CA-0017-0913 Nonprecedential Affirmed Processed

Ronald Colson and Virginia Colson v. Colfax Treating Co, LLC

Louisiana Court of Appeal, Third Circuit · Filed April 18, 2018

Opinion text

STATE OF LOUISIANA
COURT OF APPEAL, THIRD CIRCUIT

17-913 consolidated with 17-912

RONALD COLSON AND VIRGINIA COLSON, ET AL.

VERSUS

COLFAX TREATING CO, LLC, ET AL.

**********

APPEAL FROM THE
NINTH JUDICIAL DISTRICT COURT
PARISH OF RAPIDES, NO. 236,116 C/W 236,112
HONORABLE WILLIAM GREGORY BEARD, DISTRICT JUDGE

**********

SHANNON J. GREMILLION
JUDGE

**********

Court composed of Marc T. Amy, Shannon J. Gremillion, and Candyce G. Perret,
Judges.

MOTION TO STRIKE GRANTED. MOTION TO SUPPLEMENT THE
RECORD DENIED. JUDGMENT AFFIRMED.

Joseph J. Bailey
Eli J. Meaux
Provosty, Sadler, & deLaunay, APC
P. O. Drawer 1791
Alexandria, LA 71309-1791
(318) 445-3631
COUNSEL FOR PLAINTIFFS/APPELLANTS:
Virginia Colson
Ronald Colson

Daniel E. Broussard, Jr.
Broussard, Halcomb & Vizzier
P. O. Box 1311
Alexandria, LA 71301
(318) 487-4589
COUNSEL FOR PLAINTIFFS/APPELLANTS:
Virginia Colson
Ronald Colson

Randall B. Keiser
David E. Boraks
Keiser Law Firm, P.L.C.
P. O. Box 12358
Alexandria, LA 71315
(318) 443-6168
COUNSEL FOR DEFENDANT/APPELLEE:
City of Pineville

2

GREMILLION, Judge.

Plaintiffs/appellants, Ronald and Virginia Colson, appeal summary judgment

in favor of the City of Pineville in this suit arising from damage to the Colsons’

home in the wake of Hurricane Gustav. The City filed a Motion to Strike the

Colsons’ reply brief. In response to the City’s motion to strike, the Colsons filed a

motion for leave to exceed the page limit on reply briefs. The Colsons also filed a

motion to supplement the record with documents proffered at the hearing on the

motion for summary judgment but were excluded from evidence by the trial court.

For the reasons that follow, we grant the City’s motion to strike, deny the Colsons’

motion to supplement the record, and affirm the trial court.

FACTS AND PROCEDURAL HISTORY

The Colsons own property on Church Street in Pineville, Louisiana. They

alleged in their petition that their property was flooded on September 1 and 2, 2008,

and that the flood water was contaminated with creosote/pentachlorophenol, TPH

diesel, and other contaminates that originated at the Colfax Treating Company’s

(Colfax) wood treating facility in Pineville, which was allowed by permit to be

disposed of through Pineville’s waste water system. When Hurricane Gustav

inundated Central Louisiana with heavy rains, according to the petition,

contaminated waste and storm water overwhelmed Pineville’s system and

contaminated the Colsons’ property. The petition further alleges that the

contamination resulted in the Colsons’ forcible and unlawful eviction from their

home. The Colsons sued both Colfax and the City. The City is alleged to have

failed to timely activate pumps designated to evacuate waste and storm water,

failed to properly inspect or maintain those pumps prior to the event, and allowed

Colfax to improperly dispose of these contaminates above legally-allowed limits.

The Colsons’ suit was joined with two other neighbors and consolidated

with a similar action filed by yet more neighbors in the Church Street area. The

other actions, though, have all been dismissed.

The City filed a motion for summary judgment on October 17, 2016, in

which it asserted that it was immune from liability pursuant to the Louisiana

Homeland Security and Emergency and Disaster Assistance Act (“the Act”),

La.R.S. 29:721-39. A second motion for summary judgment was filed the same

day and asserted that the City was not liable for flooding, as the Red River,

Atchafalaya, and Bayou Boeuf Levee District was solely responsible for flood

control within the area of its operation, which includes the City of Pineville.

The Colsons filed oppositions to these motions, arguing that the City

violated applicable Environmental Protection Agency and Louisiana Department

of Environmental Quality statutes, orders, and regulations governing waste water

contaminants, as well as requirements that it develop a plan to deal with situations

like it faced in Hurricane Gustav. Further, the Colsons argued, the City was

empowered by terms of its permit to Colfax to order Colfax to cease releasing

waste into its system. In their opposition, the Colsons offered the affidavit of Dr.

Nicholas P. Cheremisinoff, Ph.D., a chemical engineer with many years of

experience in environmental management and a CD containing several exhibits,

which they sought to authenticate through the affidavit of their counsel. They also

offered the deposition of Mr. Colson.

The Colsons’ exhibits presented in opposition to the City’s motion, other

than the affidavits and deposition, were contained on a compact disc. The City

filed, in its reply memorandum, an objection to all of the Colsons’ exhibits except

Mr. Colsons’ deposition.

2

The Colsons sought a continuance of the hearing on the City’s motions

because of outstanding discovery issues. Nonetheless, the motions were heard by

the trial court on January 9, 2017. The trial court also heard the City’s objections

to various exhibits and struck all exhibits besides Dr. Cheremisinoff’s affidavit and

Mr. Colsons’ deposition. The Colsons then made a proffer of those exhibits. The

trial court rendered judgment in favor of the Colsons on the issue of the City’s

immunity under the Act. It ruled in favor of the City on the issue of flooding,

rendering judgment as follows (emphasis in original):

IT IS FURTHER ORDERED, ADJUDGED, AND DECREED
THAT the City of Pineville’s Motion for Summary Judgment based
on LSA-R.S. 38:291 et seq. is hereby GRANTED and that all claims
against the City of Pineville by Plaintiffs for injuries and damages
related to flooding are hereby dismissed with prejudice at Plaintiffs’
sole cost;

IT IS FURTHER HEREBY ORDERED, ADJUDGED, AND
DECREED THAT all of Plaintiffs’ claims for damages resulting from
the City of Pineville’s sewer system are not dismissed and remain
pending before this Court.

The Colsons perfected this appeal of the judgment. They assert that the trial court

erred in not continuing the hearing, in striking certain exhibits, and in granting

summary judgment on the issue of flooding. The City answered the Colsons’

appeal and ask that this court reverse the trial court’s denial of its motion for

summary judgment regarding applicability of the Act.

The City has also filed a motion to strike the Colsons’ reply brief because it

exceeds the thirteen-page limit on reply briefs found in Uniform Rules—Courts of

Appeal, Rule 2-12.2(D) and Internal Rules—Third Circuit Court of Appeal, Rule

18.

DISCUSSION AND ANALYSIS

Courts of appeal review summary judgments de novo employing the same

analysis as does a trial court. Samaha v. Rau, 07-1726 (La. 2/26/08), 977 So.2d
3

880. The mover bears the burden of proof in a motion for summary judgment to

prove that there is no genuine issue of material fact and that it is entitled to

judgment as a matter of law. La.Code Civ.P. arts. 966, 967.

The City’s motion to strike the Colsons’ reply brief

Uniform Rules—Courts of Appeal, Rule 2-12.2(D) provides that reply briefs

on 8 ½"x 14" paper are limited to thirteen pages, exclusive of the tables of contents

and authorities. The Colsons’ reply brief exceeds the authorized page limit at

sixteen pages. This court has discretion to allow a reply brief when in the interest

of justice. In the present matter, we do not find that the interests of justice are

furthered by allowing this departure from our rules. The City’s motion to strike the

Colsons’ reply brief is granted.

Striking exhibits and the motion to supplement the record

Louisiana Code of Civil Procedure Article 966(A)(4) prescribes the

documents that may support or oppose a motion for summary judgment. Those are

“pleadings, memoranda, affidavits, depositions, answers to interrogatories,

certified medical records, written stipulations, and admissions.” Under La.Code

Civ.P. art. 966(D)(2), the court may only consider the documents filed in support

of or in opposition to the motion, “and shall consider any documents to which no

objection is made.” Objections must be raised in a timely-filed opposition or reply

memorandum. Id.

The contents of the compact disc contain no self-authenticating formal

requirements and do not meet the criteria of La.Code Civ.P. art. 966(A)(4). They

primarily consist of items obtained from the websites of governmental agencies.

Much of this information was contained or summarized in Dr. Cheremisinoff’s

affidavit, which was considered by the trial court. Accordingly, we affirm the trial

4

court’s grant of the City’s motion to strike and deny the Colsons’ motion to

supplement the record on appeal.

Refusal to grant a continuance of the hearing

Louisiana Code of Civil Procedure Article 966(C)(4) provides that the trial

court may continue a hearing on a motion for summary judgment “[f]or good cause

shown.” The determination of whether a trial court should have granted a

continuance of a hearing on a motion for summary judgment is reviewed by this

court to determine whether the trial court abused its discretion. Advance Prods. &

Sys., Inc. v. Simon, 06-609 (La.App. 3 Cir. 12/6/06), 944 So.2d 788, writ denied,

07-26 (La. 3/9/07), 949 So.2d 444.

The Colsons sought a continuance of the hearing on the motion for summary

judgment on the grounds that discovery requests had not been answered by the

City and they were intent on taking depositions, but needed responses to their

written requests first. The trial court held that La.Code Civ.P. art. 966 provides

that the parties be given adequate opportunity for discovery. Given the length of

time suit had been filed, the trial court opined that adequate opportunity for

discovery had been afforded.

A review of the record1 reveals that the suit was filed on August 31, 2009.

The matter was consolidated for trial in 2010. A flurry of activity followed the

trial court’s denial of an exception of prescription filed by the City in the

consolidated matter. Several parties’ claims, also in the consolidated matter, were

dismissed in 2010. Thereafter, between December 2010 and June 2016, there were

two dismissals, a motion to enroll as co-counsel, and a motion to withdraw as

counsel. In June 2016, the City filed a motion for leave to amend its answer. In

1
After this matter was consolidated, pleadings that should have been designated for filing
in this matter were actually filed in the record of the consolidated matter, Mack v. Colfax
Treating Co., Inc., 17-912. For purposes of this appeal, we have reviewed both records.
5

October 2016, this motion for summary judgment was filed. The motion was not

heard until January 2017. We can find no abuse of the trial court’s discretion in

this ruling. This assignment of error lacks merit.

Immunity under the Act

The City argues that the trial court erred in denying its motion for summary

judgment under the Act. Immunity under the Act is an affirmative defense that

must be specifically pleaded. Rogers v. State, ex rel. Dep’t of Pub. Safety and

Corr., 07-1060 (La.App. 3 Cir. 1/30/08), 974 So.2d 919, writ denied, 08-504 (La.

4/25/08), 978 So.2d 367. The burden of proof of an affirmative defense lies with

its proponent. Hines v. Garrett, 04-806 (La. 6/25/04), 876 So.2d 764. “If the party

moving for summary judgment will bear the burden of persuasion on the subject

issue at trial, that party must support his motion with credible evidence that would

entitle him to a directed verdict if not controverted at trial.” Id. at 766.

Louisiana Revised Statutes 29:735(A)(1) reads:

Neither the state nor any political subdivision thereof, nor other
agencies, nor, except in case of willful misconduct, the agents’
employees or representatives of any of them engaged in any homeland
security and emergency preparedness activities, while complying with
or attempting to comply with this Chapter or any rule or regulation
promulgated pursuant to the provisions of this Chapter shall be liable
for the death of or any injury to persons or damage to property as a
result of such activity.

‟‘Emergency preparedness’ means the mitigation of, preparation for, response to,

and the recovery from emergencies or disasters. The term ‘emergency

preparedness’ shall be synonymous with ‘civil defense’, ‘emergency management’,

and other related programs of similar name.” La.R.S. 29:723(4). The provisions

of the Act are initiated with the issuance of a declaration “by executive order or

proclamation of the governor if he finds a disaster or emergency has occurred or

the threat thereof is imminent.” La.R.S. 29:724(B)(1). As with all statutes that

6

confer immunity from liability, La.R.S. 29:735 is strictly construed. Robertson v.

St. John the Baptist Parish, 15-240 (La.App. 5 Cir. 10/14/15), 177 So.3d 785.

In support of its motion, the City annexed a copy of the emergency

declaration issued by Governor Bobby Jindal, 51 BJ 2008, which declared a state

of emergency throughout the State of Louisiana. The City also annexed thereto the

affidavit of Mr. Charlie Moore, who was Superintendent of Public Works for the

City at the time the emergency was declared. Mr. Moore attested that the City of

Pineville’s waste water (sewerage) and storm drainage systems are entirely

separate. The City’s lift stations were powered by electricity delivered by CLECO.

The lift stations lost power during Hurricane Gustav; before and after the loss of

power, the lift stations were operating properly.

To prevail in a claim of immunity under the Act, the City must demonstrate

that the acts or omissions complained of occurred during the declared emergency.

Bordelon v. Gravity Drainage Dist. No. 4 of Ward 3 of Calcasieu Parish, 10-1318

(La.App. 3 Cir. 10/5/11), 74 So.3d 766, writ denied, 11-2438 (La. 1/13/12), 77

So.3d 971. As will be discussed more fully, the issue is not the failure of pumps or

loss of power to pumps. There exist genuine issues of material fact in this case

regarding alleged actions or omissions that well predated Hurricane Gustav.

Dr. Cheremisinoff attested that he reviewed documents produced by the

Louisiana Department of Environmental Quality, the City, and Colfax. He also

relied upon the depositions of the Colsons. From prior experience consulting in

other litigation and from his review of the records, Dr. Cheremisinoff opined that

Colfax has a long history of problems complying with its permit from the City that

resulted in a Consent Agreement between the City and Colfax, under which Colfax

agreed to install some treatment equipment of its own to bring it into compliance

with the permit issued by the City. This Consent Agreement was dated August 4,
7

2008, less than a month before Gustav’s landfall. Dr. Cheremisinoff also outlined

the City’s obligations under federal and state laws and regulations, including the

requirement that it identify events in which overflow can occur and plan

accordingly.

Most crucial, though, was Mr. Colsons’ testimony that sewerage, and thus

these chemicals, was being released from the sewer cleanout adjacent to the

Colsons’ property before the heavy rains and flooding started. This demonstrates a

genuine issue of material fact regarding the applicability of the Act to this matter.

The City’s assignment of error lacks merit.

The City’s responsibility for flood control

The Colsons argue that the trial court erred in granting the City’s motion for

summary judgment on the issue of whether the City is relieved of liability for

flooding. The City argued that the entity responsible for flood control is the Red

River, Atchafalaya, and Bayou Boeuf Levee District (the Levee District).

Asserting that another is at fault or bears the legal obligation that forms the

basis of a plaintiff’s suit is an affirmative defense. La.Code Civ.P. art. 1005. The

City bears the burden of proof of this defense.

The Levee District’s territorial limits are fixed by La.R.S. 38:291(M). The

territory includes the City. La.R.S. 38:291(M)(1)(c). We see no authority in the

statutes governing levee districts, however, that relieves other governmental

entities within a levee district’s territory of liability for the failure of storm

mitigation systems not built by the levee district.

In Fryoux v. Tensas Basin Levee District, 12-997 (La.App. 3 Cir. 2/6/13)

(unpublished), this court faced the issue of liability of the Tensas Basin Levee

District (TBLD) from flood damage during Hurricane Gustav. The TBLD filed a

motion for summary judgment asserting that under the Act it was immune from
8

liability for emergency preparedness activities. The Town of Jonesville filed

exceptions asserting that TBLD owned, maintained, and controlled the levee

system in Catahoula Parish, including the ring levee gates that, had they operated

correctly, according to the plaintiffs’ petition, would have prevented their flooding

damage. The trial court maintained this exception, and the plaintiffs did not appeal.

TBLD’s motion for summary judgment was granted, and plaintiffs appealed.

On appeal, we found that a genuine issue of material fact existed regarding

which entity was responsible for the flood control structures within the town. We,

therefore, reversed summary judgment in favor of TLBD.

It is certainly implicit in this discussion that ownership and control of the

flood prevention works determines whether a city or a levee district is potentially

liable for its failure. See La.Civ.Code arts. 2317, 2317.1.

The City argues, however, that the Colsons have judicially confessed that

they have no damage claims arising from any flooding event. In support of its

argument, the City cites La.Civ.Code art. 1853, which reads, “A judicial

confession is a declaration made by a party in a judicial proceeding. That

confession constitutes full proof against the party who made it. A judicial

confession is indivisible, and it may be revoked only on the ground of error of

fact.” The City argues the Colsons have judicially confessed that their damages

were not caused by “flood waters.” Indeed, in argument before the trial court,

counsel for the Colsons admitted that his clients’ damages were not caused by

flood water. Arguments of counsel can serve as a judicial confession. Id. at

Comment (b).

We see no contradiction between counsel’s arguments and the allegations of

the petition. The petition sets forth that the condition of the Colsons’ home that

has prevented and continues to prevent its occupation is the presence of
9

pentachlorophenol and other contaminants, not water. Thus, we see no

contradiction between the arguments before the trial court and this court and the

contents of the Colsons’ petition. “The purpose of summary judgment is to ‘pierce

the pleadings and to assess the proof in order to see whether there is a genuine

need for trial.’” Hines, 876 So.2d at 769 (quoting Matsushita Elec. Indus. Co. v.

Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 1356 (1986)). The

Colsons’ damages, if substantiated at trial, are asserted in pleadings and in Dr.

Cheremisinoff’s affidavit to have resulted from chemical contamination and not

from flood waters.

Accordingly, we affirm summary judgment on the issue of liability on the

City’s part for flood damage, but not on the basis of any immunity of the City by

virtue of the creation of the levee district.

SUMMARY

The City’s motion to strike the Colsons’ reply brief is granted. We find no

error in the trial court’s refusal to grant a continuance of a hearing on a motion for

summary judgment filed in a case in which the petition was filed seven years

before the motion. Seven years certainly represents an adequate opportunity for

discovery in this case. We find no error in the trial court’s exclusion of the

documents on the CD submitted by the Colsons; the pertinent information was

summarized in Dr. Cheremisinoff’s deposition.

The trial court properly denied the City’s motion for summary judgment on

the issue of immunity under the Louisiana Homeland Security and Emergency and

Disaster Assistance Act. Genuine issues of material fact exist regarding whether

the Act applies to this matter. The trial court properly granted summary judgment

on the issue of the City’s responsibility for “flood waters,” not because the levee

10

district is liable for them, but because the evidence demonstrates that the plaintiffs’

damages arise from chemical contamination.

The motion to strike Appellants’ reply brief filed by the City of Pineville is

granted. The judgment of the trial court is affirmed. All costs of this appeal, in the

amount of $1,997.50, are taxed as costs to the City of Pineville.

MOTION TO STRIKE GRANTED. MOTION TO SUPPLEMENT

THE RECORD DENIED. JUDGMENT AFFIRMED.

11