Michigan Wisconsin Pipe Line Co. v. Scanlan
Also decided on this docket: La. Ct. App. 1st Cir., December 1, 1969 228 So. 2d 692; La. Ct. App. 5th Cir., May 5, 1969 222 So. 2d 548; La. Ct. App. 1st Cir., October 16, 1967 203 So. 2d 906
Michigan Wisconsin Pipe Line Co. v. Scanlan, 229 So. 2d 190 (La. Ct. App. 1st Cir. 1969).
Cited by
- Gulf Coast Bank & Trust Co. v. Warren 125 So. 3d 1211 La. Ct. App. 1st Cir. 2013
- Standard Mortgage Corp. v. Wells 865 So. 2d 93 La. Ct. App. 1st Cir. 2002
- Fabacher v. Hammond Dairy Co., Inc. 389 So. 2d 87 La. Ct. App. 4th Cir. 1980
- Louisiana National Bank of Baton Rouge v. Heroman 280 So. 2d 362 La. Ct. App. 1st Cir. 1973
- Margolis v. Allen Mortgage & Loan Corp. 268 So. 2d 714 La. Ct. App. 4th Cir. 1972
- Michigan Wisconsin Pipe Line Company v. Miller 229 So. 2d 182 La. Ct. App. 3d Cir. 1970
Authorities cited
Identified automatically; this list may not be exhaustive.
- Michigan Wisconsin Pipe Line Company v. Miller 229 So. 2d 182
Opinion text
SAVOY, Judge. This expropriation suit was consolidated for trial and appeal with the companion case of Michigan Wisconsin Pipe Line Company v. Miller, 229 So.2d 182 (La.App. 3 Cir. 1969), decided also on this date. For the reasons assigned in the companion case, the judgment of the district court is amended so as to increase the award to defendants, Michael W. Scanlan, Jr., Lela Andrus Scanlan, and Carl Dean Scanlan, from $1,604.50 to $4,178.50, together with legal interest on all unpaid amounts from the date of the taking, until paid. In all other respects, the judgment of the district court is affirmed at plaintiff-appel-lee’s costs. Amended and affirmed. HOOD, J., dissents for reasons assigned in 229 So.2d 182 (La.App. 3 Cir. 1969).