No. 11284
Precedential
Processed
Lake Providence Equipment Co. v. Tallulah Production Credit Ass'n
Also decided on this docket: La. Ct. App. 4th Cir., October 9, 1980 389 So. 2d 908; La. Ct. App. 1st Cir., May 9, 1977 346 So. 2d 816
Lake Providence Equipment Co. v. Tallulah Production Credit Ass'n, 228 So. 2d 315 (La. Ct. App. 1st Cir. 1969).
Cited by
- Austin v. Perry 325 So. 2d 722 La. Ct. App. 4th Cir. 1976
- Lake Providence Equipment Co. v. Tallulah Production Credit Ass'n 241 So. 2d 506 La. 1970
- Lake Providence Equipment Co. v. Tallulah Production Credit Ass'n 229 So. 2d 737 La. 1970
Opinion text
PER CURIAM. It has been brought to our attention that in our opinion we stated “the substitute note was executed by Bramlett, signed and endorsed by him for the exact amount of the original note, and this substitute note was dated August 31, 1964”. It was our intention to signify the note was executed and paraphed on August 31, 1964. Application for rehearing is denied.