The Sweet Lake Land and Oil Company v. Oleum Operating Company, L.C.
The Sweet Lake Land and Oil Company v. Oleum Operating Company, L.C., No. CW-0017-0464 (La. Ct. App. 3d Cir. Oct. 18, 2017).
Authorities cited
Identified automatically; this list may not be exhaustive.
- Brown v. Sanders 960 So. 2d 931
- Herlitz Const. Co., Inc. v. Hotel Investors of New Iberia, Inc. 396 So. 2d 878
- Holly & Smith v. St. Helena Cong. Facility 943 So. 2d 1037
- In Re Succession of Boyter 756 So. 2d 1122
- Hutchinson v. Patel 637 So. 2d 415
- MJ Farms, Ltd. v. Exxon Mobil Corp. 998 So. 2d 16
- State v. Louisiana Land & Exploration Co. 110 So. 3d 1038
Opinion text
STATE OF LOUISIANA
COURT OF APPEAL, THIRD CIRCUIT
17-464
THE SWEET LAKE LAND AND OIL COMPANY, ET AL.
VERSUS
OLEUM OPERATING COMPANY, L.C., ET AL.
**********
ON SUPERVISORY WRITS FROM THE
FOURTEENTH JUDICIAL DISTRICT COURT
PARISH OF CALCASIEU, NO. 2010-1272
HONORABLE DAVID ALEXANDER RITCHIE, DISTRICT JUDGE
**********
ELIZABETH A. PICKETT
JUDGE
**********
Court composed of John D. Saunders, Elizabeth A. Pickett, and Shannon J.
Gremillion, Judges.
STAY LIFTED. WRIT DENIED.
Guy E. Wall
Paul E. Bullington
Jonathon R. Cook
Sara Lewis
Wall, Bullington & Cook, LLC
540 Elmwood Park Blvd
Harahan, LA 70123
(504) 736-0347
COUNSEL FOR PLAINTIFF-RESPONDENT:
Sweet Lake Land & Oil Co., LLC
James P. Doré
Alan J. Berteau
Shannan Sweeney Rieger
Deborah J. Juneau
R. Benn Vincent, Jr.
Matthew B. Smith
Hattie V. Guidry
Kean Miller LLP
P. O. Box 3513
Baton Rouge, LA 70821
(225) 387-0999
COUNSEL FOR DEFENDANTS-APPLICANTS:
Sohio Petroleum Company
BP Exploration & Oil, Inc.
BP Exploration, Inc.
BP Products North America, Inc.
PICKETT, Judge.
Defendants-Relators, BP Products North America, Inc.; BP Exploration &
Oil, Inc.; BP Exploration, Inc.; and Sohio Petroleum Company (“BP”), seek a
supervisory writ from the judgment of the trial court which denied their Motion for
Adoption of LDNR’s Most Feasible Plan Pursuant to La.R.S. 30:29 and ordered
LDNR to submit a final plan by July 8, 2017.
STATEMENT OF THE CASE
This case involves an oilfield contamination lawsuit that is governed by the
2012 version of La.R.S. 30:29, which was originally enacted by 2006 La. Acts 312
(Act). The plaintiff, the Sweet Lake Land & Oil Company, LLC, (Sweet Lake)
filed suit against BP, among other defendants, alleging environmental damage to
its property caused by decades of oil and gas exploration activities. After trial,
conducted from May 11 through May 27, 2015, the jury found BP 100% liable for
the environmental damage. On September 11, 2015, the trial court referred the
case to the Louisiana Department of Natural Resources, Office of Conservation,
(LDNR) for a public hearing and the development of the most feasible plan under
La.R.S. 30:29. The judgment also ordered BP to submit to LDNR a plan to
“remediate to applicable regulatory standards the contamination that resulted in the
environmental damage to the Property.” LDNR held a public hearing from April
25 through April 28, 2016.
Based upon the evidence presented and in response to questions raised by
the LDNR panel, the LDNR issued and filed in the trial court record its “Most
Feasible Plan and Written Reasons in Support as Required by La.R.S. 30:29”
(LDNR plan) on October 3, 2016. Thereafter, on October 16, 2016, BP filed its
motion for adoption of LDNR’s plan pursuant to La.R.S. 30:29. Sweet Lake
opposed the adoption, arguing the motion was premature because the plan was not
a “final plan” to clean up the property and was not even a “final plan” to evaluate
the property. In reply, BP argued that the LDNR plan was a final plan, as La.R.S.
30:29 specifically contemplates that the final most feasible plan can require
evaluation only, and the LDNR plan does much more.
At the February 15, 2017 hearing, the trial court denied BP’s motion,
ordering LDNR to perform additional work because the plan was only partially a
remediation plan. The trial court’s greatest concerns were those “parts” or areas of
contamination, namely the groundwater and flowlines, where LDNR admittedly
did not have enough information to formulate a remediation plan. In its written
judgment, signed on May 9, 2017, the trial court specifically required the final plan
to address those questionable areas and provide a remedial plan of action for same:
a. Address groundwater remediation on the property. . . . The
final remediation plan may contain clean up options that
depend upon the results of additional information and should
be accompanied by an estimate of the cost to obtain the
additional information. If LDNR is unable to provide the
foregoing final remediation plan, it shall provide the Court
with information to help the Court better order LDNR to do
what needs to be done;
b. Specify the regulation or standard for each clean up activity so
that the Court can enforce it;
c. Specify the flowlines on the property and include a remediation
plan for flowlines that must be removed; and
d. State whether a response or command was received from any
other agency to whom the October 3, 2016 LDNR plan was
submitted pursuant to La. R.S. 30:29[C](3)(b)(i) and (ii).
The Department shall submit this final remediation plan within 60
days of this order but the Department may move the Court for an
extension of this deadline.
BP filed this writ application seeking “prompt” review of the trial court’s
rejection of LDNR’s most feasible plan. We granted the writ for full briefing and
to issue an opinion and stayed the trial court’s order directed at the LDNR. Sweet
2
Lake Land & Oil Co., LLC v. Oleum Operating Co., L.C., an unpublished writ
disposition bearing docket number 17-464 (La.App. 3 Cir. 6/13/17).
SUPERVISORY RELIEF
“The proper procedural vehicle to contest an interlocutory judgment that
does not cause irreparable harm is an application for supervisory writs. See La.
C.C.P. arts. 2087 and 2201.” Brown v. Sanders, 06-1171, p. 2 (La.App. 1 Cir.
3/23/07), 960 So.2d 931, 933. But see La.Code Civ.P. art. 2083, comment (b),
“Irreparable injury continues to be an important (but not exclusive) ingredient in an
application for supervisory writs.” (Citation omitted.) A court of appeal has
plenary power to exercise supervisory jurisdiction over trial courts and may do so
at any time, according to the discretion of the court. When the trial court’s ruling
is arguably incorrect, a reversal will terminate the litigation, and there is no dispute
of fact to be resolved, judicial efficiency and fundamental fairness to the litigants
dictate that the merits of the application for supervisory writs should be decided in
an attempt to avoid the waste of time and expense of a possibly useless future trial
on the merits. Herlitz Const. Co., Inc. v. Hotel Inv’rs of New Iberia, Inc., 396
So.2d 878 (La.1981) (per curiam).
DISCUSSION
The proper interpretation and application of statutory provisions are subject
to de novo review. Holly & Smith Architects, Inc. v. St. Helena Congregate
Facility, Inc., 06-582 (La. 11/29/06), 943 So.2d 1037. The fundamental question
in all cases of statutory interpretation is legislative intent and the ascertainment of
the reason or reasons that prompted the Legislature to enact the law. In re
Succession of Boyter, 99-0761 (La. 1/7/00), 756 So.2d 1122. “When a law is clear
and unambiguous and its application does not lead to absurd consequences, the law
shall be applied as written and no further interpretation may be made in search of
3
the intent of the legislature.” La.Civ.Code art. 9. Though the language of the law
may be susceptible to different meanings, it must be interpreted as having the
meaning that best conforms to the purpose of the law, and the words of law must
be given their generally prevailing meaning. La.Civ.Code arts. 10 and 11. The
meaning of ambiguous terms must be sought by examining the context in which
they occur and the text of the law as a whole, and laws on the same subject matter
must be interpreted in reference to each other. La.R.S. 1:3; La.Civ.Code. arts. 12
and 13. “Courts should give effect to all parts of a statute and should not give a
statute an interpretation that makes any part superfluous or meaningless, if that
result can be avoided.” Boyter, 756 So.2d at 1129. “If application of the foregoing
rules of interpretation fails to illuminate definitively the legislature’s intent, only
then should the rule of strict construction apply to the interpretation of laws in
derogation of common rights . . . .” Hutchinson v. Patel, 93-2156 (La 5/23/94),
637 So.2d 415, 421.
Through its enactment of La.R.S. 30:29, the legislature established a
sequenced protocol for the management of cases alleging environmental
contamination and the remediation of contaminated properties. Once the factfinder
determines that environmental contamination has occurred and that defendant
caused or is legally responsible for such damage, La.R.S. 30:29(C)(emphasis
added) sets forth the remediation protocol:
C.(1) If at any time during the proceeding a party admits
liability for environmental damage or the finder of fact determines
that environmental damage exists and determines the party or
parties who caused the damage or who are otherwise legally
responsible therefor, the court shall order the party or parties who
admit responsibility or whom the court finds legally responsible for
the damage to develop a plan or submittal for the evaluation or
remediation to applicable regulatory standards of the contamination
that resulted in the environmental damage. The court shall order that
the plan be developed and submitted to the department and the court
within a time that the court determines is reasonable and shall allow
4
the plaintiff or any other party at least thirty days from the date each
plan or submittal was made to the department and the court to review
the plan or submittal and provide to the department and the court a
plan, comment, or input in response thereto. The department shall
consider any plan, comment, or response provided timely by any
party. The department shall submit to the court a schedule of
estimated costs for review of the plans or submittals of the parties by
the department and the court shall require the party admitting
responsibility or the party found legally responsible by the court to
deposit in the registry of the court sufficient funds to pay the cost of
the department’s review of the plans or submittals. Any plan or
submittal shall include an estimation of cost to implement the plan
(2)(a) Within sixty days from the last day on which any party
may provide the department with a plan, comment, or response to a
plan as provided in Paragraph (C)(1) of this Section, the department
shall conduct a public hearing on the plan or plans submitted. When
a public hearing is held following a limited admission pursuant to the
Code of Civil Procedure Article 1563, then the department shall not
conduct an additional public hearing pursuant to this Section for the
same environmental damage. Within sixty days of the conclusion of
the hearing, the department shall approve or structure a final plan,
or if applicable, a preliminary plan pursuant to Subparagraph
(C)(3)(b) of this Section, based on the evidence submitted which the
department determines to be the most feasible plan to evaluate or
remediate the environmental damage and protect the health, safety,
and welfare of the people. The department shall issue written reasons
for the plan it approves or structures. On motion of the department, for
good cause shown, the court may grant the department additional
time, not to exceed sixty days, within which to either conduct the
hearing or approve a plan with reasons.
(b) Except as otherwise provided for in this Section, from the
date the party or parties, who admit responsibility or whom the court
finds legally responsible for the damage, submit a plan to the
department until after the department has filed with the court the
approved feasible plan for the evaluation or remediation of the
environmental damage, no party to the litigation, either directly or
indirectly, shall have ex parte communication with any employee,
contractor, or representative of the department regarding the
formation of the feasible plan or an agency providing comments to the
department regarding the formation of the feasible plan. The feasible
plan issued by the department shall contain a signed affidavit of
compliance with this restriction. Any comments provided by an
agency to the department shall also contain a signed affidavit of
compliance with this restriction.
(3)(a) The department shall use and apply the applicable
regulatory standards in approving or structuring a plan that the
department determines to be the most feasible plan to evaluate or
remediate the environmental damage.
(b)(i) If the department preliminarily approves or structures a
preliminary plan that requires the application of regulatory
standards of an agency other than the department or that provides
5
an exception from the department’s standards, within fifteen days of
such preliminary structuring or approval, the department shall
submit the plan to the Department of Agriculture and Forestry, the
Department of Environmental Quality, and the Department of
Natural Resources for review and comment. Within thirty days after
the department’s submission of the plan to all of the agencies, each
agency may provide written comments regarding the plan. Each
agency providing written comments shall submit a schedule of the
agency’s costs for review of the plan to the court for reimbursement
by the responsible party. Failure of an agency to respond to the
department shall not affect the validity of the plan approved by the
department. The department and agency heads shall coordinate in
order to establish protocol to ensure inter-agency communication
regarding plan development, timely delivery of all proposed plans to
the appropriate agency heads, and timely receipt of all agency
comments back to the department.
(ii) Within thirty days after the receipt of any agency’s written
comments, the department shall file in the court record the final
plan, with written reasons that the department determines to be the
most feasible plan to evaluate or remediate the environmental
damage under applicable regulatory standards, together with any
comments submitted by an agency under Item (i) of this
Subparagraph. Based on the findings of the department, the
department may issue any compliance order it deems necessary to
either the operator of record or, where applicable, a party found
responsible or admitting responsibility for implementing the most
feasible plan to evaluate or remediate the environmental damage
under applicable regulatory standards. If a compliance order is issued
against the responsible party who is not the current operator of record,
the responsible party shall give the current operator of record notice of
the compliance order within thirty days of the responsible party’s
receipt of the compliance order.
(4) The plan approved by the department for submission to the
court shall not be considered to be an adjudication subject to appellate
review pursuant to R.S. 49:964 or R.S. 30:12.
(5) The court shall adopt the plan approved by the
department, unless a party proves by a preponderance of the
evidence that another plan is a more feasible plan to adequately
protect the environment and the public health, safety, and welfare.
The court shall enter a judgment adopting a plan with written reasons
assigned. Upon adoption of a plan, the court shall order the party or
parties admitting responsibility or the party or parties found legally
responsible by the court to fund the implementation of the plan.
(6)(a) Any judgment adopting a plan of evaluation or
remediation pursuant to this Section and ordering the party or parties
admitting responsibility or the party or parties found legally
responsible by the court to deposit funds for the implementation
thereof into the registry of the court pursuant to this Section shall be
considered a final judgment pursuant to the Code of Civil Procedure
Article 2081 et seq., for purposes of appeal.
6
(b) Any appeal under this Section shall be a de novo review and
shall be heard with preference and on an expedited basis.
(c) The appellate court may affirm the trial court’s adoption of a
plan or may adopt a feasible plan in conformity with this Section and
shall issue written reasons for its decision.
As contemplated by these provisions, a trial court, upon a finding of
liability/responsibility, (1) refers the matter to LDNR to develop a remediation
plan, (2) orders the responsible party to develop a plan for the “evaluation or
remediation to applicable standards” of the contamination and submit same to
LDNR and the court, and (3) allows the plaintiff and other parties to review the
plan submitted by the responsible party and to provide to LDNR and the court a
plan, comment, or input in response thereto. La.R.S. 30:29(C)(1). LDNR then
conducts a public hearing on the submitted plans and either approves one of the
submitted plans or comes up with its own plan. La.R.S. 30:29(C)(2) & (3). If
LDNR’s plan requires the application of another agency’s regulatory standards or
an exception from LDNR’s standards, LDNR must submit its preliminary plan to
the other agencies for review and comment, but failure of an agency to respond
does not affect the validity of the plan. La.R.S. 30:29(C)(3)(b)(i). Thereafter,
LDNR files its final plan with written reasons in the trial court record. La.R.S.
30:29(C)(3)(b)(ii). The statute then mandates: “The court shall adopt the plan
approved by the department, unless a party proves by a preponderance of the
evidence that another plan is a more feasible plan to adequately protect the
environment and the public health, safety, and welfare.” La.R.S. 30:29(C)(5).
BP challenges the trial court’s refusal to adopt the LDNR plan herein as an
error of law in contravention of the mandatory requirements of La.R.S.
30:29(C)(5) cited above. First, BP claims the LDNR plan is, in fact, a final plan
pursuant to the statutory provisions, which include, by their express terms, plans
for “evaluation or remediation.” Under the Act, the plan filed with the trial
7
court—whether an “evaluation” plan, a “remediation” plan, or both—should be
considered the final plan. Therefore, BP argues the trial court had no authority to
unilaterally determine the finality of the plan or to decide the LDNR plan was not
“final” because it was not a “remediation-only” plan.
Second, BP asserts the LDNR plan satisfies the requirements of La.R.S.
30:29 as it was developed by a panel of LDNR personnel embodying a variety of
environmental disciplines that heard the testimony of both parties’ witnesses and
received into evidence documents selected by each party supporting and opposing
the plans submitted. Moreover, it contains the detailed findings on the nature and
extent of any “environmental damage” and the steps required of BP to address that
damage.
Third, BP argues the trial court impermissibly narrowed the definition of a
final most feasible plan to mean a remediation-only plan. In support of its
position, BP cites State v. La. Land & Expl. Co., Inc., 82,162 (15th JDC), in which
Judge Jerome Winsburg (Ad Hoc) adopted an LDNR plan, which included a
significant evaluation component (including evaluation of groundwater and soil).
BP further notes this court denied writs, citing the availability of an appeal remedy.
State v. La. Land & Expl. Co., Inc., 16-914 (La.App. 3 Cir. 11/30/16)
(unpublished).
According to BP, it is undisputed that Sweet Lake did not introduce any
evidence to demonstrate that another plan “is a more feasible plan to adequately
protect the environment and the public health, safety and welfare.” La.R.S.
30:29(C)(5). BP argues the trial court has essentially usurped the primary role
assigned to LDNR by statute and has no authority to unilaterally determine the
finality of a plan in the absence of a showing, by a preponderance of the evidence,
of a more feasible plan.
8
In opposition, Sweet Lake asserts that La.R.S. 30:29 is silent on (1) whether
the trial court must accept a final plan, which calls for further evaluation, when it
ordered a plan of remediation, as well as (2) the participation of the court and the
landowner after a final plan is adopted by the court. The trial court expressed
concern that adopting a plan that merely requires the responsible party to submit a
plan to LDNR to evaluate the property could lead to a remediation plan not
approved by the trial court or with input from the landowner. Sweet Lake notes
that no appellate court has addressed these issues despite BP’s claims that
numerous trial courts have adopted similar plans.
Sweet Lake also submits that an LDNR plan, which orders a responsible
party to prepare a plan of investigation and evaluation of groundwater and soil
contamination in response to a trial court order requiring a remediation plan, is not
a final plan. It further argues the term “evaluation” in La.R.S. 30:29 is used to
cover situations where a party settles and assumes responsibility or formally admits
responsibility before trial because otherwise damages are evaluated at trial.
Moreover, according to Sweet Lake, it does not make sense to issue a final
judgment where LDNR did not even estimate the cost of further evaluation as
La.R.S. 30:29 contemplates the final judgment will order the responsible party to
deposit into the trial court’s registry the funds needed to remediate the property.
Additionally, Sweet Lake asserts the trial court has primary jurisdiction over this
matter, and LDNR’s stamping of a plan as final is not determinative. Until LDNR
submits a remediation plan, the trial court is not required to adopt the LDNR plan
as the most feasible plan under La.R.S. 30:29.
Alternatively, Sweet Lake requests that, in the event this court reverses the
trial court’s interpretation of La.R.S. 30:29, this Court remand the matter to the
trial court for hearing on the final plan in light of this court’s decision. It also
9
claims that it presented to the trial court an alternative to LDNR’s plan; so if this
court grants BP’s writ and determines remand is inappropriate, Sweet Lake
requests that its feasible plan be adopted. Finally, Sweet Lake posits that State v.
La. Land & Expl. Co., Inc., has no relevance to the instant matter as this court
merely denied writs, and the issue therein was whether plaintiff, and not the
responsible party, should perform remediation and evaluation.
This matter raises several res nova issues regarding the authority and roles
of the trial court and LDNR after LDNR files its most feasible plan in the trial
court record. The primary issue is whether the trial court can order LDNR to re-
submit a plan for remediation when the judgment called for such a plan and the
originally submitted plan still requires evaluation. Admittedly, the statute does not
provide for a resubmission to LDNR but, rather, explicitly mandates the adoption
of the plan submitted by LDNR, unless it has been shown by a preponderance of
the evidence that a more feasible plan exists. Herein, although Sweet Lake
apparently submitted a plan, there was no evidence, much less a preponderance of
evidence, as to whether its plan was more feasible than LNDR’s plan. During the
hearing, the experts mainly testified regarding the flaws and proper interpretation
of the LDNR plan.
By the explicit terms of La.R.S. 30:29(C)(2), (3), & (5), the role of LDNR is
to develop the most feasible plan and file the plan in the court record, while the
role of the trial court is to adopt the plan unless evidence supports otherwise.
Nevertheless, both the “court and the department shall retain oversight to ensure
compliance with the plan.” La.R.S. 30:29(F). The problem herein is that the
judgment called for a remediation plan, and no one disputes the LDNR plan is not
strictly remedial because, even with the expert reports, LDNR did not have
sufficient information to formulate a plan for remedial action in certain areas,
10
namely groundwater contamination and flowlines. Furthermore, while La.R.S.
30:29(C)(5)(b) does provide for a preliminary plan, the language of La.R.S
30:29(C)(b)(ii) seems to indicate such a plan becomes final when filed in the court
record and does not provide for preliminary review and comment by the trial court
upon submission. Interestingly, the final sentence of the LDNR plan filed herein
states: “This will be and/or is being forwarded. It is being sent to the other
appropriate agencies set forth in La. R.S. 30:29 (C)(3)(b)(i) for comments prior to
being finalized and filed with the Court in accordance with La. R.S. 30:29(C)(3) &
(4).” The trial court noted the reference as well, pondering whether it was merely
an oversight or whether it indicated the plan was merely preliminary. Arguably,
the filing of the plan in the trial court record best indicates its finality as the statute
does not provide for preliminary filings.
Moreover, the supreme court in M.J. Farms, Ltd. v. Exxon Mobil Corp., 07-
2371, pp. 37-38 (La. 7/1/08), 998 So.2d 16, 32, stated in dicta: “Finally, it is the
district court who considers the various restoration plans, including any that the
surface owner may choose to submit, determines which one is most feasible, and
oversees the implementation of the restoration plan. La.Rev.Stat. § 30:29(C)(5).”
In State v. Louisiana Land and Exploration Co., 12-884, p. 16 (La. 1/30/13), 110
So.3d 1038, 1049, the supreme court explained that “although the La. DNR has
input into the plan to remediate the property, the final decision as to the
remediation plan adopted rests with the court. Throughout the remediation
process, the court remains the gatekeeper to ensure the purpose of the Act is
accomplished--remediation of the property to the extent of the public’s interest.”
Inherent in the trial court’s authority as gatekeeper in this statutory scheme
is the option of rejecting an LDNR plan it determines is incomplete and ordering
LDNR to fully comply with its original order pursuant to the statute. We find the
11
trial court did not err here, where LDNR failed to submit a plan for groundwater or
flowline remediation, and, instead, its plan consisted of further testing by BP the
plan would be revised accordingly. The trial court determined that the submission
by LDNR did not constitute a final plan, and, therefore, the submission was
incomplete. The trial court ordered LDNR to supplement the plan submitted to the
court to include options for groundwater remediation. Based on our interpretation
of the statute and the authority granted to the trial court under the statute, we find
no error in the trial court’s failure to approve the final plan or in its order to
supplement the plan.
CONCLUSION
After reviewing the judgment of the trial court and the submissions of the
parties, we find no error in the trial court’s ruling. The application for supervisory
writs filed by BP is hereby denied. The stay issued by this court on June 13 is
hereby lifted, and the case is remanded to the trial court for further proceedings
consistent with this opinion.
STAY LIFTED. WRIT DENIED.