CA-0006-0729 Nonprecedential Affirmed in part, reversed Processed

Hai Nam Chinese Restaurant Partnership v. B & B Construction of New Iberia

Louisiana Court of Appeal, Third Circuit · Filed November 2, 2006

Authorities cited

Identified automatically; this list may not be exhaustive.

Opinion text

STATE OF LOUISIANA
COURT OF APPEAL, THIRD CIRCUIT

06-729

HAI NAM CHINESE RESTAURANT PARTNERSHIP

VERSUS

B & B CONSTRUCTION OF NEW IBERIA, ET AL.

**********

APPEAL FROM THE
ABBEVILLE CITY COURT
PARISH OF VERMILION, NO. 13234
HONORABLE CRAIG STEVE GUNNELL, CITY COURT JUDGE, AD HOC

**********

ULYSSES GENE THIBODEAUX
CHIEF JUDGE

**********

Court composed of Ulysses Gene Thibodeaux, Chief Judge, J. David Painter, and
James T. Genovese, Judges.

AFFIRMED IN PART, REVERSED
IN PART, AND RENDERED.

Roger Chadwick Edwards, Jr.
Edwards & Edwards
P. O. Box 217
Abbeville, LA 70511-0217
Telephone: (337) 893-2884
COUNSEL FOR:
Intervenor Appellee - Third Generation Properties, L.L.C.

Mark Christopher Surprenant
Adams & Reese
4500 One Shell Square
New Orleans, LA 70139
Telephone: (504) 581-3234
COUNSEL FOR:
Defendant - GS Roofing Products Co., Inc.

Paul Gonsoulin Moresi, III
P. O. Box 1140
Abbeville, LA 70511-1140
Telephone: (337) 898-0111
COUNSEL FOR:
Plaintiff/Appellant - Hai Nam Chinese Restaurant Partnership

Mark Gerard Artall
111 East Main Street - Suite 108
Lafayette, LA 70501
Telephone: (337) 233-1777
COUNSEL FOR:
Secondary Defendant/Appellant - B & B Construction of New
Iberia, Inc.

THIBODEAUX, Chief Judge.

Plaintiff-appellant, Hai Nam Chinese Restaurant Partnership (“Hai

Nam”), filed an action for breach of contract and breach of warranty against its roofer,

defendant-appellee, B & B Construction of New Iberia, Inc. (“B & B”), because of

a defect in the new roof that it paid to have installed at its restaurant. The trial court

found that the roofing contract had been breached due to the negligent installation of

the roof and awarded Hai Nam the return of the full roofing contract cost. Third

Generation Properties, L.L.C. (“Third Generation”), the owner-lessor of Hai Nam’s

restaurant space, intervened in the action, seeking a recovery of any damages awarded

to Hai Nam in the main demand. The trial court relied on the indemnification clause

in their lease agreement and ruled in favor of Third Generation. Hai Nam appeals that

ruling, and B & B has answered the appeal, seeking a reversal of the trial court’s

judgment against it on the main demand.

We affirm the trial court’s judgment in favor of Hai Nam and against B

& B Construction. The judgment of the trial court on the incidental demand in favor

of Third Generation is reversed. Under the terms of the lease agreement and the

record evidence, Third Generation did not suffer a loss because of any act of alleged

noncompliance with the lease agreement.

I.

ISSUES

1. Did the trial court err in finding that B & B
negligently installed the roof and, therefore,
breached the roof construction contract?

2. Did the trial court err in awarding Hai Nam the
return of the entire roof construction price that had
been paid to B & B?

3. Did the trial court err in finding that Hai Nam was
obligated under its lease agreement to indemnify
Third Generation for the failure of the roof?

II.

FACTUAL BACKGROUND

Ke Nong Shi and Xue (a/k/a Linda) Mei Yang are the partners

comprising the Hai Nam Chinese Restaurant Partnership (hereinafter referred to

collectively as “Hai Nam”). Hai Nam entered into a commercial lease agreement with

the entity, Abbeville Associates, for the lease of restaurant space in the strip mall

known as the Abbeville Shopping Center. The primary lease term was August 1,

1998, through July 31, 2004. During the primary lease term, the strip mall was

purchased by Third Generation Properties, L.L.C., and the existing lease was assigned

to Third Generation.

Although the regular monthly rent was $900.00, Hai Nam was given a

$200.00 per month rent credit for the entire primary lease term, resulting in a reduced

monthly rent obligation of $700.00. This amounted to a total rent reduction of

$14,400.00 during the initial lease term. The basis for the rent credit was explained

in the lease agreement as follows:

2.4 BASE RENT: The first payment of rent shall be due
on the day that the term of this lease begins and subsequent
payments of rent shall be due on the first day of each
succeeding calendar month throughout the term of this
lease. Except as provided herein the rent for the period
from August 1, 1998 through July 31, 2004 shall be a
monthly rental of $900.00 and shall be paid as follows:

A. Lessor and Lessees recognize that there is a
need for major repairs to the roof, air-
conditioning and sewage facilities in the
building herein leased. Estimates for those
repairs indicate that it will approximate
$25,000.00 to make the necessary repairs.
Lessees agree to make the repairs which will

2

satisfy their needs and place the premises in a
condition satisfactorily [sic] to Lessees.
However, Lessor will cooperate and make
every effort to obtain the municipal or
governmental permits necessary to repair the
plumbing problems that currently exist. In
consideration thereof Lessor agrees to provide
a rent credit to Lessees in an amount of
$200.00 a month for the entirety of the
primary term. It being understood by and
between Lessor and Lessees that Lessees shall
commence paying the sum of $700.00 per
month for the entire primary term. The
agreement as herein stated is meant to be an
exception to the provisions of this lease
expressed in Paragraph 4.1 wherein Lessees
must obtain written consent of Lessor prior to
making any improvements on the premises.

During the lease term, Hai Nam undertook repairs of the plumbing, air

conditioning, and roof. Hai Nam paid $2,500.00 for repair work to the plumbing to

unplug drains. Hai Nam also paid $9,692.83 for the installation of new air

conditioning duct work and for the replacement of one of the location’s two, roof-top

air conditioning units. In addition, Hai Nam paid $12,585.23 for the installation of

a new roof.

The roof was replaced because, by all accounts, it was in very poor

condition and leaked excessively. According to Hai Nam, an inspection by the state

health department determined it would be necessary for the roof leaks to be resolved

before the restaurant could be opened. Therefore, in September 1998, prior to

opening, Hai Nam accepted B & B’s estimate for the installation of a new roof, which

included a twelve-year materials warranty and a five-year labor warranty. B & B

completed the installation in October 1998 and was promptly paid. Hai Nam also

paid B & B to install new ceiling tiles throughout the restaurant at a cost of

$3,200.00. Hai Nam, in sum, paid a total of $27,978.06 for repairs and improvements

to the leased space during the primary lease term.

3

Approximately one year later, the new roof began to leak. Although B

& B responded to numerous calls from Hai Nam over the next three years to address

the leaking, the problems were never resolved. Ultimately, in 2002, even though the

five-year labor warranty was still in effect, B & B refused to respond to repair calls

from Hai Nam. As a result, on October 16, 2002, Hai Nam filed suit, alleging breach

of contract and breach of warranty.1 Hai Nam continued its restaurant operations at

the leased location until August 31, 2004. When Hai Nam relocated its restaurant (for

reasons unrelated to the leaky roof issue), there had been no resolution of the pending

roof dispute and the roof was still leaking.

In September 2004, the month following Hai Nam’s move, Third

Generation, the lessor-owner of the property, replaced the roof that had been installed

by B &B, based on its contractor’s (Glenn Romero Roofing) determination that the

six-year-old roof had multiple flaws in its construction. Specifically, Romero’s

representative testified at trial that the torch roofing (bitumen membrane) had not

been applied to the area surrounding the roof-top air conditioning unit, leaving a

perimeter of approximately one foot of exposed roof around the air conditioner. Also,

the representative testified that there was no metal flashing or bitumen membrane

applied at the intersection of the roof and the walls that extended above the roof line;

there was no membrane applied up the sides of those walls that rose above the roof

line; and, there was no membrane or flashing installed along the ledge jacks or around

the roof jacks. Finally, the representative testified that he observed uncut, bitumen

membrane improperly overlapping the roof’s ledge in areas.

1
Hai Nam also sued the roofing product manufacturer, GS Roofing Products, Inc., and B &
B’s liability insurer, Scottsdale Insurance Company. They both were voluntarily dismissed from the
action prior to trial.

4

According to Romero’s representative, the absence of the flashing and

the application of the bitumen membrane allowed water to collect in areas and seep

into various unsealed joints, causing the roof leaks. The representative testified that

a new roof was preferred, rather than patching, in order to avoid creating a large

number of seams that would compromise the roof’s integrity. Third Generation,

consequently, paid $13,500.00 to have a new roof installed and then intervened in the

action that had been filed by Hai Nam against B & B.

In its suit, Third Generation tracked the language of its former lease

agreement with Hai Nam and asserted that in exchange for the $14,400.00 rent credit

that had been given, Hai Nam was obligated to make repairs to the leased space.

Third Generation conceded that Hai Nam was only obligated to make the repairs that

it determined to be necessary to place the premises in a condition satisfactory to its

needs. However, Third Generation claimed that because a satisfactorily installed new

roof constituted such a repair—since the restaurant could not be opened without the

repair being made—Hai Nam, in effect, breached the lease agreement when the roof

failed. Moreover, because of this breach, Third Generation stated that it had to pay

$13,500.00 for a new roof because of the poor workmanship performed by B & B on

the installation of the first replacement roof. Consequently, Third Generation claimed

that it was entitled to the recovery of the $12,585.23 sought by Hai Nam in its

principal demand against B & B.

The trial court found in favor of Hai Nam on the principal demand,

finding that B &B had negligently installed the roof. Having found the contract

breached, the court awarded damages in the amount of $12,585.23, the full cost paid

to B & B for the installation of the roof. The court then granted Third Generation’s

intervening claim, but relied on the lease agreement’s indemnification clause to

5

support its ruling, as opposed to Third Generation’s rationale. The court reasoned

that according to the terms of the lease agreement, Hai Nam was not obligated to

perform roof repairs, but that once it undertook repair of the roof, it became obligated

“to hold, the Intervenor, Third Generation, harmless from the effects of defective

installation.” The indemnification clause contained in the lease agreement states:

6.5 INDEMNIFICATION: Lessees covenant and agree
that it [sic] will protect, save and keep Lessor forever
harmless and indemnified against and from any penalty or
damage or charges imposed for any violation of any law or
ordinance, whether occasioned by the act, omission or
neglect of Lessees to those claiming or holding under
Lessees, and that Lessees will at all times protect,
indemnify and save and keep Lessor harmless and
indemnified against and from all claims, loss, cost, damage
or expense arising out of or from any accident or other
occurrence in or about the lease premises causing injury to
any person or property whomsoever or whatsoever, and
that it will protect, indemnify, save and keep Lessor
harmless against and from any and all claims, loss, cost
damage or expense arising out of any failure of Lessees, its
agent, employees, licensees, contractors or persons and
entities claiming or holding under Lessees in any respect
to comply with and perform any of the requirements and
provisions of this lease.

(Emphasis added).

The court then ordered Hai Nam to pay to Third Generation the

$12,585.23 that it had been awarded as a result of its suit against B & B. Hai Nam

has suspensively appealed this judgment, claiming that Third Generation is not

entitled to any indemnity because there has been no breach of the lease agreement.

Hai Nam contends also that it achieved a satisfactory roof repair because the

replacement of the roof allowed the restaurant to be opened and operated, without

interruption. Moreover, Hai Nam argues that, despite its defects, the roof that it paid

to have installed left Third Generation in possession of a property in significantly

better condition than it was in at the beginning of the lease term.

6

On the main demand, B & B answered the appeal, arguing that the trial

court erroneously found that it breached the roofing contract. B & B contends that

there was insufficient evidence presented of its failure to adequately perform the work

described in the agreed upon work estimate. Alternatively, B & B claims that the

damage award was excessive and that the trial court failed to apply the proper

standard to determine the amount of any damages that might be due.

III.

LAW AND ANALYSIS

Performance or Breach?

A contract defines the respective rights and obligations of the parties and

is the law between them. Corbello v. Iowa Production, 02-826 (La. 2/25/03), 850

So.2d 686. “Each provision in a contract must be interpreted in light of the other

provisions so that each is given the meaning suggested by the contract as a whole,”

and any unambiguous terms of that contract must be enforced as written.

La.Civ.Code art. 2050; see also, Brown v. Manhattan Life Ins. Co., 01-147 (La.

6/29/01), 791 So.2d 74. In other words, when the words of a contract are clear,

unambiguous, and do not lead to absurd consequences, the court should not look

beyond the contract language to determine the true intent of the parties. La.Civ.Code

art. 2046. In the event the contract is found to contain ambiguous terms, those terms

are to be interpreted against the party who furnished the text of the contract.

La.Civ.Code art. 2056.

Consequently, the ultimate determination of whether a contract has been

breached must begin with an analysis of the terms of that agreement. Corbello, 850

So.2d 686. The estimate provided by B & B constitutes the roofing agreement

accepted by B & B and Hai Nam. It sets forth an itemized list of work to be

7

performed for the replacement of the roof. The relevant part of the agreed-upon

estimate states:

After checking the roof the solution is to go with [a] new
roof, new tapye [sic] of roof material. G. S. roofing
products, flintlastic modified bitrmen [sic].2 This bid is to
provide labor and material to do the following work.

1. Remove all of the gravel.

2. Check the botton [sic] decking for rotten material.

3. Clean all debri [sic] from roofing area.

4. Install a single ply hot tar roof system.

5. Install a base sheet with hot tar.

6. Install a flintlastice [sic] modified bitrmen [sic] roof.

7. Install two roof drain from deck to drain water from
roof.

8. Cleaning and haul all debri [sic] from job site.
Material as 12 YR. warranty.
Labor as 5 YR. warranty.

TOTAL COST = $12,585.53

Accordingly, it is clear that the parties agreed that B & B would replace the flat roof

with a certain brand of modified bitumen roofing, using hot tar. During the process,

B & B expressly stated that it was to check the bottom decking of the existing roof

for rotten material and was to also install two new roof drains.

In this case, it is uncontested that the new roof installed by B & B began

to leak about a year after its installation. However, despite the subsequent appearance

of new leaks approximately one year after the roof’s installation, B & B contends that

no evidence was provided at trial that it breached the contract by failing to adequately

2
Modified bitumen is an asphalt compound that is applied to roof surfaces. It has been made
more water resistant and durable by the addition of polymers. “Flintlastic” is the brand name of a
particular modified bitumen membrane on the market.

8

perform the agreed upon work. We disagree. Louisiana codal law governing a

contractor’s liability for non-performance of a contract provides that “[i]f an

undertaker fails to do the work he has contracted to do, or if he does not execute it in

a manner and at the time he has agreed to do it, he shall be liable in damages for the

losses that may ensue from his non-compliance with his contract.” La.Civ.Code art.

2769; Austin Homes, Inc. v. Thibodeaux, 01-1282 (La.App. 3 Cir. 5/8/02), 821 So.2d

10, writ denied, 02-2324 (La. 11/15/02), 829 So.2d 436. Moreover, implied in every

building contract is the notion that a contractor will perform its work in a good and

workmanlike manner, that the work will be suitable for its intended purpose, and that

the work will be free of defects in workmanship or materials. Austin, 821 So.2d 10.

The record shows that Shane Romero, the representative of Glenn

Romero Roofing, offered testimony establishing multiple instances of poor

workmanship performed by B &B that either caused or contributed to the recurrence

of leaks. B & B’s only refutation of Romero’s testimony was offered by the

employee who prepared the estimate for Hai Nam, Edwin Buteau, Jr. He opined that

although the presence of leaks had been established, there was insufficient evidence

that B & B’s work was responsible for the recurrence of any leaks. Rather, he

testified that his company’s inspections of the roof after the recurrence of the leaks

showed that there was a buildup of condensation on or around the roof-top air

conditioning unit and/or its ductwork located below the roof. This, he claimed, was

caused by poor or inadequate construction of the building and/or installation of the

air conditioning system, for which B & B was not responsible.

In addition, B & B argues on appeal that it satisfied the terms of its

contract and no evidence was presented of its failure to perform any of the seven

work items set forth in the roofing estimate. Finally, B & B urges that Romero’s

9

testimony was unreliable because he was eighteen years old at the time of the trial,

possessed minimal formal training in roofing, and although he claimed six years of

roofing experience and was in charge of the application of the second roof for Third

Generation, all of this prior experience was obtained while he was a minor.

At the outset, we recognize that the trial court heard all of this testimony

and made a credibility call as to the weight to be given to the witnesses presented,

which this court will not disturb on appeal. See Rosell v. ESCO, 549 So.2d 840

(La.1989) (explaining that when findings of fact are based on decisions regarding the

credibility of witnesses, respect should be given to those conclusions, because only

the factfinder can be aware of the variations in demeanor and tone of voice that bear

so heavily on understanding and believing what is said). That being said, we find B

& B’s failure to adequately weatherproof the restaurant to have been substandard

conduct and a breach of the contract. The trial court’s findings of fact were

reasonable in light of the evidence presented and, therefore, we find no manifest error

in its ruling.

Damages

The trial court awarded Hai Nam $12,585.23, which constituted the

return of the entire roofing contract price. B & B asserts that this award of damages

was excessive, and the determination of damages should have been guided by the

degree to which it substantially performed the contract. According to La.Civ.Code

art. 2769 and cases interpreting it, the proper measure of damages caused by a breach

of a contract to build is what it will take to place the entity who contracted for the

work in the position it deserved to be in when the project was completed. See, Austin,

821 So.2d 10 (citing Hageman v. Foreman, 539 So.2d 678 (La.App. 3 Cir. 1989);

Hebert v. McDaniel, 479 So.2d 1029 (La.App. 3 Cir. 1985)). This necessitates a

10

finding of the cost which would be required to rectify and complete each imperfectly

constructed component. See id.

In this case, Hai Nam failed to present any detailed information

regarding the amount that it would have cost to correct B & B’s substandard work.

The trial court offered no explanation for awarding the amount aside from stating that

it was granting the amount prayed for in Hai Nam’s suit. Third Generation offered

the only testimony of specific findings of substandard workmanship having been

performed by B & B and established that it paid $13,500.00 to have the roof replaced.

Although the trial court did not reference this evidence when it rendered its decision,

we find its reasonable to infer that the trial court accepted this evidence regarding the

cost of necessary repairs to achieve a watertight roofing system.

The trial court possesses vast discretion in determining damages, and the

appellate court’s role in reviewing this determination is not to decide what it

considers to be an appropriate award, but instead, is to review the exercise of

discretion by the trier of fact. See Corbello, 850 So.2d 686. In effect, the standard

for overturning such awards is whether it is so high or so low in proportion to the

injury that it shocks the conscience. See Gravolet v. Fair Grounds Corp., 03-392

(La.App. 4 Cir. 7/4/04), 878 So.2d 900. In this case, we believe the trial court heard

sufficient evidence to support its award. The evidence presented established that

patching would not have been sufficient to repair the roof. Romero testified that the

amount of patching needed would have created numerous seams, compromising the

soundness of a new roof. Consequently, we affirm the award of damages to Hai Nam

in the amount of the return of its full contract cost.

11

Indemnity

Hai Nam asserts that the trial court incorrectly interpreted the

indemnification clause in the lease agreement to find that it was obligated to

indemnify Third Generation for the failures of the roof installed by B & B. We agree

and find that the trial court was legally incorrect in its finding. First, we note that the

general rules governing the interpretation of contracts apply in construing indemnity

agreements. See Sovereign Ins. Co., v. Texas Pipe Line Co., 488 So.2d 982

(La.1986); see also, Soloco, Inc. v. Dupree, 99-1476 (La.App. 3 Cir. 2/9/00), 758

So.2d 851. Most importantly, the language in the indemnity agreement dictates the

obligations of the parties. Jessop v. City of Alexandria, 03-1500 (La.App. 3 Cir.

3/31/04), 871 So.2d 1140, writ denied, 04-1529 (La. 10/01/04), 883 So.2d 991

(quoting Kinsinger v. Taco Tico, Inc., 03-622, p. 1 (La.App. 5 Cir. 11/12/03), 861

So.2d 669, 671). Also, “[t]he question to be considered in determining whether an

indemnity agreement is enforceable is ‘whether the risk that resulted in the injury was

one contemplated by the parties to the contract.’” Soloco, 758 So.2d at 855 (quoting

Perkins v. Rubicon, Inc., 563 So.2d 258, 259 (La.1990)).

In this case, we note that the indemnification agreement, most

pertinently, provides that Hai Nam, as lessee, agreed to do the following:

[P]rotect, indemnify, save and keep Lessor harmless
against and from any and all claims, loss, cost damage or
expense arising out of any failure of Lessees, its agent,
employees, licensees, contractors or persons and entities
claiming or holding under Lessees in any respect to comply
with and perform any of the requirements and provisions of
this lease.

In this case, we reject an interpretation of these facts that would suggest that Third

Generation was placed at a risk of a loss, or suffered a loss, due to Hai Nam’s

noncompliance with the lease agreement. Instead, we find that Hai Nam performed

12

more than the mutually recognized, estimated $25,000.00 of repair work needed by

the leased premises, from which Third Generation has benefitted.

Moreover, whether it be from unfortunate drafting or otherwise, we

cannot deny that the express terms of this contract failed to state that Hai Nam was

obligated to perform any of the repairs but, rather, stated that “[l]essees agree to make

the repairs which will satisfy their needs and place the premises in a condition

satisfactorily [sic] to Lessees.” (Emphasis added). The terms are clear and

unambiguous and must be given their commonsense meaning. See Sovereign, 488

So.2d 982.

In this regard, the record reflects testimony from Linda Yang on behalf

of Hai Nam. She stated that the roof was placed in a far better condition than it was

prior to their occupation of the premises and that, although certain leaks reappeared,

a satisfactory roof condition was achieved for Hai Nam’s purpose of running a

restaurant. We reject Third Generation’s argument that, by virtue of Hai Nam filing

suit to pursue the full enforcement of their contract with B & B, Hai Nam was

admitting to a breach of the lease agreement, i.e., the failure to obtain a satisfactory

repair of the roof. Indemnity, in its most basic sense, is due when fairness requires

that one person bear the total responsibility for an injury or loss. See Vaughn v.

Franklin, 00-291 (La.App. 1 Cir. 3/28/01), 785 So.2d 79, writ denied, 01-1551 (La.

10/5/01), 798 So.2d 969. Additionally, “[t]he basis for indemnity in the civil law is

restitution, the indemnitor having been unjustly enriched when the person seeking

indemnity has discharged liability that was his responsibility.” Klumpp v. XYZ Ins.

Co., 547 So.2d 391, 393 (La.App. 3 Cir.), writ denied, 551 So.2d 1322 (La.1989).

Considering this, we do not find that the circumstances triggering indemnification,

according to the express terms of the lease agreement, occurred and, therefore, we

13

reverse the trial court’s finding of Hai Nam’s breach of the lease agreement and

reverse its award of damages to Third Generation.

IV.

CONCLUSION

The judgment rendered in favor of Hai Nam Chinese Restaurant and

against B & B Construction, Inc., is affirmed. The judgment on the intervention in

favor of Third Generation Properties, L.L.C., is reversed. Costs of this appeal are

assessed equally between B & B Construction, Inc. and Third Generation Properties,

L.L.C.

AFFIRMED IN PART, REVERSED IN PART, AND RENDERED.

14