CA-0010-0194 Nonprecedential Reversed and remanded Processed

Charles Ebinger, Et Ux. v. Venus Construction Corporation

Louisiana Court of Appeal, Third Circuit · Filed October 6, 2010

Authorities cited

Identified automatically; this list may not be exhaustive.

Opinion text

STATE OF LOUISIANA
COURT OF APPEAL, THIRD CIRCUIT

10-194 consolidated with CW 09-1407

CHARLES EBINGER, ET UX.

VERSUS

VENUS CONSTRUCTION CORPORATION, ET AL.

**********

APPEAL FROM THE
FIFTEENTH JUDICIAL DISTRICT COURT
PARISH OF LAFAYETTE, NO. 20035416
HONORABLE EDWARD B. BROUSSARD, DISTRICT JUDGE

**********

MARC T. AMY
JUDGE

**********

Court composed of John D. Saunders, Marc T. Amy, and Elizabeth A. Pickett,
Judges.

REVERSED AND REMANDED.

Wayne M. Babovich
Babovich & Spedale, PLC
1750 St. Charles Avenue, Unit 206
New Orleans, LA 70130
(504) 310-3886
COUNSEL FOR DEFENDANT/APPELLEE:
Roy Carubba

Thomas J. Eppling
Craig W. Brewer
Sara P. Scurlock
Staines, Eppling & Myers
3500 N. Causeway Boulevard, Suite 820
Metairie, LA 70002
(504) 838-0019
COUNSEL FOR DEFENDANT/APPELLEE:
Post-Tension Slabs, Inc.

Thomas H. Morrow
William Lee Melancon
Melancon & Associates
900 S. College Boulevard, Suite 300
Lafayette, LA 70503
(337) 233-8600
COUNSEL FOR PLAINTIFFS/APPELLEES:
Charles Ebinger
Charlene Ebinger

W. Evan Plauche'
Justin E. Alsterberg
Shailendra Kulkarni
Hailey, McNamara, Hall, Larmann & Papale, LLP
One Galleria Boulevard, Suite 1400
Metairie, LA 70011-8288
(504) 836-6500
COUNSEL FOR DEFENDANT/APPELLANT:
Venus Construction Corporation

Glen E. Mercer
Kourtney Twenhafel French
Salley, Hite, Rivera & Mercer
365 Canal Street, Suite 1710
New Orleans, LA 70130
(504) 566-8800
COUNSEL FOR DEFENDANT/APPELLEE:
Maryland Insurance Company

AMY, Judge.

The plaintiffs filed suit against their home contractor alleging structural defects

in the home’s construction. The contractor later filed a third party demand against a

subcontractor and an engineer. The engineer was dismissed from the demand upon

a granting of an exception of peremption pursuant to La.R.S. 9:5607. That

determination was affirmed on appeal. The subcontractor also filed an exception of

prescription which was granted by the trial court in light of the determinations as to

the engineer. The contractor seeks review of the subcontractor’s dismissal, filing

both an application for supervisory writ and an appeal. On consolidated review, we

reverse and remand.

Factual and Procedural Background

The plaintiffs, Charles and Charlene Ebinger, engaged Venus Construction

Corporation to construct their residence in 1995. In the 2003 petition instituting this

matter, the plaintiffs alleged that the home contained major structural defects,

including defects in the foundation system which resulted in, among other things,

cracks in the sheet rock, tile, and brick floor. The plaintiffs sought recovery under

the New Home Warranty Act, see La.R.S. 9:3141, et seq., and named Venus as a

defendant.

In a 2006 Third Party Demand, Venus sought indemnification from Post-

Tension Slabs, Inc., a foundation subcontractor, and from Roy Carubba, an engineer.

Mr. Carubba filed an exception of peremption based on La.R.S. 9:5607. He observed

that La.R.S. 9:5607, as enacted in 2003, contained a five-year peremptive period for

suits brought under the New Home Warranty Act and argued that this period should

be applied retroactively to dismiss Venus’s indemnification suit against him. The

trial court granted the exception as the third party demand was not filed until nine

years after the home was completed. On appeal, a panel of this court affirmed the

trial court’s ruling that, prior to the 2003 enactment of La.R.S. 9:5607, Venus’s claim

for indemnification did not yet exist. See Ebinger v. Venus Constr. Corp., 08-379

(La.App. 3 Cir. 10/1/08), 995 So.2d 1224. The panel determined that Venus acquired

an unvested, conditional right to indemnification at the time the Ebingers filed the

initial suit. Id. However, it was three additional years until Venus filed a third party

demand against Mr. Carubba and no judgment on the Ebingers’ suit had been

rendered against Venus at that time. By then, Venus’s claim was perempted by the

five-year peremptive period of La.R.S. 9:5607.1

Thereafter, and at issue in this review, Post-Tension filed an exception of

prescription, asserting that Venus’s claim for indemnification had perempted against

it as it had against Mr. Carubba since both claims were for indemnification. The trial

1
Entitled “Actions against a professional engineer, surveyor, professional interior
designer, architect, real estate developer; peremptive period[,]”, La.R.S. 9:5607 provides:

A. No action for damages against any professional engineer, surveyor,
engineer intern, surveyor intern, or licensee as defined in R.S. 37:682, or any
professional architect, landscape architect, architect intern, or agent as defined in R.S.
37:141, or professional interior designer, or licensee as defined in R.S. 37:3171, or
other similar licensee licensed under the laws of this state, or real estate developer
relative to development plans which have been certified by a professional engineer
or professional architect, whether based upon tort, or breach of contract, or otherwise
arising out of an engagement to provide any manner of movable or immovable
planning, construction, design, or building, which may include but is not limited to
consultation, planning, designs, drawings, specifications, investigation, evaluation,
measuring, or administration related to any building, construction, demolition, or
work, shall be brought unless filed in a court of competent jurisdiction and proper
venue at the latest within five years from:
....
(2) The date the owner has occupied or taken possession of the
improvement, in whole or in part, if no such acceptance is recorded[.]
....
B. The provisions of this Section shall apply to all persons whether or not
infirm or under disability of any kind and including minors and interdicts.
C. The five-year period of limitation provided for in Subsection A of this
Section is a peremptive period within the meaning of Civil Code Article 3458 and
in accordance with Civil Code Article 3461, may not be renounced, interrupted, or
suspended.
D. The provisions of this Section shall take precedence over and
supersede the provisions of R.S. 9:2772 and Civil Code Article 2762 and 3545.

2

court granted the exception and dismissed Venus’s claim against Post-Tension Slab.

Venus seeks review of the ruling through application for supervisory writ and by

appeal.2 These matters were consolidated for review.

Discussion

Venus contends that the trial court erred in determining that its right to

indemnification vested at the time of the main 2003 demand. It argues, instead, that

its right vested, at the latest at the time the home was occupied in April 1997. In

support of this, it points to Post-Tension’s completion of its foundation work prior to

the home’s occupancy. It also contends that Post-Tension fulfilled, or breached, its

contract by that time period and, therefore, the applicable peremptive period is that

in place at the time of the occupancy.

As Post-Tension is a contractor rather than an engineer, like Mr. Carubba in the

first review of this matter in Ebinger, 995 So.2d 1224, La.R.S. 9:2772 provides the

applicable peremptive period in this case. Venus and Post-Tension differ, however,

on which version of the statute is applicable.

Post-Tension argues that the statute, as amended in 2003, is applicable and

provides a five-year peremptive period. This version of the statute, which was

followed by the trial court, provides:

§ 2772. Peremptive period for actions involving deficiencies in
surveying, design, supervision, or construction of
immovables or improvements thereon

A. No action, whether ex contractu, ex delicto, or otherwise,
including but not limited to an action for failure to warn, to recover on
a contract, or to recover damages, or otherwise arising out of an
engagement of planning, construction, design, or building immovable
or movable property which may include, without limitation,

2
For disposition of the companion writ application, see Ebinger v. Venus Constr. Corp.,
CW09-1407 (La.App. 3 Cir. _/_/10), _ So.3d _.

3

consultation, planning, designs, drawings, specification, investigation,
evaluation, measuring, or administration related to any building,
construction, demolition, or work, shall be brought against any person
performing or furnishing land surveying services, as such term is
defined in R.S. 37:682, including but not limited to those services
preparatory to construction, or against any person performing or
furnishing the design, planning, supervision, inspection, or observation
of construction or the construction of immovables, or improvement to
immovable property, including but not limited to a residential building
contractor as defined in R.S. 37:2150.1(9):

(1)(a) More than five years after the date of registry in the
mortgage office of acceptance of the work by owner.

(b) If no such acceptance is recorded within six months from
the date the owner has occupied or taken possession of the
improvement, in whole or in part, more than five years after the
improvement has been thus occupied by the owner.

....

B. (1) The causes which are perempted within the time
described above include any action:

....

(b) For damage to property, movable or immovable, arising out
of any such deficiency.

....

(3) This peremptive period shall extend to every demand,
whether brought by direct action or for contribution or indemnity or by
third-party practice, and whether brought by the owner or by any other
person.

Thus, Post-Tension contends that the peremptive period for Venus’s

indemnification claim commenced in 1997 at the time the Certificate of Occupancy

was issued. See La.R.S. 9:2772(A)(1). It further argues that, since Venus did not file

its third party demand until 2006, its claim was perempted due to the expiration of

more than five years. The trial court, citing Ebinger, 995 So.2d 1224, agreed with

4

Post-Tension and applied the 2003 version of La.R.S. 9:2772 in dismissing the

matter.

Venus, however, contends that the 1997 version of La.R.S. 9:2772 is applicable

as it set forth the peremptive period at the time the Certificate of Occupancy was

issued, or alternatively, as the latest day its contract with Post-Tension could have

been breached. In 1997, the statute included a ten-year peremptive period and

provided:

A. No action, whether ex contractu, ex delicto, or otherwise,
including, but not limited to, an action for failure to warn, to recover on
a contract or to recover damages shall be brought against any person
performing or furnishing land surveying services, as such term is
defined in the first paragraph of R.S. 37:682(9), including but not
limited to those services preparatory to construction, or against any
person performing or furnishing the design, planning, supervision,
inspection, or observation of construction or the construction of an
improvement to immovable property:

(1) More than ten years after the date of registry in the
mortgage office of acceptance of the work by owner; or

(2) If no such acceptance is recorded within six months from
the date the owner has occupied or taken possession of the
improvement, in whole or in part, more than ten years after the
improvement has been thus occupied by the owner[.]

....

B. The causes which are perempted within the time described
above include any action:

(1) For any deficiency . . . . in the construction of any
improvement to immovable property;

....

This peremptive period shall extend to every demand whether
brought by direct action or for contribution or indemnity or by third
party practice, or whether brought by the owner or by any other person.

5

Thus, the final clause of La.R.S. 9:2772(B) specifically indicates that the

peremptive period is applicable to an indemnity claim. Moreover, Venus asserts that

its right to seek indemnity against Post-Tension became a vested right at the time of

occupancy.

Generally, Louisiana courts have determined that prescription on an

indemnification claim “begins to run when the indemnity claimant suffers the loss or

damage, at the time of the payment of the underlying claim, payment of a judgment

thereon, or payment of a settlement thereof by the party seeking indemnity, i.e., when

the judgment has been cast.” Reggio v. E.T.I., 07-1433, p. 9 (La. 12/12/08), 15 So.3d

951, 957 (emphasis in the original). This was recognized by the panel in Ebinger,

995 So.2d at 1226, when it explained:

Prior to the enactment of the statute, Venus Construction had not yet
been sued by the Ebingers; therefore, no right to indemnification for the
Ebingers’ potential claims existed. Once the Ebingers’ suit was filed,
Venus Construction acquired an unvested, conditional right to
indemnification. Nevertheless, three years passed before Venus
Construction filed its third party demand against Roy Carubba, and no
judgment had yet been rendered against Venus Construction.

Accordingly, the Ebinger panel determined that Venus’s indemnity claim against Mr.

Carubba had perempted as the period expired before the third party demand was filed

or Venus was cast in judgment. Post-Tension seeks to apply that general principle

to its contention that Venus’s indemnity claim has similarly perempted.

Yet, La.R.S. 9:5607, as applied in the first Ebinger review, and La.R.S. 9:2772

differ. La.R.S. 9:2772(B), at all times pertinent to this matter, has provided that “this

peremptive period shall extend to every demand, whether brought by direct action or

for contribution or indemnity or by third-party practice, and whether brought by the

owner or by any other person.” (Emphasis added.) This provision deliberately

6

commenced the peremptive period at the time of the 1997 Certificate of Occupancy

and became a vested right of the indemnity claimant. Jurisprudence has recognized

that La.R.S. 9:2772 is “an exception to the general rule that a claim for

indemnification doesn’t begin to prescribe until the party is cast in judgment.” See

Claiborne v. Rheem Mfg. Co., 579 So.2d 1199, 1200 (La.App. 5 Cir.)(citing Smith v.

Ly, 498 So.2d 128 (La.App. 5 Cir. 1986)), writ denied, 584 So.2d 1164 (1991).

For these reasons, Post-Tension’s reliance on Ebinger, 995 So.2d 1224, and

Patriot American Hospitality Partnership, LP v. Mississippi Land Holdings, Inc., 06-

0601 (La.App. 4 Cir. 12/13/06), 948 So.2d 249, writ denied, 07-80 (La. 3/9/07), 949

So.2d 450, is misplaced as both cases involved interpretations of La.R.S. 9:5607. See

also Lafayette Parish Sch. Bd. v. Ratcliff Constr. Co., 09-762 (La.App. 3 Cir. 2/3/10),

30 So.3d 279, writ granted in part, denied in part, 10-0931 (La. 9/17/10), _ So.3d _

(wherein the Louisiana Supreme Court recently remanded the matter to the district

court to allow the plaintiff to remove the grounds of the exception of peremption by

amendment of the petition.).

Furthermore, this case falls outside of the general concept that a law modifying

the duration of prescription will be inapplicable in cases where prescription has

accrued, but may be applicable to those which are running. See Elevating Boats, Inc.

v. St. Bernard Parish, 00-3518 (La. 9/15/01), 795 So.2d 1153. This jurisprudence is

inapplicable in cases in which a statute shortens a prescriptive period, as here. Id. at

163, n. 12. Instead, the supreme court has remarked that “[p]rinciples of fairness and

equity combined with constitutional considerations have led us to find that statutes

shortening a prescriptive period may be impermissible absent a transitional period

7

sufficient to permit a claimant to seek judicial enforcement of a claim otherwise

adversely affected by the new prescriptive period.” Id. (Emphasis in the original.)

For these reasons, we find error in the trial court’s retroactive application of

La.R.S. 9:2772 in granting Post-Tension’s exception of prescription. We reverse that

determination and remand for further proceedings.

DECREE

For the foregoing reasons, the trial court’s dismissal of the appellee, Post-

Tension Slabs, Inc., pursuant to the granting of the exception of prescription is

reversed. This matter is remanded for further proceedings. All costs of this

proceeding are assessed against the appellee, Post-Tension Slabs, Inc.

REVERSED AND REMANDED.