CA-0007-0354 Nonprecedential Affirmed Processed

Camo Construction Co., Inc. v. Town of Vidalia

Louisiana Court of Appeal, Third Circuit · Filed October 3, 2007

Authorities cited

Identified automatically; this list may not be exhaustive.

Opinion text

STATE OF LOUISIANA
COURT OF APPEAL, THIRD CIRCUIT

07-354

CAMO CONSTRUCTION CO., INC.

VERSUS

TOWN OF VIDALIA

**********

APPEAL FROM THE
SEVENTH JUDICIAL DISTRICT COURT
PARISH OF CONCORDIA, NO. 39589
HONORABLE LEO BOOTHE, DISTRICT JUDGE

**********

ULYSSES GENE THIBODEAUX
CHIEF JUDGE

**********

Court composed of Ulysses Gene Thibodeaux, Chief Judge, Marc T. Amy, and
Michael G. Sullivan, Judges.

AFFIRMED.

Ronald J. Fiorenza
Provosty, Sadler, deLaunay, Fiorenza & Sobel
P. O. Drawer 1791
Alexandria, LA 71309-1791
Telephone: (318) 445-3631
COUNSEL FOR:
Defendant/Appellee - Town of Vidalia

Richard Brooks Easterling
450 Laurel Street - Suite 1900
Baton Rouge, LA 70801
Telephone: (225) 336-5200
COUNSEL FOR:
Plaintiff/Appellant - CAMO Construction Co., Inc.

THIBODEAUX, Chief Judge.

This case involves a contract dispute between the plaintiff-appellant,

CAMO Construction Company, Inc., (CAMO) and the defendant-appellee, the Town

of Vidalia (Town). In January of 2001, CAMO was awarded the contract for a street

improvement and drainage project in Vidalia, Louisiana which called for completion

in 270 days. The project was plagued with delays from the beginning and after two

extensions of time was still not complete. The Certificate of Substantial Completion

was issued 1007 days after the start date on the contract.

During construction, CAMO instituted a claim for extended overhead

and delay damages of $221,634.04, later reduced to $141,681.59. At the end of the

project, the Town rejected the claim and deducted $80,000.00 from CAMO’s last

payment as liquidated damages for 160 of the days that CAMO went beyond the last

approved extension date on the contract.

CAMO filed suit for breach of contract in April 2004 seeking to recover

the liquidated damages and the funds claimed for overhead and delay damages. After

a bench trial, the trial court found in favor of the Town and dismissed all of CAMO’s

claims. CAMO filed this appeal. For the reasons set forth below, we affirm the

judgment of the trial court.

I.

ISSUES

We must decide:

(1) whether the trial court erred in finding that CAMO
Construction Company, Inc. was not entitled to
additional payments for delays and extended
overhead on the construction project for the Town of
Vidalia; and

(2) whether the trial court erred in finding that the Town
was entitled to deduct from CAMO’s final payment
liquidated damages for 160 days at $500.00 per day.

II.

FACTS AND PROCEDURAL HISTORY

In early January of 2001, the Town invited bids on a construction project

entitled, “Town of Vidalia 1999 Street Improvement Program, Phase II-Subsurface

Drainage.” The Town estimated that the project would require funds of

$2,445,016.00 and that the construction would take 270 days. CAMO Construction

submitted the lowest overall bid, at $2,165,976.50 and was awarded the contract. In

general, the project called for the installation of catch basins and various sizes of PVC

pipe in open ditches, and then required covering the installations with dirt and sod,

called “dressing up.” The new installations were tied into, and sometimes replaced,

existing subsurface drainage systems, at times requiring the breaking up and repair

of private driveways.

The contract documents called for “unit price” bids, not cost plus bids,

or price per hour bids. The bid forms were pre-printed with the description of each

item, the estimated quantity of that item needed for the project, and the measurement

unit for that item (linear foot, square yard, cubic yard, etc.). Blanks were provided

at the end of each line item for the contractor to write in his “unit price” bid and his

“total price” bid for that item. The contractors “unit price” bid was his price for each

item installed, that is, after installation. Therefore the “unit price” bid for each item

specifically included the cost of the material, the labor, the contractor’s overhead,

profit, taxes, insurance, bond premiums, equipment rentals, and any other contractor

costs associated with the installation.

2

For example, in one instance, 3,670 linear feet of fifteen-inch (15") inch

pipe, was bid by CAMO at $17.88 per linear foot installed. Although not shown on

the bid form, the purchase price (or unit rate) for this pipe was $5.60 per linear foot

at one time during the project. The $17.88 per unit bid by CAMO is called the “unit

price” and is then multiplied times the 3,670 linear feet indicated on the bid form, for

a “total price” bid of $65,619.60 for that item (15" pipe). The original bid form

contained eighteen (18) line items which included five sizes of corrugated PVC pipe,

catch basins, inline drains, driveway repair, asphalt street repair, sand/clay/gravel, and

other materials. Item 17 was a “utility relocation” lump sum cash allowance pre-set

on the bid form at $2,000.00. Item 18 asked for a lump sum bid for “mobilization.”

The pre-printed quantities on the bid form were estimates only. CAMO would be

paid for actual quantities installed based upon its “unit price” bid for each item.

Page two (2) of the bid packet signed by CAMO contained the following

language:

The Bidder, in compliance with your Advertisement
for Bids . . . having examined the plans and specifications
with related documents and the site of the proposed work,
and being familiar with all of the conditions surrounding
the construction of the proposed project including the
availability of materials and labor, hereby proposes to
furnish all labor, materials, and supplies, and to construct
the project in accordance with the contract documents
within the time set forth therein and at the prices stated
below. These prices are to cover all expenses incurred in
performing the work required under the contract
documents, of which this proposal is a part.

....

BIDDER hereby agrees to commence WORK under
this contract on or before a date to be specified in the
written NOTICE TO PROCEED and to fully complete the
PROJECT with[in] 270 consecutive calendar days
thereafter. BIDDER further agrees to pay as liquidated
damages, the sum of $500.00 for each consecutive calendar

3

day thereafter as provided in Section 9 of the Information
for Bidders.

Bryant Hammett and Associates, the engineering firm, was responsible

for plan designs and drawings, materials lists, bid and contract documents and

specifications, and supervision and administration of the project. The only two

signatories on the two-page contract document setting forth the price, the completion

time, and the amount for liquidated damages, were the CONTRACTOR (CAMO

Construction) and the OWNER (Town of Vidalia through its Mayor, Hyram

Copeland).

The notice to proceed was issued on January 31, 2001, and provided a

construction start date of March 6, 2001. Since the construction contract required

completion of the project in 270 days, the contract between the Town and CAMO had

a completion date of December 1, 2001, which means that the project must be

“substantially complete” by the designated date. Basically, the contractor notifies the

owner that he is finished; the owner conducts a pre-final inspection, and issues a

Certificate of Substantial Completion.

In addition to the provision in the bid packet, the contract document

itself provided for liquidated damages in the form of a $500.00 per diem charge

against the contractor for every day that the project ran over the completion date on

the contract. However, the entire contract, which contained four parts – Contract and

Bid Documents, General Conditions, Special Conditions, and Technical

Specifications – provided specific mechanisms for adjusting the contract price and

the completion time, due to inevitable delays and unforseen costs as the project

progressed. Those mechanisms are defined under Section 1.01 on page one of the

General Conditions (GC-1) as a Change Order and a Claim, as follows:

4

9. Change Order – A document recommended by
ENGINEER which is signed by CONTRACTOR and
OWNER and authorizes an addition, deletion, or revision
in the Work or an adjustment in the Contract Price or the
Contract Times, issued on or after the Effective Date of the
Agreement.

10. Claim – A demand or assertion by OWNER or
CONTRACTOR seeking an adjustment of Contract Price
or Contract Times, or both, or other relief with respect to
the terms of the Contract. A demand for money or services
by a third party is not a claim.

The project was besieged with delays from the beginning. CAMO began

ordering materials, and sent drawings for the catch basins and drain tops to the

fabricator for review when the notice to proceed was issued. It was soon discovered

that the catch basins could not be fabricated because the pipe to be installed was too

big to go in the basin elevations that had been supplied on the drawings by the

engineers. After lengthy discussions with the project engineer, CAMO was still

corresponding with the fabricator in mid-March 2001 about the various pipe sizes and

the minimum depth for the coordinating catch basins. CAMO did not begin

construction at the work site until June 11, 2001.

Once construction began, it became apparent that the eighteen-inch

(18") PVC pipe ordered pursuant to the plans and specifications was too large for the

intended ditches. Therefore, a large amount of this pipe was unusable. There were

also problems with the elevations prepared by surveyors with the engineering firm,

and CAMO could not tie the new pipe into the existing pipes and cross-drains.

CAMO began taking the elevations in the field and adjusting the pipe as it was laid.

This process is called “field engineering.” CAMO also encountered underground

gas, sewer, and water lines that were not accurately marked on the drawings,

requiring the relocation by the Town of some of the utilities, and circumvention by

CAMO of others. The project was far from completion by the original deadline of

5

December 1, 2001. On December 13, 2001, the engineering firm wrote CAMO

asking it to provide a written request for additional time to complete the project.

On December 20, 2001, with the Hammett firm’s recommendation,

Change Order No. 1 was issued granting an additional 200 days for completion of the

project, thereby extending the contract period to 470 calendar days, with a beginning

date of March 6, 2001 and a completion date of June 19, 2002. The reasons listed for

the change order were: (1) delays in material deliveries; (2) delays in material

fabrication; (3) extreme weather conditions; and, (4) conflicts with existing

underground utilities.

On January 29, 2002, Change Order No. 2 was issued due to a decision

by the Town to delete Bid Item 12 - “trench repairs with sod.” CAMO’s unit price

for that item was $87,108.00. Therefore, the contract price was reduced from

$2,165,976.50 to $2,078,868.50. CAMO had no objection to this deletion, and the

change order was approved. The contract time of 470 days remained the same, as did

the completion date of June 19, 2002.

Problems continued in 2002. CAMO met with Hammett in mid-January

to discuss the project needs. The conflicts with underground utilities, and problems

with inlets and catch basins continued. Too many catch basins had been ordered;

discussions were underway for a new design on the inlets; and CAMO suggested

modifying some of the extra basins in order to use them. At some point a switch was

made from concrete basins to plastic basins. There were continued delays due to

material fabrication. CAMO lost a month due to adverse weather conditions. The

Hammett engineering firm wrote CAMO twice in July of 2002, advising CAMO to

provide another written request for more time, since the contract had expired on June

19, 2002.

6

Change Order No. 3 was issued on September 3, 2002, two-and-a-half

months after the June 19, 2002 deadline. This change order added 320 days to the

original contract time, resulting in a contract period of 790 calendar days, from March

6, 2001 to May 5, 2003. The reasons for Change Order No. 3 were the same as those

stated on Change Order No. 1 - delays in material deliveries and material fabrication,

weather conditions, and conflicts with underground utilities.

Hammett had begun drawing new plan designs on August 30, 2002.

While the plan revisions were underway, CAMO could not install pipe but was able

to work on punch list items. CAMO reported the punch list complete on October 8

and requested the new drawings. Hammett sent the revised plan drawings and new

materials list on October 9, 2002. The revised plans called for the installation of

additional units of fifteen-inch (15") pipe and also added twelve-inch (12") pipe and

side drains to the project. Once the new materials were ordered, there were some

delays waiting for their delivery. The fifteen-inch (15") pipe had gone up in price by

$1.41 per linear foot since CAMO bid the job in January of 2001. The Town agreed

to pay CAMO the higher unit price on this bid item.

Change Order No. 4 was submitted on December 2, 2002, to increase

the contract price for four new line items, Items 19-22, for the installation of 6,895

linear feet of fifteen-inch (15") pipe, 870 linear feet of twelve-inch (12") pipe, 51 side

drains with pads and grates, and the 88 side drains on the punch list. Pursuant to this

change order, the contract price was increased by $280,164.65, which was CAMO’s

price for installing the new items, which were mostly the result of the plan revisions.

The change order also decreased the contract price due to deletions of certain items

for a net increase of $209,969.65. Originally, the deletions were incorrect, and the

change order was subsequently corrected to the price here stated. Change Order No.

7

4 brought the contract price up to $2,288,838.15. It did not add any days to the

contract, and the completion time remained at 790 days with the completion date of

May 5, 2003.

On December 13, 2002, CAMO wrote Hammett requesting the resolution

of five items revolving around CAMO’s extended overhead due to the delays and to

alleged costs associated with excessive field engineering. However, none of the

claims were quantified. CAMO considered the letter a claim and requested a meeting

the following week to discuss the specific items. The meeting took place, but it was

agreed that CAMO would keep working and the claims would be revisited.

On May 2, 2003, three days before the latest extension expired on May

5, 2003, Hammett wrote CAMO expressing the Town’s concern that the project

would not be completed that summer. Hammett noted the two previous time

extensions and asked CAMO to submit a completion schedule detailing the work

remaining and the time frame for completing the project. Hammett also asked CAMO

to submit a written explanatory request for more time.

CAMO responded in correspondence dated May 19, 2003, summarizing

the reasons for the previous extensions, but wanted to know whether streets

previously discussed as possible additions to the project were going to be added,

before providing a new extension time. CAMO never did provide a request in writing

to the engineer for an additional extension of time. In this letter of May 19, CAMO

also expressed concern about the outstanding issues in its December 13, 2002 letter.

In a separate letter dated the same day, CAMO asked for a new punch list. Hammett

mailed a four-and-one-half page punch list on June 20, 2003.

Several letters were exchanged between Hammett and CAMO between

July 17, 2003 and October 27, 2003. These communications prompted the Mayor to

8

instruct Hammett to attempt a compromise of the claim for extended overhead and

delay damages.

A meeting between Hammett and CAMO resulted in a reduction of these

claims from $221,634.04 to $141,681.59 and an additional claim for $20,926.44 for

removal of the leftover materials to the Town’s storage facility. This was confirmed

in writing on October 27, 2003. On October 30, 2007, CAMO requested from

Hammett a Certificate of Substantial Completion.

On November 19, 2003, the project engineer for Hammett, Keith

Capdepon, wrote CAMO referencing CAMO’s October 27, 2003 letter containing the

revised numbers and stating that the revised cost breakdown was approved. He

further indicated that a change order would be issued showing the cost breakdown

and adding it to the final estimate for payment.

On November 19, 2003, Change Order No. 5 was prepared and

subsequently signed by Bryant Hammett and CAMO, adding 217 days to the contract

period that had expired on May 5, 2003. This change order would result in a contract

period of 1007 calendar days and extend the contract completion date to December

8, 2003. Change Order No. 5 also contained a change in the contract price that

reflected the deletion of leftover, uninstalled materials, in the amount of $485,459.60,

and the addition of CAMO’s revised cost breakdown of $162,608.03. The new

contract price according to this change order was $1,985,986.58. However, Change

Order No. 5 was never signed by Mayor Copeland on behalf of the Town. While the

change order contains an issue date of November 19, Hammett was still trying to

confirm the figures with CAMO on December 13, 2003, and the change order was not

submitted to the Town by Hammett until December 17, 2003.

9

On November 26, 2003, the pre-final inspection that was attempted on

October 9, 2003, was rescheduled for December 9, 2003.

On December 8, 2003, Hammett generated a final punch list for CAMO,

and December 8, 2003 was determined to be the date of substantial completion of the

project. CAMO signed the Certificate of Completion on December 16, 2003.

On December 17, 2003, Hammett submitted correspondence to Mayor

Copeland attaching a twenty-third and final payment request and original Change

Order No. 5, both of which incorporated a $162,608.03 payment to CAMO for the

revised cost breakdown (extended overhead and delay costs of $141,681.59 plus

$20,926.44 for moving excess materials to storage). The December 17, 2003 letter

also attached Revised Change Order No. 4 as previously indicated.

On December 31, 2003, the Town’s comptroller, Kenneth J. Davis, wrote

CAMO, stating that the December 17, 2003 items had been reviewed for payment, but

more information was needed from the engineers before a final determination could

be made.

In January of 2004, the Town’s comptroller wrote CAMO indicating that

CAMO’s final payment would not include the $141,681.59 cost breakdown claimed

for extended overhead and delay damages, as the figures seemed arbitrary, and as the

contract was bid as a unit price contract. The letter stated that such a payment would

convert the contract to a cost plus contract and cause severe ramifications for the

Town. The Town further indicated that it would deduct the amount of $108,500.00

from CAMO’s final payment as liquidated damages for the 217 days that CAMO had

run over the contract period ($500.00 per day). The Town explained that its work

summaries indicated that CAMO had only worked 389 days on the project, and that,

10

even with an allowance for 107 rained out days, such a schedule did not justify the

217-day extension sought in Change Order No. 5.

On March 4, 2004, CAMO’s attorney wrote the City Attorney asserting

that CAMO’s records indicated 435 days on the job and that CAMO was entitled to

the extra cost because it based its bid on only 270 days of work. He indicated that

CAMO was not seeking additional costs for days not worked, or for delays caused by

waiting on materials and waiting on revised plans, but rather for extra days working

on the project due to delays beyond CAMO’s control.

On April 2, 2004, the Town comptroller, Mr. Davis, wrote CAMO’s

attorney presenting the Town’s adjustment to the Change Orders and the estimate for

payment number 23. The Town had deducted $80,000.00 for 160 days of liquidated

damages, instead of $108,500.00 for 217 days of damages for exceeding the contract

period, and had approved Revised Change Order No. 4. It had deleted the

$162,608.03 cost breakdown from Change Order No. 5 and from the estimate for

payment number 23, but indicated that it would pay the portion of that breakdown

that represented the cost of $20,926.44 for moving the leftover materials. It requested

that this amount be billed outside of the contract. Hence, CAMO’s claim for

extended overhead and delay damages was denied. The Town indicated that it had

issued a check to CAMO for a balance due of $207,168.65, which included a negative

balance of -$31,052.33 on the contract, due to the deduction of damages, and a

payment of plus $20,926.44 for moving the excess materials, and plus $217,568.10

for the installed price of the excess materials, which were paid outside the contract.

11

III.

LAW AND DISCUSSION

Standard of Review

An appellate court may not set aside a trial court’s findings of fact in

absence of manifest error or unless it is clearly wrong. Stobart v. State, Through

DOTD, 617 So.2d 880 (La.1993); Rosell v. ESCO, 549 So.2d 840 (La.1989). A two

tiered test must be applied in order to reverse the findings of the trial court:

a. the appellate court must find from the record that a
reasonable factual basis does not exist for the
finding of the trial court, and

b. the appellate court must further determine that the
record establishes that the finding is clearly wrong
(manifestly erroneous).

Mart v. Hill, 505 So.2d 1120 (La.1987).

Even where the appellate court believes its inferences are more

reasonable than the fact finders, reasonable determinations and inferences of fact

should not be disturbed on appeal. Arceneaux v. Domingue, 365 So.2d 1330

(La.1978). Additionally, a reviewing court must keep in mind that if a trial court’s

findings are reasonable based upon the entire record and evidence, an appellate court

may not reverse said findings even if it is convinced that had it been sitting as trier

of fact it would have weighed that evidence differently. Housely v. Cerise, 579 So.2d

973 (La.1991). The basis for this principle of review is grounded not only upon the

better capacity of the trial court to evaluate live witnesses, but also upon the proper

allocation of trial and appellate functions between the respective courts.

Claims for Extended Overhead and Delay Damages

CAMO contends that the trial court erred in finding that it was not

entitled to additional costs for extended overhead and delays beyond its control on

12

the construction project. The record reveals that the delays to which CAMO refers

began before the authorized start date on the contract of March 6, 2001. Yet, CAMO

did not provide a written request for compensation until December 13, 2002, after it

had received three change orders compensating CAMO in both time and price for the

costs and delays alleged.

More specifically, Mike Grantham, President of CAMO, testified that

around the time that the notice to proceed was issued on January 31, 2001, he began

ordering materials, and it was soon determined that the catch basins could not be

fabricated because the pipe to be installed was too big to go in the basin elevations.

Grantham had lengthy discussions with the engineers and the fabricator and wrote the

fabricator on March 15, 2001, regarding the various pipe sizes and the minimum

depth for the coordinating catch basins that were needed. Accordingly, he did not

begin construction until June 11, 2001. Once on the site it became apparent that the

eighteen-inch (18") pipe was too big and “riding out” of the ditches, and he began

running into underground utilities not accurately marked on the engineer’s drawings.

Grantham began making changes in the field, called “field engineering,”

from the very beginning. By September 3, 2002, Change Order No. 1 and Change

Order No. 3 had been issued giving him 200 and 320 additional days, respectively,

for a total of 520 additional days on the contract. The reasons for both change orders

were: (1) delays in material deliveries; (2) delays in material fabrication; (3) extreme

weather conditions; and, (4) conflicts with existing underground utilities. The

September 3, 2002 change order was accompanied by a cover letter from Bryant

Hammett specifically recommending the additional days. The drawings were being

revised at the time of the September 3, 2002 change order, and on December 2, 2002,

Change Order No. 4 was issued in order to compensate CAMO its quoted price of an

13

additional $280,164.65 for modifications and the installation of new materials due to

the changes in the plans not previously part of the original contract.

Eleven days later, on December 13, 2002, CAMO wrote Hammett the

letter, now being characterized as the claim. The letter requested resolution of: (1)

extended overhead for the delays listed in Hammett’s September 3, 2002 letter; (2)

delays due to conflicts with utilities and other obstructions; (3) delays due to work

stoppage for material revisions and deliveries; (4) costs due to excessive field

engineering for installation of pipe, catch basins, and inlets; (5) demobilization and

remobilization due to revision of drawings from August 30, 2002 to October 9, 2002.

The trial court agreed with the Town’s position that CAMO was granted

both time extensions and additional compensation for the items in the claim in three

previous change orders. Specifically, following two extensions of time in Change

Orders No. 1 and in Change Order No. 3, Change Order No. 4 increased the contract

by a net figure of $209,969.65 in order to pay CAMO $280,164.65 for the installation

of new material due to plan revisions and to pay CAMO its quoted price for

modifying some of the excess catch basins. Moreover, as the Town points out in its

brief, the Town paid CAMO for all of the excess catch basins that CAMO allegedly

ordered as a result of the duplication error on the plans. In fact, CAMO was paid the

installed price of the leftover materials.1 We also note that while the revisions during

construction led to the addition of certain installations to the original contract that

1
The evidence reveals that CAMO was paid the installed price of all of the leftover catch
basins, pipe, and other materials that CAMO ordered and moved to the Town’s storage barn at the
end of the project, even though CAMO did not actually install these materials. The cost of the
leftover material was $173,967.50, and CAMO was paid $217,568.10 for the material, the difference
being $15,222.16 (8.75%) for taxes, plus $28,378.45 (15%) for profit and overhead. Additionally,
CAMO was paid its requested price of $20,652.88 for moving the material to storage. These
payments to CAMO were not reflected in the change orders presumably because these materials were
not installed as part of the project. CAMO was paid for these items outside of the contract.
However, the unit price bid for these materials was included in the overall reductions in the contract
price.

14

were not part of CAMO’s original bid, the revisions also caused the deletion of

certain installations that CAMO had bid in the original contract. That is the reason

for change orders – to document revisions in the work as it progresses, to adjust time

and prices as needed, and to pay the contractor his unit price for items actually

installed. In the end, in this case, there were more deletions than additions of work.

With regard to CAMO’s claim for cost of demobilization and

remobilization between August 30 and October 9 of 2002 while the engineers revised

the plan drawings, the Town’s comptroller gathered documentation from the project

engineer, Capdepon, stating that CAMO was working on a preliminary punch list

during that time in the Southern part of town where subsurface drainage had already

been installed and needed dressing up. Hammett testified at trial that his

understanding was that CAMO was working on a punch list except for about two

days during that time. This information is confirmed by CAMO’s letter from

Grantham to Capdepon, the project engineer, dated October 8, 2002, stating that “We

have completed the punch list . . . we are ready to proceed with the completion of the

project and are awaiting the revised drawings.” The following day, October 9, 2002,

a letter from Capdepon to Grantham encloses the requested drawings.

Moreover, Grantham testified at trial that during the plan revisions, they

could not install pipe so they dropped back and worked on punch list items. We note

that Change Order No. 4, issued on December 2, 2002 adds four Items to the contract,

Items 19-22. Items 19-21 are for the new installations pursuant to the revised plans

provided in October. The last item is described thusly: “Item 22 side drain (punch

list) were side drains installed by contractor after pipe had been laid.” Out of the total

of $280,164.65 paid to CAMO for the four additional items on Change Order No. 4,

Item 22 for the punch list items represents $88,484.00 of that amount.

15

We note that at the end of the project, the final contract price shown on

Revised Change Order No. 5 and on the final payment summary is $1,823,378.55,

which is less than CAMO’s bid of $2,165,976.50. This is because there were more

deletions of work due to revisions than additions to the work because of revisions.

We also note that, even though the final contract price was $1,823,378.55, the total

payments to CAMO were $1,981,599.53, due to the payment to CAMO for the

leftover materials. As is evident in the record, CAMO did not submit a price per hour

bid or a cost plus bid. The bid packet specifically invited only unit price bidding, and

the bid proposal is entitled “Bid for Unit Price Contracts.”

General Conditions to the Contract, Section 11.03, entitled “Unit Price

Work,” provides as follows:

A. Where the Contract Documents provide that all or part
of the Work is to be Unit Price Work, initially the Contract
Price will be deemed to include for all Unit Price Work an
amount equal to the sum of the unit price for each
separately identified item of Unit Price Work times the
estimated quantity of each item as indicated in the
Agreement. The estimated quantities of items of Unit Price
Work are not guaranteed and are solely for the purpose of
comparison of Bids and determining an initial Contract
Price. Determinations of the actual quantities and
classifications of Unit Price Work performed by
CONTRACTOR will be made by ENGINEER subject to
the provisions of paragraph 9.08.

B. Each unit price will be deemed to include an amount
considered by CONTRACTOR to be adequate to cover
CONTRACTOR’s overhead and profit for each separately
identified item.

C. OWNER or CONTRACTOR may make a Claim for an
adjustment in the Contract Price in accordance with
paragraph 10.05 if:

1. the quantity of any item of Unit
Price Work performed by CONTRACTOR
differs materially and significantly from the
estimated quantity of such item indicated in
the Agreement; and

16

2. there is no corresponding
adjustment with respect [to] any other item of
Work; and

3. if CONTRACTOR believes that
CONTRACTOR is entitled to an increase in
Contract Price as a result of having incurred
additional expense or OWNER believes that
OWNER is entitled to a decrease in Contract
Price and the parties are unable to agree as to
the amount of any such increase or decrease.

(All emphasis ours.)

Based upon the foregoing, CAMO’s argument fails. Section 11.03(C)

provides that the contractor can make a claim for an adjustment in the contract price

in accordance to paragraph 10.05, which was not done in this case as explained more

fully below, if all three of conditions one (1) through three (3) are met. The second

condition, at Subsection (2), requires that there can be no other corresponding

adjustment with respect to any other item of work. As previously indicated, the

Town’s position is that previous change orders compensated CAMO for the changes

in the work. The trial court agreed. We also agree. The plans and drawings were

being revised by Hammett on August 30, 2002, and Change Order No. 3, granting

320 additional days to the contract, was dated September 3, 2002.

Testimony at trial indicated that the change orders requesting additional

time covered delays in the past and delays anticipated. Hence, in addition to Change

Order No. 1, granting 200 days for delays at the beginning of the contract in 2001,

Change Order No. 3, granting 320 days extension, compensates CAMO for delays

before, after, and at the time the plans were being revised in the fall of 2002.

Likewise, Change Order No. 4 compensates CAMO in the amount of $280,164.65 for

revisions and modifications in the work.

17

Pursuant to Section 12.05 of the General Conditions, delays beyond the

control of both owner and contractor are compensated by an extension of time equal

to the time lost, which “shall be the CONTRACTOR’s sole and exclusive remedy for

such delay.” Further, Section 12.06 provides that, “In no event shall OWNER or

ENGINEER be liable to CONTRACTOR . . . for damages arising out of . . . delays

. . . within the control of CONTRACTOR; or . . . delays beyond the control of both

OWNER and CONTRACTOR.” CAMO further argues that it should be compensated

in price for the delays caused by the conflicting underground utilities under Section

4.03(C) of the General Conditions. That section provides for contract changes in time

or price if subsurface conditions are unusual or materially different from conditions

ordinarily encountered or of such a nature as to establish material inaccuracies in the

technical data relied upon by the contractor. Again, since interference with

underground utilities started at the beginning of the work, Change Orders No. 1 and

No. 3 granted a total of 520 additional days for delays which specifically included

conflicts with underground utilities.

As to an increase in price due to those delays, paragraph 20 of page SC-6

of the Special Conditions in the contract, which override the General Conditions,

provides in pertinent part that, “The Contractor shall make his own investigations and

be fully responsible for locating and taking care not to damage any gas, water or

sewer lines. . . . In case that such physical properties conflict with the performances

of the contract, it shall be the Contractor’s responsibility to anticipate such conflicts

and to give advance notice thereof to the Owners.” (Emphasis added). In particular,

paragraph 21 of the Special Conditions at SC-7, entitled “Subsurface Conditions,”

provides: “Contractor shall make his own investigations of subsurface conditions.

No claims for extra compensation due to unusual conditions or development[s] that

18

are found to exist underground will be allowed.” (Emphasis added). Paragraph 9 at

SC-3, entitled “Site Investigation,” provides that the contractor is presumed to have

visited the site before bidding and to be thoroughly familiar with the nature and

location of the job, the equipment and quantities of materials needed, and that any

failure to acquaint himself with all available information “will not relieve him of

responsibility for estimating properly the difficulty or cost of successfully performing

this work.”

Section 2.05 of the General Conditions, entitled “Before Starting

Construction,” provides that “Before undertaking each part of the Work

CONTRACTOR shall carefully study and compare the Contract Documents and

check and verify pertinent figures therein and all applicable field measurements.”

Additionally, Section 4.04 of the General Conditions provides that

information shown or indicated in the contract documents with respect to existing

underground facilities is based on information and data furnished by the owners of

such underground facilities, and unless otherwise expressly provided in the

Supplementary Conditions, the OWNER and ENGINEER “shall not be responsible

for the accuracy or completeness of any such information or data.” It further provides

that the cost of reviewing and checking all such information, locating all underground

facilities, and coordinating the work during construction with the owners of the

utilities, “will be included in the Contract Price” and shall be the full responsibility

of the contractor.

Likewise, paragraph 11 on page 02221-4 of the Technical Specifications

of the contract provides that “it is solely the Contractor’s responsibility to verify the

exact location, number of utilities, number of lines, etc., prior to beginning

construction.”

19

Moreover, Section 11.03(C) and Section 4.03, and every other section

of the General Conditions dealing with the filing of a claim, whether for changes to

contract times or contract prices, requires that the claim be filed in accordance with

Section 10.05 of the General Conditions. Section 10.05 requires that written notice

of a claim “shall be delivered by the claimant to ENGINEER and the other party to

the Contract promptly (but in no event later than 30 days) after the start of the event

giving rise thereto.” CAMO did not comply with this requirement. CAMO waited

until December 13, 2002, eleven days after Change Order No. 4 was issued, to

provide written notice of events that started at the very beginning of the contract. The

final subsection - D - of Section 10.05, at page GC-27, provides that “No Claim for

an adjustment in Contract Price or Contract Times (or Milestones) will be valid if not

in accordance with this paragraph 10.05.”

CAMO has made much of the fact that on December 17, 2003, Hammett

sent a cover letter to the Mayor attaching the original proposed Change Order No. 5,

showing a 217-day extension to December 8, 2003, and showing an increase in the

contract price for the claim of extended overhead and delay damages. Therefore,

CAMO argues that Hammett’s signature on the change order constitutes a written

recommendation from the engineer that was binding upon the Town pursuant to

General Condition 9.08, which provides:

A. ENGINEER will determine the actual quantities and
classifications of Unit Price Work performed by
CONTRACTOR. ENGINEER will review with
CONTRACTOR the ENGINEER’s preliminary
determinations on such matters before rendering a written
decision thereon (by recommendation of an Application for
Payment or otherwise). ENGINEER’s written decision
thereon will be final and binding (except as modified by
ENGINEER to reflect changed factual conditions or more
accurate data) upon OWNER and CONTRACTOR, subject
to the provisions of paragraph 10.05.

20

As a threshold matter, the claim for extended overhead and delay

damages was not for quantities of unit price work performed, nor did CAMO submit

a proper claim under Section 10.05. Therefore, Section 9.08 is inapplicable. CAMO

was paid for every unit of pipe or other material that it installed. With regard to

having CAMO’s crew and equipment on the job longer than Grantham anticipated

when he bid the job, that is covered in the numerous sections requiring CAMO to

anticipate and include all such delays and underground obstructions in his bid price.

Hammett testified that during his 22 years as a project engineer, working on hundreds

of projects, he had never heard of a contractor being paid “extended overhead.”

Hammett further testified that he never made a final decision as to

whether CAMO had submitted a claim entitling it to additional money under the

contract, nor did he investigate or make any determinations regarding the validity of

CAMO’s claim. He testified that CAMO’s methodology for calculating equipment

rentals and some of the percentages seemed fair. However, the charge for one or two

man hours a day and increased cost of labor was completely arbitrary and not based

on anything. Hammett indicated that he had been instructed to try to work out

something with Grantham, and after meeting with him, Grantham reduced the

disputed portion of the claim, and Hammett presented the reduced amount in the

change order simply because he knew that it was the lowest that Grantham would go.

Hammett specifically stated that he told Grantham numerous times

throughout their discussions that he (Hammett) did not have the final say on the

claim. Moreover, Section 10.03 of the General Conditions provides that the Owner

and Contractor shall execute “appropriate” change orders recommended by the

engineer covering changes in the contract price or contract times “which are agreed

21

to by the parties” and “which embody the substance of any written decision rendered

by ENGINEER pursuant to paragraph 10.05.”

As stated, there was no written decision by Hammett pursuant to Section

10.05; indeed, there was no proper claim submitted pursuant to Section 10.05. There

was clearly no agreement by the parties since the Town refused to execute the original

proposed Change Order No. 5 and instructed Hammett to revise it, deleting the claim

for compensation and the 217-day extension of time.

In finding that CAMO had been compensated for its claims in time

extensions and price increases in previous change orders, the trial court concluded

it was well settled that after adjustments have been negotiated to a contract and

agreed upon by all parties, one party cannot subsequently seek additional relief. For

that proposition, the court cited Circle, Inc. v. Board of Supervisors, Sewerage

District No. 2, St. Bernard Parish, 387 So.2d 606 (La.App. 4 Cir.), writ denied, 394

So.2d 613 (La.1980). CAMO attempted to distinguish the case, but provided no

supporting precedent of its own. Contrary to CAMO’s assertion otherwise, the issues

and holding in Circle are quite analogous to this case. The 1967 contract in Circle

was a unit price contract. After construction on a public sewerage contract began, the

contractor encountered unexpected soil changes and obstructions to installation of the

line requiring changes to the proposed construction plan.

Accordingly, the parties in Circle negotiated a change order that

increased the contract time by 56 days and the contract price by $3,020.01 as

compensation for the relocation of some lines and the redesign of others.

Subsequently, the contractor sued for additional amounts for the extra work, delays,

and changes in the contract. The court determined that the change order involved the

entire contractual obligation and was a compromise between the parties after

22

negotiation, and therefore had the force of law. The court in Circle articulated that

the contractor may have made a bad bargain, but he had made a legally binding

bargain. The fact that the change order also provided that the cost for the work could

not exceed the contract amount plus a five percent contingency does not create an

“entirely different situation” as CAMO suggests.

Nor does CAMO’s assertion that the previous change order in Circle was

dissimilar to the previous change orders in the present case because it was reached

only after considerable negotiation and exploration. Change Orders No. 1, 3 and 4,

in the present case were certainly the result of much deliberation and extensive

calculations, and because they were signed by both of the parties to the contract,

CAMO and the Town, they were binding. Further, contrary to CAMO’s assertions,

the proposed Change Order No. 5 in the present case was not binding because it was

not signed by both parties to the contract in that the Mayor never endorsed it.

Accordingly, we find no manifest error in the trial court’s judgment dismissing

CAMO’s claim for additional compensation for extended overhead and delay

damages under the contract.

CAMO’s Claim for Additional Time

CAMO further contends that the trial court erred in finding that CAMO

was not entitled to the 217 additional days on the contract as indicated in Hammett’s

December 2003 letter to the Town. The record reveals that the Certificate of

Substantial Completion signed by CAMO was issued with a substantial completion

date of December 8, 2003. On December 17, 2003, nine days after the date on the

Certificate of Completion, Bryant Hammett submitted a proposed Change Order No.

5 to the Town that included the request for the 217 additional days that had already

been consumed, and the Town declined to grant the extension. The previous

23

extension of time approved by the Town had expired on May 5, 2003, pursuant to

Change Order No. 3. Hence, these final 217 days requested would cover the period

from May 5, 2003 to December 8, 2003 and prevent the assessment of the $500.00

per-day liquidated damages called for under the contract.

CAMO argues that it should have been granted the 217-day extension

because CAMO relied on a pattern established during construction wherein Hammett

would ask CAMO to submit a request for time, CAMO would comply, Hammett

would write up the change order, and the Town would approve it, and that Change

Order No. 5 should have been no different. More specifically, CAMO’s appellate

brief to this court provides: “Each time the current time period would be close to

expiring, the engineers would write CAMO and ask CAMO to request additional

time.” This is not an accurate statement. The pattern that had been established was

one wherein CAMO would fail to request an extension, as required under the

contract, and the Hammett firm would somewhat paternalistically carry CAMO

through the process, after the previous extension had already expired.

The record reveals that the initial completion date under the contract for

270 days was December 1, 2001. On December 13, 2001, the project engineer,

Capdepon, wrote to Mike Grantham as follows: “This correspondence is to advise

you that the contract time for the above captioned project expired on December 1,

2001. Please submit to us, in writing, a request for more contract time for the

completion of this project.” Grantham complied with this request by correspondence

dated December 20, 2001. The result was the Town’s approval of Change Order No.

1, dated December 20, 2001, granting 200 additional days from the December 1st

expiration date.

24

The new expiration date, pursuant to Change Order No. 1 was June 19,

2002. On July 8, 2002, Capdepon wrote Grantham an almost identical letter advising

him that the contract had expired on June 19, 2002, and asking for a written request

for more contract time, and an explanation for the extension. CAMO did not respond.

On July 30, 2002, Capdepon again wrote Grantham with the identical language as the

July 8th letter, asking for a written request for time. On August 1, 2002, Grantham

wrote Capdepon regarding the June 19th expiration date, indicating that he did not

know the extent of remaining changes due to obstructions, and he therefore did not

enter a request for time. There must have been verbal discussions, because on

September 3, 2002, Bryant Hammett wrote the Mayor recommending a 320-day

extension to the contract, and attaching Change Order No. 3.

Change Order No. 3, dated September 3, 2002, extended the contract

expiration date from June 19, 2002 to May 5, 2003. Revised plans were being drawn

up simultaneously with Change Order No. 3, indicating that the Town looked for

completion of the project on the date of May 5, 2003, as provided for therein. On

December 2, 2002, when Change Order No. 4 was issued for the $280,164.65

increase in contract price for CAMO’s quote on the additional Items 19-22, most of

which were due to the plan revisions, there was no request for additional time, and

the expiration date of Change Order No. 3 remained the same, May 5, 2003.

For the first time, on May 2, 2003, three days before the expiration date

of the May 5, 2003 deadline, Bryant Hammett wrote Grantham in advance that there

was “a growing anxiety among town officials and the Mayor that the work initially

begun will not be completed this summer.” The second paragraph reminded

Grantham of the specifics of the previous extensions and change orders and then

stated, “To date this project is not finished.” In the third paragraph, Hammett asked

25

Grantham to submit “a completion project schedule detailing the work remaining and

time frame for completing this project.” He then asked for a written request for more

time, with an explanation, and asked for Grantham’s help in completing the project

in a timely manner due to the inconvenience the project was causing the residents.

On May 19, 2003, two weeks after the expiration of the contract on May

5, 2003, Grantham responded to Hammett’s May 2nd correspondence, providing

reasons for the previous extensions and expressing his own anxiety over his

December 2002 letter asking for extended overhead and delay damages. Grantham

still did not request an extension time, stating that in order to do that he would need

to know whether the additional streets discussed the previous year were going to be

added. At trial, Grantham testified that, at that point in time, he did not know how

much time to ask for, so he did not put a time in the letter.

In another letter dated the same day, May 19, 2003, Grantham wrote

Capdepon, asking for a punch list of items to be addressed, and asked that any

additional streets should be made part of the punch list. On June 20, 2003, Capdepon

sent Grantham the punch list comprised of four-and-a-half pages of items to be

completed, but the additional streets were not added. Grantham was still laying pipe

when he received the punch list. The record contains no evidence that Grantham ever

provided the engineers with a written request for an extension of time, though there

is correspondence regarding his claim for extended overhead and delay damages in

October 2003.

Section 12.02(A) of the General Conditions provides that the contract

times may only be changed by a change order or written amendment, and, any claim

for an adjustment in contract times “shall be based on written notice submitted by the

party making the claim to the ENGINEER and the other party to the Contract in

26

accordance with the provisions of paragraph 10.05.” CAMO did not comply with

Section 12.02(A) under its own volition for the first two extensions of time. Rather,

it had to be asked to comply after the expiration of the contract. That was the actual

pattern that had been established. For what might have been the third extension of

time, even though he was pleaded with prior to the final expiration on May 5, 2003,

CAMO never provided the written request to the engineers as required.

Section 12.02(B) provides that any adjustment to the contract times will

be in accordance with the provisions of Article 12. Section 12.04 provides that the

contract times will not be extended due to delays within the control of the contractor.

Even though the engineers, Hammett and Capdepon, took full responsibility for their

drawings, the Town’s position is that CAMO was granted 520 additional days on the

contract for delays beyond its control, and that some of the delays were the fault of

CAMO, including its failure to verify information in advance and to allow for

interference with utilities in its bid as required by the contract. Moreover, the Town’s

information demonstrated that out of the 1007 days between the contract start date

and the Certification of Completion date, CAMO was on the site for only 392 days,

and that only around 100 days were attributable to rain-out days. CAMO argued that

its records indicated 435 days on the job, asserting that the Town failed to include wet

days following the rain-out days and failed to include the work done prior to the

beginning of construction. The trial court agreed with the Town’s position, and the

record supports the trial court’s findings.

With regard to the proposed Change Order No. 5 that Hammett and

CAMO signed requesting a 217-day extension of time and the price increase for

extended overhead and delay damages, the Town apparently did not receive the

request until December 17, 2003, when Hammett attached it to his cover letter of the

27

same date. By that time, the 217 days had already expired, and the completion

certificate had been executed. Once the Town received the request, it began to

investigate, and found that the reports did not support either the time extension or the

price increase requested pursuant to CAMO’s claim for extended overhead and delay

damages. Therefore, the Town never signed or approved the original proposed

Change Order No. 5. For all of the reasons discussed above, proposed Change Order

No. 5 was not binding. Therefore, the Town was authorized under the contract to

deduct liquidated damages for the unapproved 217 days between the contract

expiration date on Change Order No. 3, which was May 5, 2003, and the date on the

Certificate of Substantial Completion, which was December 8, 2003.

CAMO argues that if it is found liable for liquidated damages, that such

damages should not be imposed beyond September 8, 2003, at which time it sent

correspondence to Capdepon that the pipe was installed pursuant to the drawings and

that CAMO was currently working on punch list items and dressing up recently

installed piping. However, the record also reveals that CAMO did not request the

Certificate of Substantial Completion until October 30, 2003. The Town chose to

impose liquidated damages only to October 12, 2003, which was a date nearer to the

first date scheduled for the pre-final inspection, which was October 9, 2003, pursuant

to Capdepon’s letter to the Mayor. The record indicates that the pre-final inspection

had to be rescheduled to December 8, 2003. Notwithstanding, the Town still chose

to deduct only 160 days of liquidated damages through October 12, 2003, for a total

of $80,000.00. The trial court determined that this was more than fair. We find no

manifest error in its judgment.

28

IV.

CONCLUSION

Based upon the foregoing, we affirm the trial court’s judgment

dismissing CAMO’s claims for additional compensation for extended overhead and

delay damages and for additional time on the subject contract with the Town of

Vidalia. All costs of this appeal are assessed against plaintiff-appellant, CAMO

Construction Co., Inc.

AFFIRMED.

29