Kelly McHugh and Associates, Inc. v. RPDE Development, LLC, David W. Johnson, Phillip G. Mayeaux and Edward J. Van Hoven

Louisiana Court of Appeal, First Circuit · Filed March 5, 2020

Authorities cited

Identified automatically; this list may not be exhaustive.

Opinion text

STATE OF LOUISIANA

COURT OF APPEAL

FIRST CIRCUIT

er 2019 CA 0709

V KELLY MCHUGH AND ASSOCIATES,, INC.

VERSUS
A I

RPDE DEVELOPMENT, LLC DAVID W. JOHNSON PHILLIP G.
MAYEAUX AND EDWARD J. VAN HOVEN

DATE OF JUDGMENT: MAR 0 5 2020

ON APPEAL FROM THE TWENTY- SECOND JUDICIAL DISTRICT COURT
NUMBER 2012- 12905, DIVISION 1, PARISH OF ST. TAMMANY
STATE OF LOUISIANA

HONORABLE REGINALD T. BADEAUX, III, JUDGE

Richard A. Richardson Counsel for Defendant -Appellee
Covington, Louisiana RPDE Development, LLC

David M. Cohn Counsel for Defendant -Appellant
D. Brian Cohn
Daton Contracting, Inc.
Bartley Paul Bourgeois
Allyson S. Jarreau
Baton Rouge, Louisiana

BEFORE: McDONALD, THERIOT, AND CHUTZ, JJ.

Disposition: APPEAL MAINTAINED; MARCH 8, 2018 JUDGMENT AFFIRMED; JANUARY 31,
2019 JUDGMENT VACATED; REMANDED WITH INSTUCTIONS.

CHUTZ, J.

Third -party defendant -appellant, Daton Contracting, Inc. ( baton), appeals

the trial court' s judgment awarding damages and costs in favor of third -party
plaintiff a
- ppellee, RPDE Development, LLC ( RPDE), for substandard work in the

construction of a subdivision roadway. We affirm in part, vacate in part, and

remand with instructions.

FACTUAL AND PROCEDURAL BACKGROUND

Kelly McHugh and Associates, Inc. ( McHugh) is an engineering firm that

contracted with RPDE to provide engineering and survey services in connection

with the development of land located in Mandeville, Louisiana into a subdivision.

McHugh commenced this litigation by filing a claim against RPDE for its alleged

failure to pay fees and costs due under the terms of a contract. RPDE responded

with a reconventional demand against McHugh and this third -party demand against

Daton. RPDE alleged that pursuant to a written agreement, Daton was required to

remove and replace soil cement that had failed in conjunction with the construction

of a roadway but had instead submitted an invoice to RPDE for the work. Initially,

RPDE refused to pay but because an impending sale of the developed property
from RPDE to a residential developer was unable to close without payment of the

invoice to Daton, RPDE paid the outstanding amount at the closing. In its third -
party demand, RPDE demanded damages from Daton. Daton answered the third -

party demand, generally denying RPDE' s allegations.

RPDE and McHugh voluntarily settled their claims against one another, and

the matter proceeded to trial on the third -party demand. After the introduction of

testimony and documentary evidence, the trial court found in favor of RPDE and,

in three separate judgments, awarded damages and costs against Daton. Daton

appealed.

2

VIABILITY OF THE APPEAL

The first judgment that the trial court entered was on March 8, 2018, stating
the following:

IT IS HEREBY OR[DEREDI, ADJUDGED] AND
DECREED that ... [ Daton] is to pay ... [ RPDE] an amount of

91, 228. 00 in damages and ... all costs of these proceedings,
including any expert witness fees and depositions used at trial.

Thereafter, the trial court, apparently on its own motion, issued an " AMENDED

JUDGMENT" on March 29, 2018, which provided:

IT IS HEREBY OR[ DERED], ADJUDGED] AND
DECREED that ... [ Daton] is to pay ... [ RPDE] an amount of

91, 228. 00 in damages and ... [ RPDE' s] costs of court in the amount
of $2, 167. 45.

On April 5, 2018, RPDE filed a motion for new trial, contending that the March
29, 2018 amended judgment failed to provide the amount for " expert fees and

deposition costs." A hearing on the motion for new trial was held on December 4,

2018, and on January 31, 2019, the trial court signed the third judgment, which

provided in pertinent part:

IT IS HEREBY OR[ DERED], ADJUD[ GED] AND
DECREED that ... [ Daton] is to pay ... [ RPDE] ... the amount of
15, 053. 75] in Expert Witness Fees as well as an additional $ 234. 50
in Deposition Costs for a total amount of [$15, 288. 25].

Daton filed a motion and order for a devolutive appeal on April 13, 2018,

expressly naming the March 8, 2018 judgment as well as the March 29, 2018

AMENDED" judgment as the subjects of the appeal. The trial court withheld

acting on Daton' s motion and order for the devolutive appeal until after the

December 4, 2018 hearing on RPDE' s motion for new trial and its January 31,
2019 judgment. On February 15, 2019, Daton filed its second motion and order for

a devolutive appeal, specifically mentioning that the motion and order for a

devolutive appeal that it had filed April 13, 2018 was still pending. On February

3

26, 2019, the trial court signed an order that expressly granted Daton an appeal
from all three judgments. I

After the record was lodged, this court issued a show cause order, noting the
January 31, 2019 judgment failed to reflect that the terms of either the March 8,

2018 or the March 29, 2018 judgments had been incorporated into it, and

questioning the propriety of the March 29, 2018 amended judgment. A ruling on

the show cause order was subsequently referred to this panel. See McHugh and

Assocs., Ine. v. RPDE Dev , LLC, 2019- 0709 ( La. 1st Cir. 913119)
App.

unpublished action).

On its face, the March 8, 2018 judgment appears to have been a final

judgment of its own accord. It resolved all the issues on the merits between the

parties, and Daton timely sought an appeal of that judgment on April 13, 2018. It is

unclear why the trial court, rather than issuing a new judgment addressing solely
the amount of costs as it is authorized to do under La. C. C. P. art. 2088, 2

unilaterally decided to " amend" the judgment on the merits to include a specific

amount for court costs. However, Daton timely sought appeals from all of the trial
court' s judgments.

It is well settled that appeals are favored in the law and should be maintained

unless a legal ground for dismissal is clearly shown. Edgefteld a Audubon

1 Although the signed order of appeal references " the judgment ... amended on April 3, [ 2018],"
reading the motion and order as a whole, it is clear Daton intended to appeal the " AMENDED
JUDGMENT" signed on March 29, 2018. Moreover, the amount of court costs set forth in the
March 29, 2018 judgment was not challenged by Daton in its appeal.
2 La. C. C. P. art. 2088 provides in relevant part:

A. The jurisdiction of the trial court over all matters in the case reviewable
under the appeal is divested, and that of the appellate court attaches, on the
granting of the order of appeal and the timely filing of the appeal bond, in the case
of a suspensive appeal or on the granting of the order of appeal, in the case of a
devolutive appeal. Thereafter, the trial court has jurisdiction in the case only over
those matters not reviewable under the appeal, including the right to...
10) [ s] et and tax costs and expert witness fees.

91

Nature Institute, Inc., 2018- 1782 ( La. 1118119), 261 So. 3d 776 ( per curiam). Here,

any issues related to the addition of costs to the March 8, 2018 merits judgment

were created by the trial court amending the initial judgment on its own motion.

Daton, as appellant, timely sought appellate review by filing the requisite motions

following each of the trial court' s rulings. As such, any defects that may exist are
not attributable to the appellant. See La. C. C. P. art. 2161 (" An appeal shall not be

dismissed because of any other irregularity, error or defect unless it is imputable to

the appellant."). Accordingly, the appeal is maintained.

MERITS OF APPEAL

Liabili

Daton maintains that the trial court erred in applying La. C. C. art. 2762 to

support its conclusion that substandard workmanship caused RPDE' s damages. La.
C. C. art, 2762 provides in pertinent part:

If a building, which an architect or other workman has
undertaken to make by the job, should fall to ruin either in whole or in
part, on account of the badness of the workmanship, the architect or
undertaker shall bear the loss.

Although Article 2762 refers only to a " building," the jurisprudence has

extended its application to include the surfacing of streets and parking lots with
asphalt. Hallar Enterprises, Inc. v. Hartman, 583 So. 2d 883, 886 ( La. App. 1st

Cir. 1991).
With respect to defects in the soil or a defect in the existing base of the
road to be overlaid,
Article 2762 imposes liability upon a contractor only for
building upon a site that he knew or should have known was defective. The

contractor is liable only for failing to correct or disclose obvious or apparent soil

defects and not latent or hidden defects. Id. (citing Wurst v. Pruyn, 250 La. 1109,

202 So. 2d 268 ( La. 1967)).

k

If an undertaker fails to do the work he has contracted to do, or if he does

not execute it in the manner he has agreed to do it, he shall be liable in damages for

the losses that may ensue from his non-compliance with his contract. La. C. C. art.

2769. In order to recover damages from a contractor, the owner must establish: ( 1)

the defects exist, ( 2) that faulty workmanship caused the defects, and ( 3) the cost

of repairing the defects. The owner has the burden of proving each element of the

claim by a preponderance of the evidence. Matherne v. Barnum, 2011- 0827 ( La.

App. 1 st Cir. 3119112), 94 So. 3d 782, 789, writ denied, 201.2- 0865 ( La. 611112), 90

So.3d 442. But the contractor is not responsible for a latent or hidden defect in the

soil, that is, a defect which was neither apparent to nor reasonably discoverable by
the builder during construction. Harris v. Williams, 28, 512 ( La. App. 2d Cir.

8123196), 679 So. 2d 990, 994. See Hallar Enterprises, Inc., 583 So.2d at 886.

A trial court' s factual findings will not be reversed unless manifestly
erroneous or clearly wrong. A reviewing court must determine whether the

factfinder' s conclusions were reasonable based upon the entire record. Stobart v.

State, 617 So. 2d 880, 882- 83 ( La. 1993).

In its written reasons for judgment, the trial court stated:

Daton by contract was to construct sewer, water ( excluding all well
points),
curbing, soil cement, asphalt, clearing entire site except for
green space,
grubbing, drainage, pipe,
seeding, retention pond,

clearing and filling of all lots as per instruction of [ the residential
developer' s] representative Lee Foster.

A crucial part of the contract called for Daton to prepare the
road base with a combination of soil and cement ( soil cement) to a
depth of 8 inches. However, just prior to applying the soil cement
there was a significant rain event that rendered the road beds saturated
with water to the point that the application of the soil cement would
not cure properly.

Daton, as a road construction contractor, should have known
that the subsoil conditions at the time of its application of the soil
cement would not be successful. ... Daton acted unilaterally on its

own to proceed. Further, the excessive moisture in the soil is not a
latent defect which would absolve Daton of responsibility.
A reasonable factual basis exists for the trial court' s conclusion.

Phillip Mayeaux of RPDE testified that Daton' s first application of the

cement into the soil ( referred to by the witnesses as a " cutting") for the

construction of the roadways within the Lexington Place subdivision was on March

14, 2011. Around noon that day, Mayeaux visited the site and was surprised that

the cutting was underway given the wet conditions of the subdivision after a two-

day rainfall on March S and 9, 2011, and because he had not been notified by

Daton of the undertaking. According to Mayeaux, conditions in the subdivision

weren' t very good." He was unable to drive his truck too far into the subdivision.

Mayeaux recalled that the ditches were about three-quarters full of water and the

pond was also full. He believed that when Daton undertook the cutting on March
14, 2011, the subdivision was too wet and that the sub -base had been compromised

such that it was unable to hold the roadbed. Mayeaux explained that either the day

of the cutting or within the next couple of days, as the integrity of the soil cement

was tested, the failure was detected.

Mayeaux acknowledged that drainage was a problem in the subdivision

particularly after the rain event and stated that before the March 14, 2011 cutting,

he saw Daton pumping water out of the pond. Mayeaux also admitted that Daton

was not responsible for the drainage issues.

Clayton Fauntleroy of Daton testified. He agreed with Mayeaux that before

the March 14, 2011 cutting, there had been a substantial rainfall. Fauntleroy

explained that the water was so significant it did not remove itself from the site,

and that Daton had to pump it out of the subdivision. According to Fauntleroy,

there were no major issues with the cutting and none of the heavy equipment had

7

become stuck or bogged down. He recalled that in most places, the soil cement did

not initially fail. Fauntleroy described how during the process undertaken to test

the integrity of the soil cement, it began to crack up " like an eggshell" and that

once that cement breaks, it doesn' t go back together."

Fauntleroy conceded that there was too much moisture in the sub -base and

that it compromised the street. He pointed to issues with the drainage from his first

day on the job, indicating there was no off-site drainage and that "[ t] here was

nothing done about that." Fauntleroy acknowledged that it was his responsibility to

check the soil prior to commencement of the cutting. He stated, however, that

before he undertook the March 14, 2011 cutting, neither McHugh nor anyone else

on the project advised him of a need to deviate from the scheduled date of the soil

cement application because of rainfall or drainage issues. He remembered having

contacted McHugh prior to undertaking the cutting as scheduled on March 14,

2011 to notify of Daton' s intentions, suggesting that most likely he left a message
with a secretary. Fauntleroy admitted that the remedial work with the soil cement

was not undertaken pursuant to a change order as had been done with other project

modifications.

Leonard C. Quick was admitted as an expert forensic engineering,

particularly in civil engineering and structural engineering. He opined that the

failure of the soil cement was because of the condition of the sub -base and the role

of Daton in causing the failure. After validating the occurrence of the weather

event that left between seven and eight inches of rain on March 8 and 9, 2011,

interviewing Mayeaux, and reviewing Fauntleroy' s deposition, Quick determined

that the sub -base was no longer compacted as required by McHugh' s plans and

specifications. The roadway design called for four inches of asphalt, an eight -inch

soil cement -treated base, and a six- inch compacted sub -base. Quick explained that

0

once the rain fell, the sub -base was saturated and softened, which wiped out the

compact work. He believed that Daton needed to compact the sub -base again after

allowing it to dry out and prior to applying the cement into the soil.

Based on his review of Mayeaux' s and Fauntleroy' s accounts of conditions

on March 14, 2011, Quick concluded that the ground water and surface runoff had

already begun to lower since the ditches were three- quarters full and the pond was

full. While water was not sitting on or cascading over the entire development, it

was nevertheless Quick' s opinion that the sub -base was saturated and wet such that

it was not suitable for cutting. Quick advised that the sub -base needed time to dry

out before the soil cement cutting. Because it was Daton' s work, Quick stated that

Daton was responsible for the condition of the sub -base, since its contract with

RPDE did not delegate that responsibility to another party.

Quick testified that any pre- existing drainage issues may have been a partial

source of the moisture in the sub -base along with the torrential rainfall turning the

upper layer to mush and slop, but he still found Daton responsible for the untimely

cutting of the soil cement since Daton was in control of the entire cutting process
and had to account for the wetness of the soil. Quick determined that as an

experienced road construction contractor, Daton should have had knowledge of the

effect of moisture on the sub -base irrespective of its source. He explained to the

trial court that a certain amount of common sense to determine when to proceed

was required of Daton.

Based on the foregoing review of the evidence, a reasonable factual basis

exists for the trial court' s conclusion that the failed soil cement application was an

apparent defect that was caused by baton' s faulty workmanship. Although Daton
asserts that it was not responsible for the failed work since it performed in

0

accordance with the plans and specifications furnished by McHugh,' the trial court

rejected that assertion. Based on the testimony of Mayeaux and Fauntleroy as to

the conditions at the time of the March 14, 2011 cutting and Quick' s explanation of

the effect of those conditions on the sub -base, the record supports an implicit

finding that Daton failed to comply with McHugh' s requirement of a six- inch

compacted sub -base. And while it is true that Fauntleroy testified that the heavy

equipment did not bog down or become stuck in the soil during the March 14,

2011 cutting, he clearly acknowledged the wet conditions of the subdivision and

that it was his responsibility to check the soil prior to commencement of the

cutting. Fauntleroy' s testimony, Mayeaux' s description of the site conditions, and

Quick' s articulation of Daton' s responsibilities as the roadway construction

contractor provide ample support for the trial court' s finding that the failure of the

soil cement was caused by Daton' s faulty workmanship. Accordingly, the trial

court was not manifestly erroneous.

Damages

Daton asserts that the amount of damages should be reduced to reflect that a

portion of the remedial work changed the design of the roadbed from a depth of

eight inches of soil cement as initially set forth in the plans and specifications to

twelve inches. The contractor suggests that the trial court' s award allowed RPDE

to recover more than the amount for which it originally bargained.

The measure of damages for a breach of contract is the sum that will place

plaintiff in the same position as if the obligation had been fulfilled. LAD Services

3 See La. K.S. 9: 2771 (" No contractor ... shall be liable for destruction or deterioration of or
defects in any work constructed, or under construction, by him if he constructed, or is
constructing, the work according to plans or specifications furnished to him which he did not
make or cause to be made and if the destruction, deterioration, or defect was due to any fault or
insufficiency of the plans or specifications. This provision shall apply regardless of whether the
destruction, deterioration, or defect occurs or becomes evident prior to or after delivery of the
work to the owner or prior to or after acceptance of the work by the owner. The provisions of this
Section shall not be subject to waiver by the contractor.").

10

of Louisiana, L.L. C. v. Superior Derrick Services, L.L. C., 2013- 0163 ( La. App.

1st Cir. 1117114), 167 So. 3d 746, 761, writ not considered, 2015- 0086 ( La. 412115),

162 So. 3d 392. See also La. C. C. art. 1995 ( providing that the measurement of

damages for a breach of contract includes the loss sustained by the obligee).
The trial court awarded $ 91, 228. 00, which consisted of $9, 000. 00 for the

processing of new roads, $ 34, 000.00 for the processing of the new soil cement, and

48, 228. 00 for new soil cement. This amount was supported by Mayeaux' s

testimony that the corrective re -compaction and the drying out of the initial failed

soil cement cost $
9, 000. 00; as well as the invoice from Daton showing $ 82, 228 for
the other items.4

It is undisputed that after the failed cutting on March 14, 2011, a meeting

was held at which time a plan to remedy the defective soil cement was confected.

Both Mayeaux and Fauntleroy were present along with representatives from
McHugh. According to Fauntleroy, McHugh suggested that Daton remix the

existing soil to a deeper depth. He was then asked the cost of implementation of

the new plan and provided with a new design. Fauntleroy testified that he was not

informed that he would not be paid for the remedial work. After the remedial work

plans and specifications were implemented in a second cutting, Fauntleroy

acknowledged that the roadway construction was successful.

A reasonable factual basis exists to establish that the remedial work which

arose as a result of Daton' s faulty workmanship placed RPDE in the same position

as if Daton had correctly fulfilled its obligation with its first application of cement

to the soil. Mindful that at the meeting Fauntleroy attended with Mayeaux and

McHugh representatives, Daton neither complained about the remedial work

4 Mayeaux did not dispute, and paid to Daton, $ 5, 600.00 for anew drainage ditch that was added
to the subdivision after the March 2011 rainfall event and also reflected in the invoice that
included the remedial work charges.

design plan nor offered a less expensive alternative by which RPDE could have

been placed in the same position as if the soil cement had never failed, there is no

error in the trial court' s award of damages based on the additional expenses Daton

incurred in curing its defective work.

Daton next maintains that the trial court' s award of $ 91, 228. 04 is

insupportable because RPDE failed to express that its payment to Daton for the

remedial work at the closing was made under protest. Thus, the contractor urges

the trial court' s award should be reversed.

The acceptance of a work without objection, protest, or complaint respecting

the manner of performance estops the owner from recovery of damages resulting

from defective work. However, acceptance with the understanding that certain

defects will be remedied does not bar recovery for the cost of remedying such
defects. Brouillette v Consol. Constr. Co. of Florida, Inc., 422 So. 2d 176, 177- 78

La. App. Ist Cir. 1982).

It is undisputed that the failure of the application of cement into the soil was

obvious almost immediately after Daton executed the work. The meeting in which

the plan to remedy the defect with the soil cement occurred soon after the failure

and,
according to Mayeaux, he made it clear that he was protesting. Although

Mayeaux admitted he never made a demand on Daton to absorb the costs of the

redial work, Fauntleroy testified that all parties present at the meeting looked to
Daton to articulate the costs of the remedial work.
Most importantly, it is

undisputed that Mayeaux was aware of the defective soil cement and was an active

instrumentality in instigating a remedy. The application of the cement to the soil

was not a defect that RPDE accepted without objection such that it is estopped

from damages from Daton for its
recovering faulty workmanship in the

12

construction of the roadways in the subdivision. Therefore, the trial court correctly

rejected Daton' s contention that RPDE was estopped from recovering damages.

In its final challenge of the trial court' s award of damages, Daton contends it

is entitled to an offset for the amount received by RPDE in settlement of its claims

against McHugh. Daton maintains that by settling with McHugh prior to the trial of

the third -party demand, "[ c] learly, RPDE has double -dipped for the damages it

already recovered from [ McHugh]."

When each of different obligors owes a separate performance to one obligee,

the obligation is several for the obligors. A several obligation produces the same

effects as a separate obligation owed by each obligor to an obligee. La. C. C. art.

1787. An obligation is solidary for the obligors when each obligor is liable for the

whole performance.
A performance rendered by one of the solidary obligors

relieves the others of liability toward the obligee. La. C. C. art. 1794. Solidarity of

obligation shall not be presumed. A solidary obligation arises from a clear

expression of the parties' intent or from the law. La. C. C. art. 1796. An obligation

is solidary among debtors when they are obliged to the same thing so that each

may be compelled for the whole. Boudreaux v. Jeff, 2003- 1932 ( La. App. 1 st Cir.
9117/ 04), 884 So.2d 665, 672. A transaction or compromise between the obligee

and one obligor benefits the other solidary obligors in the amount of the portion of

that obligor. La. C. C. art. 1803.

In the reconventional demand, RPDE averred that during construction,

problems arose due to McHugh' s faulty work, including that the soil cement failed

in part because the depth recommendations by McHugh were faulty, the drainage
plan design caused the subsoil to have too much moisture, and McHugh failed to

properly monitor the application of the cement to the soil, all of which caused the

need for remedial work. However, RPDE additionally alleged that McHugh' s

13

original drainage design failed to work properly. Thus, on the face of the

pleadings,
McHugh' s alleged liability to RPDE was not fully coextensive with

Daton' s liability as a result of the trial on the third -party demand.

During trial, Daton raised the issue of the amount of the settlement between

McHugh and RPDE. Initially, the trial court did not allow the settlement agreement

into evidence but later did so. After the conclusion of evidence, the trial court took

the matter under advisement. In the trial court' s subsequent written reasons for

judgment, the issue of Daton' s entitlement to a credit for RPDE' s settlement with

McHugh was noted as a contention but its disposition was not expressly addressed.

Silence in a judgment of the trial court as to any issue, claim, or demand

placed before the court is deemed a rejection of the claim and the relief sought is

presumed to be denied. Alost v. Lawler, 2018- 1271 ( La. App. 1 st Cir. 518119), 277

So. 3d 329, 333 n. 3.

Here, as noted in its written reasons for judgment, the trial court cast Daton

for " the full sum of $91, 22$. 00," thus, implicitly finding that any liability between

Daton and McHugh in favor of RPDE was separate, not solidary. We have already
concluded that the trial court' s factual conclusion that the failed soil cement

application was an apparent defect that was caused by Daton' s faulty workmanship

was supported by the evidence and, therefore, not manifestly erroneous.

Additionally, an implicit factual finding that McHugh was not liable for the

failed soil cement by having created plans and specifications that required soil

cement to a depth of eight inches was likewise supported by the evidence. Quick

testified that the eight -inch depth was suitable for the sub -base but for the issue

with the moisture content that he attributed to Daton' s decision to apply the cement

despite the wet conditions in the subdivision. The trial testimony of Kelly McHugh
of the McHugh engineering firm indicated that the original plan with an eight -inch

14

depth would have been satisfactory with a subbase compacted in accordance with

the plans and specifications. He explained that the additional four -inch depth was

determined as a result of the March 14, 2011 cutting and done to ensure that the

subbase after the application of the cement on March 14, 2011 properly dried out.

We also note that the settlement agreement does not express a dollar amount

as a part of the transaction and compromise between RPDE and McHugh. The

plain language of the agreement shows only that each party dismissed their
respective claims against the other. While Daton contends that RPDE "[ c] learly"

received a credit in the amount that McHugh demanded in its original petition,

nothing in the record supports such a supposition. Indeed, Mayeaux' s testimony
that he believed RPDE did not owe McHugh the amount it claimed belies Daton' s

contention. Accordingly, Daton was not entitled to an offset for the settlement.

Expert Witness Fees

The party cast in judgment will generally be assessed with all costs of the

litigation, including its own and those of the prevailing party. See La. C. C.P. art.
1920.
The trial court has great discretion in awarding costs, including expert

witness fees, deposition costs, exhibit costs, and related expenses. On appeal, the

trial court' s assessment of costs will not be disturbed absent an abuse of discretion.

Reynolds v. Louisiana Dep' t of Transp., 2015- 1304 ( La. App. 1 st Cir. 4113116),
194 So. 3d 56, 59.

The taxing of expert witness fees is governed by La. R.S. 13: 3666, which
provides:

A.
Witnesses called to testify in court only to an opinion
founded on special study or experience in any branch of science, or to
make scientific or professional examinations, and to state the results
thereof, shall receive additional compensation, to be fixed by the
court, with reference to the value of time employed and the degree of
learning or skill required.

15

B. The court shall determine the amount of the fees of said
expert witnesses which are to be taxed as costs to be paid by the party
cast in judgment either:

1) From the testimony of the expert relative to his time
rendered and the cost of his services adduced upon the trial of the
cause, outside the presence of the jury, the court shall determine the
amount thereof and include same.

2) By rule to show cause brought by the party in whose favor a
judgment is rendered against the party cast in judgment for the
purpose of determining the amount of the expert fees to be paid by the
party cast in judgment, which rule upon being made absolute by the
trial court shall from a part of the final judgment in the cause.

Expert witnesses are entitled to reasonable compensation for their time in

court and for preparatory work done. The trial court can fix expert witness fees

based upon its own observations and evidence presented at trial. However, a party

can only have taxed as court costs the reasonable cost of time spent by the expert

in gathering facts necessary for his testimony, but not for time spent in consultation

that only assists the attorney in preparation for the litigation. Reynolds, 194 So. 3d

at 60.

The trial court awarded $ 15, 288. 25 in fees and deposition costs related to

Quick' s expertise. On appeal, Daton complains that the invoices introduced at the

hearing show " an outrageous attempt by RPDE to recoup costs" that were not fully

related to the third -party claim. Additionally, Daton asserts that the invoices

included work conducted by persons other than Quick.

The trial court may award the full amount charged by an expert witness if

the amount is reasonable in light of the many factors considered in fixing expert

witness fees, such as time spent in preparatory work for trial, the extent and nature

of the work performed, the knowledge, attainments, and skill of the expert, and the

helpfulness of the expert' s report and opinion to the trial court. Generally, the

amount and fixing of expert fees lies within the sound discretion of the trial court

16

and will not be disturbed in the absence of an abuse of discretion. Fees of expert

witnesses may be reduced if expenses were needlessly or excessively incurred. Id.,
194 So. 3d at 61.

The record reveals no evidence that RPDE caused costs to be incurred

needlessly or pointlessly, but we are mindful of the incidental actions that initially

comprised this litigation. Importantly, it has long been the law that the assertion of

an attorney and the bill of an expert do not support an award for the total time of an

expert, both in court and outside of court. Rather, the expert must testify at the trial
of the contradictory rule to tax costs and be subject to cross- examination, unless

there is some stipulation between the parties. Id.

Here, the trial court raised the issue of the quantum of the costs originally
awarded in the March 8, 2018 final judgment by way of the March 29, 2018

judgment that it issued without a rule or a motion for new trial before it. This

action by the trial court gave rise to RPDE' s subsequent request for the inclusion

of the expert witness fees within the costs assessment raised by a new trial motion

that was timely as to the March 29, 2018 judgment but untimely as to the original

final judgment of March 8, 2019. RPDE did not present Quick as a witness at the

December 4, 2018 hearing on its motion for new trial; but Daton did not object to

the introduction of Quick' s itemized charges for his fee.

The mere assertions of RPDE' s attorney and the submitted invoices

representing the amount of fees that Quick charged RPDE are insufficient to

support the trial court' s award of out- of-court work costs of the expert witness. The

burden of proving the value of Quick' s out-of-court services was on RPDE, and

although RPDE submitted the expert' s invoices at the hearing, those invoices are

insufficient to establish the value of the services. The law requires a contradictory
and full hearing, with the burden of proving the reasonable value of the expert

17

witness' s out- of-court work on RPDE as the party seeking the costs. See Reynolds,

194 So. 3d at 61- 62.

Given the inadequacy in the record regarding the details of the fees charged

by Quick, we simply cannot detennine if the trial court' s judgment taxing those

costs to Daton was an appropriate exercise or an abuse of its discretion. Under

these circumstances, we vacate the trial court' s January 31, 2419 judgment that

awards RPDE expert witness fees and deposition costs in the amount of

15, 288. 25 and remand for stipulations or a contradictory hearing to determine

expert witness fees based on the trial court' s personal observations at the trial as

well as the parties' evidentiary support subject to cross- examination and the

criteria discussed herein.

DECREE

For these reasons, we maintain the appeal. The trial court' s March 8, 2018

judgment is affirmed. The trial court' s January 31, 2019 judgment is vacated and

we remand this matter for a hearing to determine the amount of expert witness fees

to which RPDE is entitled in accordance with this opinion. Appeal costs are

assessed in the amount of two-thirds against Daton Contracting, Inc. and one- third

against RPDE Development, LLC.

APPEAL MAINTAINED; MARCH 8, 2018 JUDGMENT AFFIRMED;

JANUARY 31, 2019 JUDGMENT VACATED; REMANDED WITH

INSTRUCTIONS.