CA-0008-0038 Nonprecedential Affirmed Processed

Arrowhead Contractors, Inc. v. Graybar Electric Co., Inc.

Louisiana Court of Appeal, Third Circuit · Filed November 5, 2008

Authorities cited

Identified automatically; this list may not be exhaustive.

Opinion text

STATE OF LOUISIANA
COURT OF APPEAL, THIRD CIRCUIT

08-38

ARROWHEAD CONTRACTORS, INC.

VERSUS

GRAYBAR ELECTRICAL COMPANY, INC., ET AL.

**********

APPEAL FROM THE
THIRTIETH JUDICIAL DISTRICT COURT
PARISH OF VERNON, NO. 72,631 B
HONORABLE JOHN C. FORD, DISTRICT JUDGE

**********

MARC T. AMY
JUDGE

**********

Court composed of Ulysses Gene Thibodeaux, Chief Judge, John D. Saunders and
Marc T. Amy, Judges.

AFFIRMED.
Thibodeaux, Chief Judge, dissents in part and assigns written reasons.

Elvin C. Fontenot, Jr.
110 East Texas Street
Leesville, LA 71446
(337) 239-2684
COUNSEL FOR INTERVENOR/APPELLEE:
Patrick Carr

Lamar M. Richardson, Jr.
110 Moore's Road
Mandeville, LA 70471
(985) 626-4414
COUNSEL FOR INTERVENOR/APPELLEE:
Manilo V. Mendoza

Robin D. Pittman
Baldwin, Haspel, Burke & Mayer, LLC
1100 Poydras Street, Suite 2200
New Orleans, LA 70163
(504) 585-7711
COUNSEL FOR DEFENDANT/APPELLEE:
Graybar Electrical Company, Inc.

Eugene J. Radcliff
Jonathan C. Augustine
Montgomery, Barnett, Brown, Read,
Hammond & Mintz, LLP
5353 Essen Lane, Suite 140
Baton Rouge, LA 70809
(225) 329-2800
COUNSEL FOR PLAINTIFF/APPELLANT:
Arrowhead Contractors, Inc.

AMY, Judge.

The plaintiff, a roofing subcontractor working at Fort Polk, alleged that the

general contractor failed to pay as agreed and that it breached its contract by not

supplying supervision at the site. The contractor placed the disputed funds into the

registry of the court and contested the breach of contract claim. Two roofing

businesses hired by the plaintiff intervened and asserted that they were not paid sums

due. The subcontractor responded by filing a reconventional demand against the

roofers. The trial court granted the contractor’s motion for involuntary dismissal on

the breach of contract claim. It also awarded the roofers’ demands from the funds

deposited with the court. The plaintiff appeals. For the following reasons, we affirm.

Factual and Procedural Background

Graybar Electrical Company, Inc., a contractor working on housing units at

Fort Polk, hired the plaintiff, Arrowhead Contractors, Inc., for roofing and painting

portions of the work. Arrowhead, in turn, hired subcontractors to complete the work.

Arrowhead filed this matter, alleging that Graybar breached its contract and that it

refused to pay the full sums owed. Although Graybar contested the breach of contract

claim, it deposited $41,251.72 into the court’s registry. Graybar indicated that the

figure “correspond[ed] to the amount Plaintiff’s subcontractors and suppliers have

asserted remains unpaid by Plaintiff to them.”

Two of Arrowhead’s roofing subcontractors, Patrick D. Carr d/b/a Carr

Construction and Manlio V. Mendoza and/or Custom Quality Construction, LLC,

filed petitions of intervention, seeking distributions from the sum in the court’s

registry. Arrowhead filed reconventional demands against Carr and Custom, alleging

its entitlement to the deposit. Arrowhead claimed that Carr failed to satisfy its

contract with Arrowhead, causing it to sustain repair costs, attorney fees, and court

costs. It further claimed damages for the loss of its contract with Graybar, which, it

contends, was caused by Carr’s breach. As for Custom, Arrowhead alleged that it

failed to perform under its contract, again causing repair costs, attorney fees, and

court costs. Arrowhead additionally sought damages associated with a mechanic’s

lien filed against it by Custom.

At the close of Arrowhead’s case, the trial court granted Graybar’s motion for

involuntary dismissal. On the remainder of the claims, and after the close of evidence,

the trial court found in favor of the intervenors.1 It awarded $5,190.00 to Carr and

1
The trial court rendered the following written reasons for ruling:

The court considers the testimony of the parties, evidentiary offerings and
post-trial memoranda and finds it more probable than not that the written contract
entered into by Mendoza (Custom Quality Construction) and Arrowhead was
modified to correct certain deficiencies which were ostensibly caused by
Arrowhead’s supplier in delivering the wrong kind of roof flashing. The Court,
therefore, concludes that the work billed for by Mendoza’s company, Custom Quality
Construction, reflecting the costs necessary to make the repairs. Therefore, the court
awards Custom Quality Construction $14,205.47 plus court costs and legal interest
from date of judicial demand. Per diem and travel expenses are not payable under
the contract.

Patrick Carr seeks payment for work alleged to have been performed under
an oral contract.

Carr entered into a verbal contract with Arrowhead’s superintendent and
according to Carr was told to invoice Arrowhead at the rate of $55.00 per square plus
ten percent.

Counsel for plaintiff argues that the Court should consider Carr’s testimony
unworthy because of impeachment and assume that Carr’s contract was for the same
amount as Custom Quality Construction’s. Custom Quality Construction’s contract
was for $55.00 per square foot with no mention of ten percent.

The Court considers all of these circumstances and particularly that each
invoice submitted by Carr was clearly marked $55.00 per square plus ten percent.
Invoices were consistently underpaid by Arrowhead for one reason or another but no
mention of an overcharge of ten percent per square. There was no mention of a ten
percent overcharge on checks written for payment, correspondence or pleadings. The
Court therefore finds that it is more probably than not that Carr’s contract was for
$55.00 per square plus ten percent.

Accordingly, the court awards Carr $5,190.00 plus costs of court and legal
interest from date of judicial demand.

2

$14,205.47 to Custom from the court’s registry. It ordered the remaining funds

distributed to Arrowhead.

Arrowhead appeals, assigning the following as error:

(A) The Trial Court legally erred by awarding monetary
relief/damages to the intervenors, CQC and Carr, considering
neither party put on a case-in-chief as a prerequisite to carrying
their respective burdens of proof to show entitlement to the relief
asserted in their petitions for intervention.

(B) The Trial Court was manifestly erroneous and/or clearly wrong in
disregarding the express and unambiguous language contained
within the four corners of ACI’s written subcontractor
agreements, along with the undisputed corroborating testimony of
several witnesses, to award CQC and Carr monetary relief and/or
damages for expenses not authorized under said agreements.

(C) The Trial Court was manifestly erroneous in granting Graybar’s
Motion for Involuntary Dismissal and refusing to adjudicate
ACI’s damages claim against Graybar, considering the undisputed
witness testimony that Graybar and ACI agreed Graybar would
have someone on-site to act as a liaison between ACI and Ft.
Polk’s Garrison Department to ensure ACI’s work would pass
government inspection.

Discussion

Burden of Proof

The trial encompassed Arrowhead’s main demand against Graybar, Carr and

Custom’s intervention for entitlement to funds in the registry of the court, and

Arrowhead’s reconventional demand for the funds. The trial court explained that the

claims would be heard together.2 Carr and Custom questioned Arrowhead’s

witnesses presented in support of its main demand. At the close of Arrowhead’s case,

counsel for both intervenors explained that they did not present additional witnesses

2
The trial court explained: “No, we’re going to take the whole thing together. He’s going
to finish with this witness, I’m going to turn it over to Graybar, then you’ll get a turn at the witness.
That’s the way we’re going to do every witness.” When asked whether he objected to this procedure,
counsel for Arrowhead stated: “That’s no problem with me and I have no objection, but, yes, Your
Honor, absolutely.”

3

as Arrowhead called their chosen witnesses in its case-in-chief. Arrowhead argues

Carr and Custom could not have sustained their burdens of proof without calling their

own witnesses.

Louisiana Code of Evidence Article 611(A) provides, in part:

A. Control by court. Except as provided by this Article and
Code of Criminal Procedure Article 773, the parties to a proceeding
have the primary responsibility of presenting the evidence and
examining the witnesses. The court, however, shall exercise reasonable
control over the mode and order of interrogating witnesses and
presenting evidence so as to:

(1) Make the interrogation and presentation effective for the
ascertainment of the truth;

(2) Avoid needless consumption of time[.]

The trial court explained that each party could question each of the witnesses called

in the presentation of the three causes before it. The evidence relied upon by the

intervenors to satisfy their burdens of proof was established at the time Arrowhead

called its witnesses. To require the intervenors recall these witnesses and establish

the same evidence again, as Arrowhead’s argument seemingly demands, would

obviously defeat the trial court’s procedure which avoided needless consumption of

time per Article 611(A)(2). Also, the record reflects that counsel for Arrowhead

questioned the intervenors’ representatives, Mr. Carr and Mr. Mendoza, on cross-

examination. The witnesses were questioned by their own counsel on direct

examination. Additionally, Carr presented a number of exhibits in addition to those

of Arrowhead.

This assignment lacks merit.

4

Contract with Custom

Custom asserted in its intervention that its demand of $18,705.47 for unpaid

invoices remained unpaid. Arrowhead denied Custom’s entitlement to the funds in

its reconventional demand, citing breach of contract, and alleging entitlement to

additional sums due for the breach. As explained above, the trial court awarded

Custom $14,205.473 from the deposited funds. It found that the contract between

Custom and Arrowhead, which prescribed payment for the roofing work at “$55.00

per square,” was “modified to correct certain deficiencies which were ostensibly

caused by Arrowhead’s supplier in delivering the wrong kind of roof flashing.” In

this assignment, Arrowhead contests the awarding of sums in excess of “$55.00 per

square” as provided by the contract. It contends that Custom’s “unauthorized

changes” to the contract negated the parties’ agreement.

Arrowhead’s arguments fail on this latter point as the record supports the

determination that the contract was modified, thereby taking resolution of the case

outside of the four corners of the contract. It also supports a determination that

Arrowhead consented to the modification.

As for consideration of evidence beyond the four corners of the contract,

La.Civ.Code art. 1848, states:

Testimonial or other evidence may not be admitted to negate or
vary the contents of an authentic act or act under private signature.
Nevertheless, in the interest of justice, that evidence may be admitted to
prove such circumstances as a vice of consent, or a simulation, or to
prove that the written act was modified by a subsequent and valid oral
agreement.

(Emphasis added.)

3
The trial court did not award that portion of Custom’s invoice related to travel and per diem
expenses, finding that Arrowhead had not agreed to pay these costs.

5

Mr. Mendoza, Custom’s owner, explained that:

[E]veryday whatever happened[,] my point of contact was Mr. Mills4 or
Mr. Ed [Obet] so those were the people that I went to and when I
explained to them this is going to take a lot of extra work and he says –
I was instructed for whatever extra work we would do we would get
paid. The original installation of the drip edge and step flashing we did
it for free. But having to come back all the way from New Orleans – to
drive four hours at 2 o’clock in the morning and come back here to fix
the drip edge and spent many hours it incurred a lot of extra expenses
for me and the person that came with me to fix the problems that we had
to correct after we received original instructions.

Custom’s counsel later questioned Mr. Mendoza as to his demand letter entered into

evidence, stating: “And each of those expenditures were approved by Mr. Mills that

– as you previously testified, is that correct?” Mr. Mendoza replied: “Yes, sir, he

told me that I would be paid for reasonable expenses and that’s what I put a price on

each foot.” Further, Arrowhead’s owner, Charles Stuckey, confirmed that he told Mr.

Mendoza that Mr. Mills and Mr. Obet had his authority to represent him as the owner

at the site. Assessments of Mr. Mendoza’s credibility regarding the guarantee of

payment and the evaluation of the evidence urged by Arrowhead were within the

purview of the trial court. Rosell v. Esco, 549 So.2d 840 (La. 1989). We find no

manifest error in its determinations.

Neither is there merit in Arrowhead’s assertion that the trial court erred in

failing to award it damages for what it contends was Custom’s substandard

workmanship. It asserts that it suffered “consequential damages by losing its

previously referenced roof contract at Ft. Polk.” While Arrowhead presented

evidence as to the quality of Custom’s work, it lacked evidence on how the work

4
Testimony indicated that James “Jimbo” Mills was Arrowhead’s supervisor for a period
of time during the project. Although Arrowhead attempted to call Mr. Mills as a witness, it was
precluded from doing so by failing to timely list him as a potential witness.

6

jeopardized Arrowhead’s contract with Graybar. The trial court’s determination was

not manifestly erroneous.

Contract With Carr

It was undisputed at trial that Arrowhead had no written contract with Carr as

Carr did not sign and return the contract presented by Arrowhead. Arrowhead

contended that, as with Custom, Carr was to be paid for $55.00 per square despite the

absence of a written contract. Carr maintained that he was to be paid $55.00 per

square plus ten percent. The trial court found the additional ten percent to be part of

Carr’s verbal contract with Arrowhead and awarded these additional sums invoiced

by Carr. Arrowhead contests the award of the additional percentage.

Louisiana Civil Code Article 1846 provides:

When a writing is not required by law, a contract not reduced to
writing, for a price or, in the absence of a price, for a value not in excess
of five hundred dollars may be proved by competent evidence.

If the price of value is in excess of five hundred dollars, the
contract must be proved by at least one witness and other corroborating
circumstances.

After review, we find that the record supports the determination that Carr’s verbal

contract with Arrowhead provided for the additional ten percent invoiced.

On questioning, Mr. Carr explained:

Q. And, so, when Mr. Mills hired you did you and he discuss
anything about how you were to bill on these invoices?

A. At first they was just desperate to have a roofer to roof out there.

Q. So, what did you and he talk about as far as what you were going
to charge for doing this roofing?

A. We was going by what he had for the price we agreed on and then
after I got started it all kind of changed up.

7

Q. All right. Well, on your invoices you marked $55 per square, is
that right?

A. Yes.

Q. And you added ten percent to that?

A. Yes.

Q. And what was the ten percent for?

A. Well, we was having to hang fascia board, we’d have to primer
paint it and we’d only use, like, ten foot of the board and the rest
of it they wouldn’t let us piece it. So, we had done did the work
on that and the roof was so cut up and we was using so many
shingles and there was a lot of waste with that and that’s where I
come up with the ten percent.

Q. And did you talk to Mr. Mills about that?

A. Yes, I did.

Q. And what did Mr. – did Mr. Mills authorize you to charge that
ten percent?

A. He took my invoices and turned them in.

Q. That’s who you gave the invoices to, didn’t you?

A. Yes, it was.

Q. And he approved them for payment, didn’t he?

A. Yes.

As the trial court observed, Carr’s invoices, submitted into evidence, each reflect a

charge of the additional ten percent. While a supervisor who replaced Mr. Mills,

George Tierney, explained that he did not authorize the payment of an additional ten

percent to Carr, he acknowledged that he did not hire or select Carr. In short, the trial

court accepted Mr. Carr’s testimony that he was authorized to charge an additional

ten percent, Mr. Carr consistently included this additional percentage in the invoices,

and Arrowhead personnel consistently submitted the invoices for payment. Given

8

these factors, we find no manifest error in the trial court’s conclusion that sufficient

corroborating circumstances existed to indicate that the parties contracted for the

additional ten percent demanded.

Neither is there merit in Arrowhead’s alternative argument that Carr and

Arrowhead did not have a contract pursuant to La.Civ.Code art. 1947 and related

jurisprudence. See Carter v. Huber & Heard, Inc., 95-142 (La.App. 3 Cir. 5/31/95),

657 So.2d 409, writ denied, 95-1662 (La. 10/6/95), 661 So.2d 471. Article 1947

provides: “When, in the absence of a legal requirement, the parties have

contemplated a certain form, it is presumed that they do not intend to be bound until

the contract is executed in that form.” Arrowhead contends that, because Carr failed

to sign and return the contract form, there was no enforceable contract. Article 1947

is not applicable to this situation. Rather, when Mr. Carr did not return the contract,

Carr’s work proceeded under Arrowhead’s supervision, invoices were submitted, and

sums, other than the contested additional ten percent were paid. Under these

circumstances, it is clear that both parties contemplated that they were bound without

the form initially proposed.

This assignment lacks merit.

Involuntary Dismissal of Graybar

Finally, Arrowhead contests the involuntary dismissal of its case against

Graybar. Its demand alleged that Graybar failed to have a Graybar representative on

site at all times who, according to Arrowhead, could have acted as a liaison between

it and the Fort Polk quality control officials ultimately responsible for approving the

roofing work. At trial, Arrowhead styled its claim as one for breach of contract and

tort.

9

Louisiana Code of Civil Procedure Article 1672(B) provides for an involuntary

dismissal as follows:

B. In an action tried by the court without a jury, after the plaintiff
has completed the presentation of his evidence, any party, without
waiving his right to offer evidence in the event the motion is not
granted, may move for a dismissal of the action as to him on the ground
that upon the facts and law, the plaintiff has shown no right to relief.
The court may then determine the facts and render judgment against the
plaintiff and in favor of the moving party or may decline to render any
judgment until the close of all the evidence.

A trial court’s granting of an involuntary dismissal is not reversible absent manifest

error. Citgo Petroleum Corp. v. Yeargin, Inc., 95-1574 (La.App. 3 Cir. 2/19/97), 690

So.2d 154, writ denied, 97-1223 (La. 9/19/97), 701 So.2d 169, writ denied, 97-1245

(La. 9/19/97), 701 So.2d 170.

Arrowhead points to testimony from Mr. Tierney and Mr. Stuckey, indicating

that Graybar informed Arrowhead at the commencement of Arrowhead’s work that

it would have a supervisor present to act as a liaison with Fort Polk officials.

Arrowhead asserted that the supervisor could have ensured that the roofing work was

acceptable at the time it was presented for inspection and approval. It contends that

this testimony should have been accepted by the trial court as it was uncontradicted.

Arrowhead points to Mr. Tierney’s testimony that he saw Graybar’s supervisor only

once during Arrowhead’s six month presence at the facility. Accordingly, it contends

that Graybar’s breach of contract was proven.

However, Arrowhead presented general statements and assumptions regarding

the assurance of supervision. It did not establish the parameters of any such

supervision. Accordingly, the trial court was not manifestly erroneous in finding

insufficient evidence on this point. Further, as recognized by the trial court,

10

Arrowhead did not support its claim with proof as to causation of damages.5 No

evidence revealed how supervision would have ensured that Arrowhead’s and its

subcontractors’ work would have more readily passed inspection and resulted in

fewer incurred costs. Although Arrowhead alleged that the supervision led to its

ultimate loss of work at the site, it again lacked proof to establish this claim.

Therefore, the trial court’s granting of the motion for involuntary dismissal was not

manifestly erroneous.

This assignment lacks merit.

DECREE

For the foregoing reasons, the judgment of the trial court is affirmed. All costs

of this appeal are assessed to the appellant, Arrowhead Contractors, Inc.

AFFIRMED.

5
In granting the involuntary dismissal, the trial court remarked:

[T]here was never any causation. Even if I were to find and stretch it and say,
okay, they had a duty because to have somebody there because of this big meeting
that they had when they awarded the bids, even if I were to find duty that they did not
have anybody there or that they didn’t come and help them when they cried out for
support. I still can’t find where that caused any damage to Arrowhead because
Arrowhead, apparently, had competent personnel and Mr. Tierney seems to be
extremely well accomplished in the fields of construction and there’s no reason why
he would have needed the general contractor’s man to come help him deal with this
problem – inspector, we had quality control man from Fort Polk. That’s where the
problem was.

11

STATE OF LOUISIANA
COURT OF APPEAL, THIRD CIRCUIT

08-38

ARROWHEAD CONTRACTORS, INC.

VERSUS

GRAYBAR ELECTRICAL COMPANY, INC., ET AL.

THIBODEAUX, Chief Judge, dissenting in part.

I disagree that the award of $14,205.47 to Custom was proven with

sufficient competent evidence. Custom’s own representative/owner, Mr. Mendoza,

himself agreed that these charges were beyond the four corners of the agreement. The

written contract between Arrowhead and Custom did not modify any oral

representations worthy of any credible cognizance. Further, Mr. Mendoza admitted

that the written agreement did not authorize those amounts of money for the

additional charges.

For the foregoing reasons, I respectfully dissent in part.