums

that it was due. Alternatively, WHC asserted the defenses of “set-off, reduction,

abatement or apportionment” in regard to any damages that it might be ordered to pay

1
The two lawsuits were consolidated on July 19, 2002.
2
WHC’s claims against Eustis Engineering were severed from its reconventional demand and
transferred to the 24th Judicial District Court after a contradictory hearing on Eustis Engineering’s
Motion to Dismiss in January, 2003.
3
National Union provided the performance and labor material bonds to guarantee the
performance by Smit of the work required by the subcontract.

3

as a result of Smit’s claims. WHC also asserted its claim for payment of the

$621,410.77 in costs and expenses it claimed to have incurred as a result of the

additional work it was required to perform.

Regarding both Exxon and Eustis Engineering, WHC claimed that they

were both negligent and liable to it for damages because they provided information

that did not accurately portray the soil conditions that would be encountered while

drilling for the pipeline crossings. WHC’s claims against Exxon also included breach

of contract claims for its failure to provide a defense to, or to indemnify it for, the

claims brought by Smit. WHC also asserted its contractual entitlement of a twenty

percent markup for all costs for which it may be ordered to pay Smit as a result of the

differing site conditions encountered by Smit on the job.

Smit filed a motion for partial summary judgment on February 4, 2004,

seeking a judgment on the issue of whether it was owed the subcontract balance of

$621,410.77 that was being withheld by WHC. In addition, it asked for summary

judgment on the issue of its entitlement to penalties and attorney fees from WHC for

late payment, pursuant to La.R.S. 9:2784.

The trial court granted Smit’s motion on the issue of its entitlement to

the unpaid balance of its subcontract in the amount of $621,410.77. The trial court

stated that no genuine issues of material fact existed that prevented a finding that

Smit was entitled to the fee. The trial court, however, declined to grant summary

judgment on the issue of the assessment of penalties under La.R.S. 9:2784. The court

wrote:

Jurisprudence provides that whether a general contractor
has reasonable cause to refuse to make payment to a
subcontractor on disputes [sic] amounts is a factual inquiry
that has to be made by the district court. U.S. ex rel. Cal’s
A/C [&] Elec. [v.] Famous Const. Corp., 220 F.3d 326,
329 (5[th] Cir. 2000). Because a factual inquiry is needed,
it is precluded from summary judgment on the issue of
4

attorney’s fees and penalties. Holiday City Builders, Inc.
v. Acadian Aviation Corp., 386 So.2d 1019, 1021 (La.App.
3 Cir. 1980).

Smit then moved to have the judgment certified as final and appealable

pursuant to La.Code Civ.P. art. 1915(B). WHC opposed the motion. In its Written

Reasons, the trial court stated that the judgment met the requirements for certification

and that there was no just reason for delaying the certification, reasoning that “the

unresolved issues in this case are sufficiently distinguishable from those issues

decided on the motion for partial summary judgment.”

WHC filed a suspensive appeal that challenges the certification of the

judgment as final and the trial court’s finding that there are no remaining genuine

issues of fact regarding whether Smit is entitled to the $621,410.77.

III.

LAW AND ANALYSIS

Certification of Judgment as Final Pursuant to La.Code Civ.P. art. 1915(B)

A partial summary judgment rendered pursuant to La.Code Civ.P. art.

966(E), such as the one at issue, may be immediately appealed during ongoing

litigation, but only after it has been properly designated as final by the trial court. See

Douglass v. Alton Ochsner Med. Found., 96-2825 (La. 6/13/97), 695 So.2d 953.

Accordingly, this court’s jurisdiction to decide this appeal hinges on whether that

certification was appropriate. Id.

Article 1915(B)(1) of the Code of Civil Procedure pronounces that in

order for a partial summary judgment granting relief to be designated as final for

appeal purposes, the trial court must expressly certify the judgment as final and

determine that there is no just reason for delay:

B. (1) When a court renders a partial judgment or
partial summary judgment or sustains an exception in part,
5

as to one or more but less than all of the claims, demands,
issues, or theories, whether in an original demand,
reconventional demand, cross-claim, third party claim, or
intervention, the judgment shall not constitute a final
judgment unless it is designated as a final judgment by the
court after an express determination that there is no just
reason for delay.

A final judgment determines the merits of a controversy in whole or in part. La.Code

Civ.P. art. 1841. Therefore, even though Article 1915 dispenses with finality in the

sense of completion of the litigation, the partial judgment that is rendered should be

sufficiently final; it should dispose of the claim or dispute in regard to which the

judgment is rendered. See Van ex rel. White v. Davis, 00-206 (La.App. 1 Cir.

2/16/01), 808 So.2d 478.

The trial court’s decision to certify a partial judgment as final for appeal

purposes is to be made on a case-by-case basis, with consideration being given to the

judicial administrative interests and equities involved. Curtiss-Wright Corp. v. Gen.

Elec. Co., 446 U.S.1, 100 S.Ct. 1460 (1980); see also Banks v. State Farm Ins. Co.,

30,868 (La.App. 2 Cir. 3/5/98), 708 So.2d 523. The court may consider the following

non-exclusive list of enumerated factors when determining whether a certain partial

judgment is one that may be immediately appealable:

1) The relationship between the adjudicated and
unadjudicated claims;

2) The possibility that the need for review might or
might not be mooted by future developments in the trial
court;

3) The possibility that the reviewing court might be
obliged to consider the same issue a second time; and

4) Miscellaneous factors such as delay, economic
and solvency considerations, shortening the time of trial,
frivolity of competing claims, expense, and the like.

6

R.J. Messinger, Inc. v. Rosenblum, 04-1664 (La. 3/2/05), 894 So.2d 1113 at 1122

(citing Allis-Chalmers Corp. v. Philadelphia Electric Co., 521 F.2d 360, 364 (3rd Cir.

1975)).

In this case, the trial court provided express, written reasons for its order

that designated the partial summary judgment as final for appeal purposes. Because

the trial court provided these explicit reasons for its determination, we are to review

the certification applying the abuse of discretion standard of review. See Messinger,

894 So.2d 1113. When applying this standard, great latitude is generally given, and

the trial court’s decision is not to be disturbed absent a finding of a clear abuse of

discretion. See Rourke v. Coursey, 338 So.2d 1197 (La.App. 3 Cir. 1976); see also

City of New Orleans v. New Orleans Canal, Inc., 173 So.2d 43 (La.App. 4 Cir. 1965).

In its Written Reasons, the trial court explained its decision to certify the

judgment as final for appeal purposes, as follows:

The court agrees with Smit that the unresolved issues in
this case are sufficiently distinguishable from those issues
decided on the motion for partial summary judgment. The
court previously determined that WHC owed to Smit
$621,410.77 for work performed and that WHC was not
entitled to any type of setoff. The court finds that WHC’s
unresolved issues in its reconventional demand are clearly
separate issues. Further, the court agrees with Smit that if
the judgment is not certified as final, WHC will have
succeeded in accomplishing indirectly what it could not do
directly; that is, to postpone the final judgment in hopes
that it can in the future setoff an unliquidated claim against
a liquidated one which this Court has already determined
there is no genuine issue of material fact. Finally, WHC’s
argument that it is concerned about the solvency of Smit is
not a sufficient concern to defeat certification. As argued
by Smit, it is also concerned about the solvency of WHC.
The court does not find that this concern has any serious
bearing on the merits of the certification.

We find that the trial court abused its discretion in certifying the partial judgment as

final for appeal purposes for multiple reasons: the existing relationship between the

adjudicated and remaining unadjudicated claims in this case, the possibility that
7

future case rulings may affect this judgment, and the possibility that this court may

have to consider this same issue in later appeals. See Curtiss-Wright, 446 U.S. 1.

This case contains cross-claims, as well as third-party claims of breach

of contract, negligence, and intentional tort, all of which arise out of the contracts and

work involved in the completion of the North Mississippi River Crossing. The trial

court’s certified judgment addressed only the slim issues placed before it by

Smit—whether the balance of the agreed upon subcontract price being withheld by

WHC ($621,410.77) was owed to Smit pursuant to the terms of the subcontract and

whether WHC was entitled to a “set-off” for its unadjudicated claims against Smit

under the subcontract. We disagree with the trial court’s position that its judgment

on the issue of Smit’s entitlement to the unpaid fee is sufficiently distinguishable

from the remaining claims. We find that when this case is considered as a whole, the

trial court’s finding of no genuine issue of material fact as to Smit’s entitlement to the

$621,410.77 is so interrelated to the remaining unadjudicated claims that it will

necessarily be affected by later judgments rendered in this case. For instance, it is

possible that this judgment could be rendered moot by a judgment ultimately rendered

in favor of WHC on its claim for accrued expenses in the exact amount as that which

has already been awarded to Smit. Moreover, subsequent rulings on liability for the

remaining claims of damages that have been asserted by both WHC and Smit against

Exxon and Eustis Engineering could affect the partial summary judgment that has

been rendered by the trial court in favor of Smit. As the trial court recognized in its

Written Reasons for its certification of the judgment as final, the $621,410.77 at issue

remains a disputed sum.

As was noted by the supreme court in the Messinger, 894 So.2d at 1122,

decision:

8

Historically, we have a policy against multiple
appeals and piecemeal litigation. We also ensure that our
courts operate under principles of sound judicial
administration to promote judicial efficiency and economy.
. . . Article 1915 . . . attempts to strike a balance between
the undesirability of piecemeal appeals and the need for
making review available at a time that best serves the needs
of the parties.

Accordingly, we find that the interests of judicial administration and

justice to all of the parties involved outweigh any interest of Smit in having its

judgment certified as final so that it may execute on the judgment or immediately

exercise the option of having the judgment reviewed on appeal. See Messinger, 894

So.2d 1113. We do not find this to be one of those situations in which the claims of

the case are sufficiently unrelated such that the courts’ concerns regarding piecemeal

appeals are assuaged. See Curtiss-Wright, 446 U.S. 1. The appeal is hereby

dismissed, and the judgment certifying the appeal as final is vacated.

IV.

CONCLUSION

The judgment certifying the motion for partial summary judgment as

final pursuant to La.Code Civ.P. art. 1915(B)(1) in favor of Smit Land & Marine,

Inc., is vacated. This appeal is dismissed, and the case is remanded to the district

court for trial. Costs of this appeal are assessed to plaintiff-appellee, Smit Land &

Marine, Inc.

APPEAL DISMISSED; ORDER VACATED AND CASE

REMANDED.

9