Opinions in Louisiana that cite Grapico Bottling Works v. Liquid Carbonic Co., 113 So. 454.
- Pastorek v. Lanier Systems Company 249 So. 2d 224 La. Ct. App. 4th Cir. 1971
- Lee Const. Co. v. L. M. Ray Const. Corp. 52 So. 2d 841 La. 1951
- Matthews v. Gaubler 49 So. 2d 774 La. Ct. App. 1st Cir. 1951
-
Webb v. Martin
47 So. 2d 128
La. Ct. App. 1st Cir. 1950
Grapico Bot *130 , 113 So.
- Liberty Farms, Inc. v. Miller 45 So. 2d 610 La. 1950
- Bankston v. Loranger Milk Plant, Inc. 17 So. 2d 332 La. 1944
- Thomas v. Philip Werlein, Limited 158 So. 635 La. 1935
-
Bacher v. Higgins
156 So. 826
La. Ct. App. 2d Cir. 1934
As we view the pleadings, this is a suit on an open account, and the alleged overpayment, having grown out of the open account, was incidental to the main demand; therefore, the reeonventional demand can be considered under defendant’s answer to the appeal.” , 113 So.
-
General Talking Pictures Corp. v. Pine Tree Amusement Co.
156 So. 812
La. 1934
In the following cases contracts of a rather similar nature were construed as sales and the titles to the property described in the contract- was held to vest in the purchaser who was termed a lessee in the contract: , 113 So.
- Claude Neon Federal Co. of Shreveport v. Angell 153 So. 581 La. Ct. App. 1st Cir. 1934
- Harry B. Loeb Piano Co. v. Kessler 140 So. 398 La. Ct. App. 1st Cir. 1932
- Dickens v. Singer Sewing Mach. Co. 140 So. 296 La. Ct. App. 1st Cir. 1932
-
John J. Meier & Co. v. Schmidt & Ziegler, Ltd.
125 So. 191
La. Ct. App. 1st Cir. 1929
1058 -1063, , the court said: “On the other hand, while there was considerable delay in making delivery, according to the contract as modified, yet, when delivery was not made in April, to which time it had been advanced, plaintiff did not seek to cancel the contract, but, to the contrary, still desired it to be performed, a
- Byrd v. Cooper 117 So. 441 La. 1928
- Graham Glass Co. v. Nu Grape Bottling Co. 115 So. 285 La. 1927